About this file
Amendment 01
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFQSAPEngineeringServices.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ SP310008T0050
Amendment 01 Questions received concerning Request for Quote SP310008T0050.
Question 1:
Does the Raymond Lift Model 589 require the inspection to be performed from the inside the masts due to the plate covering all of the panel points?
Answer:
The inspection of Raymond Lift model 589 will require the use of a JLG (or equivalent) high-lift capable of a height of 65 feet as well as it may require internal inspection due to the unique mast structure associated with the model 589.
Question 2:
What level of effort is required for the contractor for both the Raymond models 89 and 589?
Answer:
The Government has estimated that the combined labor hours for the labor categories for the Project Engineer (PE), Non Destructive Examiner (NDE), and any other required labor categories to perform the inspections as follows:
Inspection of Raymond Model 89: Total quantity of model 89 lifts to be inspected:
thirteen (13) lifts in total. The Government estimates the complete inspection for all model 89’s should take approximately 130 man hours. The requested quote for Labor Hour Unit Price should be inclusive of any and all labor categories required to perform the inspections.
Government listed Electronic Job Order Number (EJON) for model 89 (First three characters is a Government Identification and the last three is the Raymond Lift Unit Number):
4D4004 4D4006 4D4009 4D4010 4D4011 4D4017 4D4021 4D4028 4D4029 4D4033 4D4036 4D4039 4D4040
Inspection of Raymond Model 589: Total Quantity of model 589 lifts to be inspected:
fourteen (14) lifts in total. The Government estimates the complete inspection for all model 589’s should take approximately 70 man hours. The requested quote for Labor Hour Unit Price should be inclusive of any and all labor categories required to perform the inspection.
Government listed Electronic Job Order Number (EJON) for model 589 (First three characters is a Government Identification and the last three is the Raymond Lift Unit Number):
4D4041 4D4042 4D4043 4D4044 4D4045 4D4046 4D4047 4D4048 4D4049 4D4050 4D4051 4D4052 4D4053 4D4054
The technical capability of a quote should explain how quoters plan on performing the inspection service.
The quote must also include past performance information.
Question 3:
Will there be a repair campaign after the inspections?
Answer:
The Government is unable to make this determination until the inspections are completed and the inspection reports reviewed. If repair is needed, it will be competed under separate solicitation.