RFQ Attachment 1 - Product Specifications

View the file

Other files

File Type Posted
SteelRack_QAs_as_of_6-16-16.pdf PDF
RFQ_Attach_2-Pricing_Quote_Sheet.xlsx XLSX spreadsheet
Comb_Synop-Sol_(16Q0202).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Product Specifications DDCN Cherry Point – Sheet Steel Storage Racks

Background:

a. Requiring Organization

Defense Distribution Depot Cherry Point, North Carolina (DDCN)

b. Purpose of this document:

The purpose of this document is to detail the requirements for purchase and installation of a six sheet steel storage racks to be used at DDCN. These racks will be installed in building 150.

1. Minimum Specifications of Product:

• The contractor shall furnish all equipment, accessories, and material necessary to install 6 ea. each rack systems in Building 150 as a finished turn-key project.

• The racks shall be installed on existing concrete floor within the specified warehouse facility.

• Each rack opening shall be capable of storing materiel up to 5’ deep by 12’ wide.

• Each rack system shall be nominal 12’ tall.

• Each rack opening shall be minimum 4”.

• 19 removable shelves (pallets) shall be supplied per system (6 systems).

• Each rack shelf shall be capable of handling weight up to 5,000 lbs.

• Each rack system shall require signage showing shelf (pallet) and system weight capacity.

• Accessories not specified mentioned herein, but necessary to furnish complete system ready for use, shall also be included, and named. The contractor shall include all shipping and destination charges.

Exterior Color: Manufacturer’s Standard.

Warranty Coverage: Warranty coverage shall be manufacturer’s standard warranty but not less than one year of parts and labor.

2. Description of Contractor’s Tasks:

Task A: Successful delivery of all products

Task B: Successful assembly and installation of products Task C: Provide Owner’s Manual (s).

3. Certification and Acceptance:

Final acceptance of the rack systems will be by Robert Skinnell-DS-FDI.

4. Project Management Approach:

N/A

5. Performance and/or Delivery Schedule:

The contractor shall be required to complete within 10 weeks after date of contract award. Installation is required and is incidental to the asset purchase.

To ship items via FedEx, UPS, and other carriers to DDCN use following address:

Defense Logistics Agency Defense Distribution Center, Cherry Point ATTN: Ervin Mewborn Building 159 Cherry Point, NC 28533

6. Work Location(s) and travel:

Travel to other locations is not required.

7. Government Furnished Property/Equipment:

The Government will provide power source for installation.

8. Security Requirements:

Contractor shall comply with DDCN security requirements for on-site access for personnel and vehicles if necessary.

9. Period of Performance:

Ten (10) weeks after date of contact award.