Sheet1

ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19718SHEET1OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCLIN-0001ESTIMATOR
Building and/or Description: Installation of removable bollards at James Road ACPCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL COST
OVERHEAD
PROFIT
BOND
TOTAL COST
ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19719SHEET2OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCLIN-0002ESTIMATOR
Building and/or Description: Installation of Knox Boxes & KeySecure 5 Units, center wide.CHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL COST
OVERHEAD
PROFIT
BOND
TOTAL COST
ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19719SHEET3OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCLIN-0003ESTIMATOR
Building and/or Description: Installation of Traffic Control Arms at the James Road ACP POV LanesCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL COST
OVERHEAD
PROFIT
BOND
TOTAL COST
ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19719SHEET4OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCLIN-0004ESTIMATOR
Building and/or Description: Installation of Cameras at Substation of the Yearling Road ACPCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL COST
OVERHEAD
PROFIT
BOND
TOTAL COST
ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19719SHEET5OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCLIN-0005ESTIMATOR
Building and/or Description: Installation of Protective Walls for ACP FD Control Box at the Yearling Road ACPCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL COST
OVERHEAD
PROFIT
BOND
TOTAL COST
ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19719SHEET6OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCLIN-0006ESTIMATOR
Building and/or Description: Installation of Cameras in Building 17CHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL COST
OVERHEAD
PROFIT
BOND
TOTAL COST
ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19719SHEET7OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCLIN-0007ESTIMATOR
Building and/or Description: Installation of Digital Signs at Both ACPsCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL COST
OVERHEAD
PROFIT
BOND
TOTAL COST
ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19719SHEET8OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCLIN-0008ESTIMATOR
Building and/or Description: Installation of Shrubs & Trees at Bldg.22 for Vission BarriersCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL COST
OVERHEAD
PROFIT
BOND
TOTAL COST
ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19719SHEET8OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCLIN-0009ESTIMATOR
Building and/or Description: Installation of Shrubs & Trees at Bldg.23 for Vission BarriersCHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMSUB CONTRACT COSTPRIME CONTRACT COSTTOTAL DIRECT COST
No. / Div.DescriptionQTY.Unit
1General Requirements1LS
2Existing Conditions1LS
3Concrete1LS
4Masonry1LS
5Metals1LS
6Wood, Plastics, and Composites1LS
7Thermal and Moisture Protection1LS
8Openings1LS
9Finishes1LS
10Specialties1LS
11Equipment1LS
12Furnishings1LS
13Special Construction1LS
14Conveying Equipment1LS
21Fire Suppression1LS
22Plumbing1LS
23Heating, Ventilating, and Air Conditioning1LS
26Electrical1LS
27Communications1LS
28Electronic Safety and Security1LS
31Earthwork1LS
32Exterior Improvements1LS
33Utilities1LS
34Transportation1LS
SUB-TOTAL COST
OVERHEAD
PROFIT
BOND
TOTAL COST
ENGINEER'S COST ESTIMATE (FOUO)
PROJECTCSC-19719SHEET9OF9
Project Title: Security Enhancements, FY19DATE PREPARED
LOCATIONCOST SUMMARYESTIMATOR
CHECKED BY
NARRATIVE / DATA SOURCE[EDIT AS NEEDED] Estimate was developed using RSMeans Online. Detailed cost breakdowns for labor, material, and equipment are available upon request.
BID ITEMTOTAL COST FOR CLIN ITEM (from BID FORMS)
CLIN NODescriptionQTY.Unit
1: Installation of removable bollards at James Road ACP1LS
2Installation of Knox Boxes & KeySecure 5 Units, center wide.1LS
3Installation of Traffic Control Arms at the James Road ACP POV Lanes1LS
4Installation of Cameras at Substation of the Yearling Road ACP1LS
5Installation of Protective Walls for ACP FD Control Box at the Yearling Road ACP1LS
6Installation of Cameras in Building 171LS
7Installation of Digital Signs at Both ACPs1LS
8Installation of Shrubs & Trees at Bldg.22 for Vission Barriers1LS
9Installation of Shrubs & Trees at Bldg.23 for Vission Barriers1LS

SUB-TOTAL COST

TOTAL COST FOR THIS PROJECT