The file is a Q&A Matrix for Solicitation SP470326Q0013, a Department of Defense (Defense Logistics Agency) contract opportunity for ADA touchless door operator installation at Building 46. The solicitation is a Request for Quote (RFQ) set aside for 100% small businesses, with an estimated contract value between $20,000 and $50,000, and a 75-day performance period.

Key details include a site visit held on 01/08/2026, a question deadline of 01/12/2026, and a quote submission deadline extended to 01/20/2026. The Q&A matrix reveals specific technical questions about door operator installation, including confirmation of existing equipment replacement, push button quantities (28 4.5-inch and 4 narrow/slim), and clarification on wiring and power supply installation. The contract will be awarded to the Lowest Priced Technically Acceptable offeror, with work to be performed in Chesterfield County, VA, under NAICS Code 236220 for Repair or Alteration of Office Buildings.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionFileSectionQuestionGovernment ResponseResponse from:
1SOW Building 46 ADA Touchless Operator Install_Rev1.pdf3. SPECIFIC REQUIREMENTSCan you please confirm whether the existing door operators are to be replaced or if they are to remain and be reused?Please refer to file and section listed in blocks B2 & C2Contracting Officer
2SF30 SP470326Q00130001.pdfPage 3; Additional InformationOf the total push buttons shown, how many are 4.5-inch push buttons and how many are narrow-size push buttons?28 are 4.5" and 4 are narrow/slim size.Project Manager
3SOW Building 46 ADA Touchless Operator Install_Rev1.pdf4. CONTRACTOR QUALIFICATIONSDo you have any information regarding the quantity or condition of the existing wiring for the door operators and push buttons?Such detailed knowledge is expected from contractors meeting the qualification requirements.Contracting Officer
4SOW Building 46 ADA Touchless Operator Install_Rev1.pdf3. SPECIFIC REQUIREMENTSCan we install new power supplies and pull/run additional wiring (4 conductors) from the power supply to each touchless wave sensor location to provide required power and control functionality? This is cost impactThe contractor shall install all necessary material, equipment etc. to ensure the push button operators can be changed to touchless.Project Manager
5SOW Building 46 ADA Touchless Operator Install_Rev1.pdf3. SPECIFIC REQUIREMENTSIf additional wiring, power supplies, and associated wall/ceiling access are required, please confirm whether this work is considered within the current scope or the scope of work will the SOWS be modifiedIt is considered within the scope as the SOW is currently written.Contracting Officer
6
7
8
9
10