San_Diego_racking_SOW_-_phase_2_Attachment_1.doc
DOC document 82 KB Posted
- Attached to
- Purchase and Installation of Storage Racks
- Solicitation number
- SP4510-15-Q-0004
About this file
Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF1449_continuation_pages__Attachment_2.pdf | ||
| San_Diego_-_new_warehouse_-_phase_2_plan_Attachment_4.pptx | PPTX presentation | |
| SF1449_Storage_Racks_Attachment_3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DLA Disposition Services – San Diego Naval Base Racking Procurement and Installation Statement of Work (SOW)
1.0 INTRODUCTION
The primary mission of the Defense Logistics Agency (DLA), Installation Support is to directly provide services for Disposition Services. Disposition Services function is to dispose of Department of Defense (DoD) excess and surplus personal property generated by the military services. This is accomplished through reutilization to other DoD activities, transfer to other Federal agencies, donation to authorized state and local organizations, sale to the general public, or ultimate disposal through abandonment or destruction. DLA Disposition Services and Installation Support is headquartered in Battle Creek, Michigan, with a variety of field sites worldwide. The purpose of this contract is to acquire new industrial storage racks and various equipment at the DLA Disposition Services – San Diego, CA.
By way of Request for Quote, is soliciting Offeror quote to purchase new fixed-height/selective pallet racks, dismantle all of the old racks, install new storage racks at the DLA Disposition Services-San Diego. This procurement service is funded through DLA Installation Support (DODAAC SC4400). DLA Installation Support’s COR will certify the invoice submitted through the Wide Area Work Flow (WAWF) system; the post-contract identified COR will verify the order is properly received and installed IAW specifications.
The contractor shall coordinate to travel to the DLA Disposition Services-San Diego site to confirm/alter the design concept as required. The Site Manager will make the final design approval(s) and can anticipate slight in-process design alterations to meet their requirements.
DLA Disposition Services-San Diego requires a 24 hour notification for all visitors. Completion date for CLINs 0001 is 90 days after award of this contract.
2.0. Common to all fixed height rack installations:
Critical requirements for fixed height locations are as follows:
1.) 16’ tall x 48” deep vertical columns with 108” long horizontal load beams. All horizontal load beams shall have a combined minimum rated capacity between 5500 and 6000 lbs. All pallet spaces shall have wire mesh decking as listed below. Install the three levels of horizontal load beams to support between 52 inches and 56 inches of available pallet height space; ie 52 inches above the floor, then between 108” and 110” above the floor, etc. All 16’ tall vertical columns shall have a minimum 23,000 lbs load capacity.
2.) All horizontal load beams are to either receive solid coats of paint on every surface and then oven baked or galvanize dipped to support corrosion resistance.
3.) Bolted frames are either electro-statically immersed in epoxy paint or galvanized to ensure that the coating saturates every surface and provides enhanced corrosion resistance in humid climates and chemical storage environments.
4.) Over the beam or commonly referred as “waterfall-type” wire mesh decking that’s 48” deep x 52” wide, 2 ½” x 4” mesh spacing size, and has a capacity between 2500-3000 lbs each with four support channels each. Wire mesh decking shall be installed in lieu of pallet supports.
5.) 24” tall column protectors that attach only to the floor specifically designed to fit with the seismic compliant columns and base plates (a decision to attach to columns only with DLA’s Industrial Engineer’s prior authorization).
6.) Each individual vertical column and horizontal load beams must be permanently marked, preferably stamped, a welded, bolted, or riveted metal data plate or an industrial strength sticker is also acceptable. The key information to be marked on each component is the manufacture’s brand name, replacement part number recognized by the manufacturer, and horizontal beam’s load capacity. This identification will support ease in component replacement (vs. entire rack replacement). An acceptable sticker will be a 2” x 4” label using two permanent enamel based inks (white and black) subsurface printed on 10 mil industrial Lexan, backed with 3M 468 permanent adhesive (an example business who demonstrated to meet these specifications is Specialty Printing Inc. in St. Louis, MO).
3.0 Install new fixed height racking in buildings 3655 – Contract Line Item (CLIN) 0001.
All material and equipment shall be delivered to: DLA Disposition Services, building 3655, 3655 Cummings Road, San Diego Naval Base, CA, 92136-5605
3.1 Row Configurations and Pallet Quantities
A. Building 3655 is approximately 100’ long x 50’ wide and has existing rows of racks manufactured by Interlake and painted reddish/orange. This new racking project will require an approximate 80 new pallet spaces between two (2) rows.
- Two (2) rows that are approximately 43 feet long (four 9’ sections long).
- Rows will follow the layout in accordance with (IAW) exhibit A.
- Rows will be installed a minimum 12” away from all wall; see exhibit A for clarification.
