Responses to Questions during Q A period

View the file

Other files

File Type Posted
SP700016R000202_-_SF30.pdf PDF
Attachment_2.pdf PDF
PERFORMANCE_WORK_STATEMENT_16-2.4_(Updated_6-21-2016).doc DOC document
SF_30_SP7000-16-R-0002_Amend_1.pdf PDF
Korea_PWS_UD.doc DOC document
Korea_PWS_Attachment_5.pdf PDF
Combined_Synopsis-Solicitation_SP7000-16-R-0002.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Question NumberDocument DescriptionPage #Section/ ParagraphQuestion/ CommentAnswer
1Provide English speaking service technician support Monday through Friday from 8:00 a.m. – 4:30 p.m. local time, except varying Federal or local Holidays.Attachment 5
PWS 4 page4.2Is it okay that we do not service on local Holiday (Korean Holiday)?

What about change it like current?

No Service on US Holiday Service on Korean Holiday

Because most of customers work on Korean Holiday and they need copier serviceNo change in the PWS
2No transformers will be used as an exception.Attachment 5
PWS 7 page9.1.4.9There is only 220v in Korea.
Please let us use transformers.No transformers will be allowed for safety reason. There's no guarantee that accidents will not happen.
3Equipment must be capable of a “secure print” function using identification (ID) and password identification number (PIN) to retrieve documents from the deviceAttachment 5
PWS 7 page9.1.4.18Does it mean when user print any document on the computer, the document should be queued on the copier or server, and print out when user log on the copier with their CAC card?Must be able to use identification (ID) and password identification number (PIN) to retrieve documents from the device
4The contractor must produce certificates of compliance if requested.
CAC authentication is required for the following capabilities: Scanning, Copying, PrintingAttachment 5
PWS 10 page11.2.3.1About scanning,

the copier should be locked always?

Should the user log on with cac card for scan function? Yes, copier should be locked always.

Yes, user log on with cac card for scanning, copying, printing, faxing

5The contractor must produce certificates of compliance if requested.
CAC authentication is required for the following capabilities: Scanning, Copying, PrintingAttachment 5
PWS 10 page11.2.3.1About copying,

the copier should be locked always?

Should the user log on with cac card for copy function? Yes, copier should be locked always.

Yes, user log on with cac card for scanning, copying, printing, faxing

6The contractor must produce certificates of compliance if requested.
CAC authentication is required for the following capabilities: Scanning, Copying, PrintingAttachment 5
PWS 10 page11.2.3.1About printing,

the copier should be locked always?

Should the user log on with cac card for print function?

Does it mean when user print any document on the computer, the document should be queued on the copier or server, and print out when user log on the copier with their CAC card?The CAC solution shall be able to protect: Scanning, Copying, and printing. If the customer requires CAC released print then the document should queue on the copier any jobs for that users should be queued when the user logs in.
7The contractor shall deliver the proposed MFDs for each VB series to DLA Document Services HQ, Bldg 9, NSA Mechanicsburg, Mechanicsburg, PA 17055, for testing, at no cost to the government.Attachment 5
PWS 11 pageTestingNetwork enviroment could be different between NSA and Korea.
What about have a CAC testing in Korea?Arrangements are underway to establish a test site in Korea.
8Provide to the designated DLA Document Services (COR) a quarterly usage report in electronic (Microsoft Office compatible version 2003 or newer) format on the total and average monthly production volumes by serial number for all devices.Attachment 5
PWS 4 page6.1If VB-1 bw copier user uses over than 5,000 copies per month, what happen?
Can I invoice the over charge? Or COR let them use VB-2 copier (bw : max 10,000 copies per month)?Vendors cannot bill if copiers exceed the allowance. It is important that such reports are submitted for us to monitor usages and notify the customers of the excessive usage.
9Provide a toll free telephone number(s) to place service maintenance calls and order consumable supplies.Attachment 5
PWS 2 page2.3Is the auto voice message possible during lunch?No voice message, must be able to respond quickly to meet the timeline for maintenance and supply delivery.
10Provide to the designated DLA Document Services (COR) a quarterly usage report in electronic (Microsoft Office compatible version 2003 or newer) format on the total and average monthly production volumes by serial number for all devices.Attachment 5
PWS 4 page6.1If VB-5 bw copier user uses over than 70,000 copies per month, what happen?
Can I invoice the over charge? Or COR let them install more copiers?Vendors cannot bill if copiers exceed the allowance. It is important that such reports are submitted for us to monitor usages and notify the customers of the excessive usage.
11Relocations shall be limited to a 50 mile radius from where the devices to be moved are located and shall not require rigging or special handling.Attachment 5
PWS 5 page8.1If it is over 50 mile, can I request relocation fee and move the copier? Or the copier cannot be moved over 50 mile?
If I can request the relocation fee, what is the fee per mile that I can request?Relocation fee may be imposed for moves over 50 miles, the cost is up to the vendor but must be reasonable
12Provide relocations aggregating to an amount equal to the total number of devices under contract for each year of the contract.Attachment 5
PWS 5 page8.1For example,
I installed the copier in NY, but several months later, I found it in DC. That means user moved the copier themselves. What happen?The users are not allowed to move the device. They must submit a relocation request to the COR, which then will submit to the vendor for action. The vendors should not relocate without written approval from the COR
13Provide relocations aggregating to an amount equal to the total number of devices under contract for each year of the contract.Attachment 5
PWS 5 page8.1If the copier is broken while the customer is moving it, Can I request the reimbursement?same as above. Customer pays if the damage is caused by the government.
14Equipment must be capable of operating using standard U.S. office 110/220 volt 15 amp 60 Hz AC electrical current or U.S. office 110/220 volt 20 amp 60 Hz AC electrical current. No transformers will be used as an exception. In the event the later (20 amp) is offered, the Contractor will clearly identify these models in proposals and in all price lists.Amended PWS Page 79.1.4.9Do MFDs must be capable of operating in not only 110 volt but also 220 volt ?

Recommendation: Please allow vendor use transformer (110V to 220V) for operating or requests the deletion of mandory comment for 220V

No transformers will be allowed for safety reasons. This paragraph will not be deleted nor amended to remove 220V.
15Feeds from at least two (2) adjustable paper trays 500 sheet minimum and (1) one bypass tray with 100 sheet minimum.PWS Page 79.3.5Do MFDS must be capable of bypass tray with 100 sheet minimumYes, the MFDs must have a 100 sheet minimum bypass tray
16Feeds from at least four (4) adjustable paper trays 500 sheet minimum and (1) one bypass tray with 100 sheet minimum.PWS Page 89.4.1Do MFDS must be capable of bypass tray with 100 sheet minimumYes, the MFDs must have a 100 sheet minimum bypass tray
17Feeds from at least four (2) adjustable paper trays 500 sheet minimum (1) one bypass tray with 100 sheet minimum and a high capacity tray with a 2000 sheet minimum.PWS Page 89.45.1Do MFDS must be capable of bypass tray with 100 sheet minimumYes, the MFDs must have a 100 sheet minimum bypass tray

Sheet2