Amendment 7.pdf

PDF 266 KB Posted

Attached to
Industrial Waste Removal, Transportation and Disposal from DRMO Bupyong, Korea
Solicitation number
SP4530-10-R-0001
Issued by

About this file

Amendment 0007

View the file

Other files

File Type Posted
Amendment 6.pdf PDF
Amendment 5.pdf PDF
Amendment 4.pdf PDF
Amendment 3.pdf PDF
Amendment 2.pdf PDF
Amendment 1.pdf PDF
10-R-01 IW Korea.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

AMENDMENT/MODIFICATION NO.

PAGE OF PAGES

3. 4.

NAME AND ADDRESS OF CONTRACTOR (No. street, city, county, State and ZIP Code)

A.

NSN 7540 - 01 - 152 - 8070

PREVIOUS EDITION UNUSABLE STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

1.

2.

7.

CONTRACT ID CODE

EFFECTIVE DATE REQUISITION / PURCHASE REQ. NO. 5.

CODE ADMINISTERED BY (If other than Item 6)6. CODE

CODE FACILITY CODE

8. AMENDMENT OF SOLICITATION NO.9A.

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

12. ACCOUNTING AND APPROPRIATION DATA (If required)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

(X)

(X)

CONTRACTOR/OFFEROR 15C. DATE SIGNED 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

FAR (48 CFR) 53.243

PROJECT NO. (If applicable)

ISSUED BY

DATED (SEE ITEM 11)9B.

MODIFICATION OF CONTRACT/ORDER NO.10A.

DATED (SEE ITEM I3)10B.

is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or

(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. 16B. UNITED STATES OF AMERICA

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

PAGE OF PAGES

NSN 7540 - 01 - 152 - 8070

PREVIOUS EDITION UNUSABLE STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

1.

CONTINUATION PAGE

CONTRACT ID CODE

FAR (48 CFR) 53.243

Amendment 0007 dated 14 January 2010 Questions and Responses to RFP SP4530‐10‐R‐0001

Question and

Response No. Question/Comment Submitted Response 1 Are these containers to be use for containing Industrial Waste we are quoting on?

Yes.

2 Is it going to be use for other than I W we are quoting on? No.

3 How many days to require to filling these containers? Industrial Waste (IW) to be removed when requested by the Government.

4 Do you want separate quote for utilizing these containers or Joint quote with

IW?

No ‐ containers will be part of the contract , not a separate quote/Contract Line Item (CLIN).

5 Our company normally uses the incineration facility of the subcontractor with a waste intermediate disposal license including incineration permit. Is it possible for our company with a subcontractor to offer for the subject solicitation?

No ‐ paragraph 3 of the Performance Work Statement (PWS) states contractor shall have its own incineration facility.

ContrCd:
Of: 3
Pg: 1
AmendNo: 0007
EffDt: 14 JANUARY 2010
PONo:
ProjNo:
Issuer: Defense Reutilization & Marketing Service- DRMS J-762

1025 Quincy Avenue, Suite 2000 Pearl Harbor, HI 96860-4512 lisa.roth@dla.mil

IssueCd: SP4530
Admin:
AdminCd:
VendNm:
VendOffAdd:
VendCd:
FacilCd:
Solicit: X
SolicitNo: SP4530-10-R-0001
SolicitDt: 02 DECEMBER 2009
Contr:
ContrNo:
ContrDt:
Amend: X
ExtendY:
ExtendN: X
Copies:
AcctData:
Chg:
ChgS:
AdminChg:
AdminChgS:
Auth:
AuthS:
Oth:
OthS:
ContrSignY:
ContrSignN:
ContrCopy:
Desc: RFP No. SP4530-10-R-0001, Transportation, Removal & Disposal of Industrial Waste generated at DRMO Bupyong and its surrounding locations, Korea.

SEE PAGES 2 AND 3.

SignerNm:
SignerTtl:
ContrOffNm:
Header:
Footer:
Pg2: 2
Contd2: RFP No. SP4530-10-R-0001, Transportation, Removal & Disposal of Industrial Waste generated at DRMO Bupyong and its surrounding locations, Korea.

1. Contractor questions (numbered 1 through 5) and Government responses are provided.

2. The proposal submission due date and time remain unchanged at 19 January 2010, 1600 Hawaii Standard Time.