- The two rows will use 6” row spacers; each column shall utilize a row spacer.
- The contractor shall purchase and install six (6) 6” long row spacers for these rows (one/column).
- The contractor shall purchase and install one hundred seventy five (175) wire mesh decks as described in section 2.0 above. The contractor shall replace the entire warehouses pallet supports with these wire mesh decks.
3.2 Column and End of Aisle Protectors
- The racking system shall include individual column protective devices that have a corrosion resistant coating applied to each to mitigate the environmental conditions (heat, humidity, and chemicals).
- The contractor shall purchase and install approximately eight (8) 24” tall column protectors that attach only to the floor specifically designed to fit with the seismic compliant columns and base plates. It is the contractor’s responsibility to ensure that all vertical columns exposed to the aisles have a column protector installed and utilize all the manufacturer’s bolt holes utilized to fasten to the concrete floor (regardless of model selected).
- Each vertical column will have a protective device (i.e. corner or column guard); these are in addition to columns with end of aisles guards.
The contractor shall install all column protectors to the concrete floor using the manufacture’s recommended bolts. Additional clarification on anchor bolts are listed in the Installation section below.
- The contractor shall purchase and install one (1) heavy duty end of aisle protector shall be installed between 3” to 6” away from racks, be a minimum of 6” tall, extend the width of the two columns (approximately 102” long), and fastened to the concrete floor as specified IAW the manufacturer’s instructions or comply with “Installation” section below.
4. Installation
- The Contractor shall coordinate with DLA Disposition Services – San Diego to conduct a pre-installation meeting with the Area and/or Site Manager. The contractor is to verify the shipping address and set up pre-installation meeting date, time, and location with the Site Manager. Contact information will be provided upon request.
- DLA Disposition Services – San Diego is in seismic zone 4 (zip code 92136-5605). Calculations support ordering/manufacturing a non-standard 5” x 7” x ¾” thick foot plate on each column in order to better distribute the loads.
- The contractor shall be prepared to adjust rack height spacing listed (as needed) in order to meet any requests from the Site Manager.
- New pallet racking shall be installed per manufacturer’s recommendation and a copy of the manufacturer’s specifications will be provided to the Site Manager for quality assurance/quality compliance.
- The contractor shall install all rack columns, column guards, end of aisle guards by anchoring down to the concrete floor as described by the manufacturer’s installation specifications using the their recommended bolts. If/when anchor bolts are not specified in the manufacturer’s installation specifications, anticipate installing a total of two (2) ½” diameter, grade 5 or better, wedge anchor bolts per column section into the concrete (one per leg); also anticipate placing the anchor bolts 2 ½” below the surface. Wedge anchors (with nuts) shall have 360-degree contact with the base material and torqued down IAW manufactures specifications. Each hole must be drilled into the concrete equal to the diameter of the anchor. Ideally the hole is drilled using a hammer drill that is set in the hammer and rotation mode, and using carbide tipped bits that meets ANSI standards. The tolerance between the hole diameter and anchor diameter is critical; using an ANSI standard bit insures the hole size. After the hole is drilled, it is important that the hole is cleaned out using a wire brush, vacuum or compressed air. The depth of the hole should be a minimum of 1/2” deeper than the anchor bolt which allows room for any dust and debris to fall into during the installation process. Most anchor bolts don’t use the bottom of the hole to be set, so the hole can be any depth as long as it is deep enough to insure that the anchor is embedded after expansion to minimum embedment depth for the diameter being installed. Oversized holes will not be required pending screw anchor type selected for installation. Fasteners shall be manufactured from carbon steel, and are heat-treated. Anchors are not to be reused after initial installation. An example acceptable wedge anchor is Hilti’s Kwik-Bolt 3 or screw anchors such as the Titen HD® anchors from Simpson Strong-Tie (provided installation follows Simpson’s Strong-Tie instructions for the Titen HD anchor) or equal. If inadequate anchor bolt binding occurs the contractor will be required to fix with an epoxy filler designed for threaded applications to ensure a solid contact with the concrete.
- Contractor shall anticipate purchasing manufactured shims to ensure a level installation IAW RMI standards under paragraph 7.1.4 as listed below:
· Shims may be used under the base plate to maintain the plumbness and/or levelness of the storage rack. The shims shall be made of a material that meets or exceeds the design bearing strength (LRFD) or allowable bearing strength (ASD) of the floor. The shim size and location under the base plate shall be equal to or greater than the required base plate size and location.
· In no case shall the total thickness of a shim stack under a base plate exceed six times the diameter of the largest anchor bolt used in that base.
· Shims stacks having a total thickness greater than two and less than or equal to six times the anchor bolt diameter under bases with only one anchor bolt shall be interlocked or welded together in a fashion that is capable of transferring all the shear forces at the base.
