AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 | 2 h //2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
12/10/2012
4. REQUISITION/PURCHASE REQ. NO.
SP4500-13-R-0003
5. PROJECT NO. (If applicable)
N/A
6. ISSUED BY CODE SP4500 7. ADMINISTERED BY (If other than Item 6) CODE SP4500
DLA Disposition Services 74 Washington Avenue North Battle Creek, MI 49017
ATTN: DAN SCHUEMANN/DRMS-J 763
PHONE - (269) 961-5238 FAX: (269) 961-7115
EMAIL: daniel.schuemann@dla.mil
8. NAME AND ADDRESS OF CONTRACTOR (NO., street,city,county,State,and ZIP Code)
X
9a. AMENDMENT OF SOLICITATION NO.
SP4500-13-R-0003
9b. DATED (SEE ITEM 11)
11/06/2012
10a. MODIFICATION OF CONTRACT/ORDER NO.
10b. DATED (SEE ITEM 13)
CODE: FACILITY CODE:
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[ X ] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ ] is extended, [ X ] is not extended
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor [ ] is not, [ X ] is required to sign this document and return __1 _ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
SEE PAGE 2
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME OF CONTRACTING OFFICER
Daniel Schuemann
15B. NAME OF CONTRACTOR/OFFEROR
BY
(Signature of person authorized to sign)
15C.DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C.DATE SIGNED
NSN 7540-01-152-9070 – Electronically Reproduced PerFORM (DLA) STANDARD FORM 30 (REV. 1083) PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 CFR) 53.243
SP4500-13-R-0003
Amendment No. 0003
1. The purpose of this amendment is to answer offeror questions:
Q: If CLIN 6502EA is the replacement in this RFP for CLIN6999ww listed in the previous contract, how can bidder qualify a financial value where the quantity is ZERO? Also, if a bidder leaves this quantity at ZERO, will billing during the contract period for this item be affected?
CLIN 6502EA is a time and material type line that will have a “not to exceed” amount of 10% of the contract. No amount should be entered in the bid schedule.
Q: Is the above CLIN used to bill for time and material spent on post? (ie: drum movement, tote draining, etc.)
Correct
Q: Are transportation values (off post) to be included in the waste disposal rates?
All costs should be included in the waste disposal rates.
Q: What is the date that the current contract ends?
The current contract expires on February 3rd, 2013. There will most likely be an extension to the current contract.
Q: If awarded, is there a transition period (ramp up time) between award of contract and start of contract?
DLA Disposition Services tries to award contracts at least a month before performance begins to give the awardee a chance to get their operations up and running.
2. No other changes are authorized.
File details come from the government source that posted it. Updated .