Q and A Matrix_DSCR HVAC Packaging Unit Replacement.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
Defense Supply Center Of Richmond (DSCR) HVAC Packaging Unit Replacement
Solicitation number
SP4703-26-Q-0043
Issued by

About this file

This is a Questions and Answers (Q&A) Matrix document for solicitation SP4703-26-Q-0043, the Defense Supply Center of Richmond (DSCR) HVAC Packaging Unit Replacement project. The matrix addresses nine key inquiries from prospective contractors regarding the scope and technical requirements of replacing a 20-ton indoor package unit with a heat pump system. Critical clarifications include: the existing Honeywell control system will be maintained by the installation; all available building diagrams will be provided post-award; temporary heating and cooling are required as the space remains occupied during replacement; existing refrigerant piping may be reused if in good condition; no economizer or mixing box is needed; and the contractor must determine the appropriate electric heat kit size and confirm it via submittal. Concrete repair photos referenced in the Statement of Work have been uploaded to SAM.gov, and the contractor retains responsibility for determining whether additional engineering details are necessary to complete the scope of work.

View the file

Other files

File Type Posted
Photo-1.jpg JPG image
Photo-3.jpg JPG image
Photo-2.jpg JPG image
WD.pdf PDF
SF1449_SP470326Q0043(Final).pdf PDF
DSCR-B66C-SOW-PackageUnit.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SP4703-26-Q-0043 HVAC Packaging Unit Replacement Q/A Matrix#QuestionAnswer
1Who currently maintains the controls for this building?The installation maintains the contorols, Honeywell control system.
2Can you provide the building’s electrical, mechanical, and controls plans?All avaliable diagrams will be provided to the contractor post-award.
3Will temporary heating and cooling be required during the replacement?This is an occupided space so, yes.
4Is the existing refrigerant piping to be reused for the new installation?Refrigerant lines may be reused as long as theyre in good condition
5Is the bid intended for a heat pump installation only, without the use of steam?Heat pump and Packaged Air Handling unit, no steam.
6Can you provide pictures of the concrete that requires repair as outlined in the SOW?Photos have been added as attachments to the solicitation in SAM.gov
7I wanted to confirm we are doing a heat pump as the replacement?Yes
8What size of electric heat do we need to use (if any)?Contractor is to determine appropriate sized heat kit for the unit they intend to use, confirm via submittal.
9Do we need an economizer/mixing box?No economizer needed.