· Shims stacks having a total thickness of less than or equal to two times the anchor bolt diameter need not be interlocked or welded together.
· Bending in the anchor associated with shims or grout under the base plate shall be taken into account in the design of anchor bolts.
- The contractor will work incrementally by dismantling/installing in sections approved by the site manager to mitigate work loss.
- All work will be accomplished in accordance with the ANSI MH16.1: 2012 edition.
Clean Up Premises Upon completion of the work, the contractor is required to clean up work space and remove and dispose of any parts or debris resulting from the contractor’s performance, with any associated costs included in existing CLIN prices. This is required after each day of on-site performance, and before the contractor leaves the premises.
Schedule
DLA Disposition Services on San Diego Naval Base requires a 24 hour notification for all visitors. Contract completion is required 60 days after award of this contract. The contractor must provide at least 14 calendar days advance notice to the Site POC before rendering services at the site.
Coordinate with DLA Disposition Services – San Diego for entry and scheduling daily work hours. Any overtime/weekend work must be coordinated with DLA Disposition Services – San Diego for advanced approval.
The service to be performed under this contract will be performed during normal government working days, Monday through Friday, which are available from the COR/POC. If services are scheduled by the contractor to be performed on a regular federal holiday (see below), designated by Presidential proclamation, or DLA, Disposition Services closure, rescheduling shall be at the discretion of the POC.
New Years Day
1 January*
Martin Luther King's Birthday
3rd Monday in January
Presidents Day
3rd Monday in February
Memorial Day
Last Monday in May
Independence Day
4 July*
Labor Day
1st Monday in September
Columbus Day
2nd Monday in October
Veterans Day
11 November*
Thanksgiving Day
4th Thursday in November
Christmas Day
25 December*
* The holiday is observed on the preceding Friday or the following Monday when the holiday occurs on Saturday or Sunday, respectively.
Contractor furnished property and services Unless otherwise noted elsewhere as Government furnished, the contractor shall provide all labor and materials to perform all necessary work.
Contractor shall:
· Supply any needed parts/hardware not included in new racking supply.
· Supply adequate supply of floor anchor bolts for the new pallet racking and corner protectors.
· Supply shims for leveling uprights.
· Coordinate with site for use of municipal utilities and shelter. However, contractor shall plan accordingly and be prepared to provide necessary assets to complete this project with little to no assistance from the site/end customer.
· All physical labor support to unload installation materials upon receiving shipment. Anticipate no support from the site.
· Provide Scissors lift (as needed) with appropriate safety harness/equipment, as needed.
· Provide forklift (as needed) for use of installation of racking.
Government furnished property and services The Government will be responsible for providing an area for the contractor to perform the required tasks. Electrical power, water, and facilities that are necessary to perform the required tasks will be available to the contractor, but all hand tools, Material Handling Equipment (MHE), and other task specific equipment are to be provided by the contractor.
Acceptance/correction of work
All work performed under this contract shall be subject to the acceptance of the designated Government Point of Contact. If performance is found to be unsatisfactory and not in accordance with the requirements of this contract, the contractor shall correct unsatisfactory work as soon as possible but not later than within 90 calendar days of Government notification. Correction of work is performed at the contractor’s expense as per FAR 52.212-4.
Contract Manager
The contractor shall be solely responsible for the overall performance of the contract. The contractor shall designate a contract manager and alternate contract manager, who will have full authority to act for and make binding contractual decisions on behalf of the contractor. Within five (5) days after contract award, the contractor shall provide the name of the primary and alternate contract managers in writing. The contract manager or the alternate shall be available during normal operating hours to meet with Government personnel. The contract manager and the alternate must be able to speak, read, write and understand the English language.
Protection to Public and Property
In order to provide for environmental abatement and control and to prevent environmental pollution arising from the services of the contractor in the performance of this contract, the contractor shall comply with applicable federal, state and local laws and regulations concerning environmental pollution abatement and control currently in effect and all applicable DLA, Disposition Services Fire, Safety, Security and Environmental Protection Regulations.
The Contractor must perform all operations in a prudent, conscientious, safe and professional manner. At a minimum, the Contractor’s personnel and equipment shall comply with applicable federal, DoD, state, local and host installation laws, safety regulations and procedures, and Contractor will ensure that its agents, employees, and subcontractors perform in a safe manner. The contractor shall ensure that its agents, employees and subcontractors involved in handling and packaging wastes are trained to the level of expertise required for the proper performance of the tasks and in particular, in the areas of chemical compatibility, safety, general first aid procedures and spills. Personal protective equipment shall be provided by the Contractor and must be appropriate for the task. The Contractor agrees that his personnel and equipment are subject to safety inspections by Government personnel while on Host Installation Property.
