Question & Answers Project CSC-18719 M & R to Building 20, FY18 Solicitation SP4702-18-R-0529
1. What Bids sheet need to fill out and turned in?
Answer: An Amendment will be sent out with new Bid Sheets: Division No sections 2 pages on original bid sheets, and 1 page on revised bid sheets. Also need Section B filled out.
Reply: Contractor shall use new revised bid sheet (attached) and still fill-out Section B.
1. Are we are replacing the entire drain assembly to the piping connection? If so, why are we replacing the entire drain?
Reply: No. Contractor shall replace strainers, threaded pipe flange connector mouth pieces, flashing clamps, metal flashings set on finished roofing membranes in mastic, prime top surface before stripping as specified in the paragraph 3.1.19 of Section 07 60 00.
3. Is all the piping cast iron no hub?
Reply: Yes.
4. Can we Value engineer a solution that maintains the manufactures warranty?
Reply: Yes.
5. The existing overflow drains and scuppers are located approximately 6-8 inches from the parapet wall. The drawings call for them to be approximately 5 feet from the wall. Are we replacing the existing in the existing location or are we removing and installing at the new location?
Reply: Replace the existing overflow drains & scuppers at the existing locations only.
6. Please confirm that if are to work in offices all furniture will be moved by others.
Reply: Yes.