The Contractor shall assume full responsibility and liability for compliance with all applicable local, state federal, and DoD regulations pertaining to the health and safety of personnel and environmental management during the execution of work. All work shall be completed and performed in accordance with the best practices of the trade and in compliance with all-applicable federal, DoD, state and local codes.
The contractor shall take all necessary precautions to prevent injury to the public, building occupants, and/or damage to property of others.
Installation/Site access security requirements
Installation/site access requirements vary for visitor badges and other access/security procedures for performing contractor services at the sites. The contractor is required to coordinate with the Government COR/POC on the task order to obtain the necessary security/access procedures prior to commencing work at the site, and in such time as the performance timeframe for completion of the services is met. If coordination and/or access is delayed by the Government such that performance timeframes cannot be met, the contractor must submit, in writing, their proposed reasons, including any supporting evidence, prior to the original due date of the task order such that an extension can be granted, if appropriate. At no cost to the government, It is the contractor’s responsibility to make arrangements to conduct site visit prior to submitting an accurate and complete bid. The government is not responsible for incomplete material or condition list and expects the final installation to be complete and fully usable IAW RMI standards.
Identification of Employees
The contractor shall be responsible for furnishing to each of their employees’ identification as may be required by the installation where the services are performed. Contractor will require each of their employees engaged on the work site to display such identification as directed by the appropriate installation. All prescribed identification shall be delivered to the COR/POC for cancellation upon the release of any employee. Badges are issued for a period of one year and must be returned to the issuing pass office prior to renewal. Failure to return badges may constitute a delay in payment.
Conduct of personnel on duty
While on duty working in Government buildings and on Government property, personnel employed by the contractor shall be prohibited from sleeping, using Government telephones and utilizing Government facilities for recreational activities. Personal items in office areas, such as desk accessories, radios, supplies, pens, pencils, plants and food shall not be disturbed by the contractor’s employees at any time. Contractor’s employees are subject to Government standards of conduct including sexual harassment. Clothing, personal grooming, and personal cleanliness standards for Government working environment apply.
Standards of conduct
All personnel employed by the contractor in the performance of this contract or any representative of the contractor entering DLA Disposition Services compound/facilities, shall obey all regulations of the installation and will be subject to surveillance to ensure that no violations occur. The contractor shall be responsible for maintaining satisfactory standards of employee competency and conduct and taking such disciplinary actions with respect to contractor employees as may be necessary. The contractor shall ensure that all personnel employed in the performance of this contract shall be United States citizens; or non-United States citizens who legally reside in the United States. No contractor employee will be permitted on DLA Disposition Services sites when investigation reveals employee’s presence would be detrimental to the security of the installation or to the accomplishment of the work prescribed. The Government reserves the right to refuse to permit any contractor employee to perform services under this contract who is not in compliance with requirements of this contract (for example, employees not meeting stated minimum qualifications). In such cases, the KO/COR will advise the contractor of the reason for requesting an employee’s removal or withdrawal of authorization to enter DLA Disposition Services sites.
Disorderly conduct
Disorderly conduct, such as use of abusive or offensive language, quarreling, intimidation by works or actions, or fighting will not be condoned. Contractor employees shall not participate in disruptive activities which interfere with normal and efficient Government operations.
Intoxicants
The contractor shall not allow any employees, while on DLA Disposition Services sites to possess, sell, consume, or be under the influence of intoxicants, illicit drugs, or any other incapacitating agent which produces similar effects. The KO/COR shall require the contractor to remove from the job site, any contractor employee found under the influence of intoxicants, illicit drugs, or incapacitating agent during his tour of duty.
Criminal Actions
Contractor employees shall be subject to prosecution for criminal actions. These shall include, but are not limited to, the following:
Falsification, unlawful concealment, removal, mutilation, or destruction of any official documents or records, or concealment of material facts by willful omission from official documents or records.
Theft, vandalism, immoral conduct, or unauthorized use of Government property.
Unethical or improper use of official authority or credentials.
Misuse of weapons, including possession of weapons on the DLA Disposition Services premises.
Violations of State laws, such as traffic offenses, which have been assimilated and are enforced through the U.S. Magistrate Court System.
The contractor’s employees shall be on DLA Disposition Services premises only for contractual duties and not for other non-contractual purposes.
Personal Protective Equipment (PPE)
The contractor shall be responsible for equipping their personnel with the proper PPE required to safely provide services required. PPE is defined as equipment and supplies to protect the human body, inside and out, from harm / injury / illness occurring in line with contracted services provided. PPE may include, but is not limited to: Goggles, ANSI approved Safety Toe Boots, Leather Gloves, Hearing Protection, Face Masks (dust).