RFQ SP3100-08-Q-0001

Amendment 04

This amendment is to respond to a question referenced on Amendment 03.

Question 1:

What is the square footage of building 268?

Answer:

The square footage of building 268 is 14,704 SF (includes both floors).

Question 2:

Are existing pole mounted transformers are to be powered off by the base?

Answer:

All work is required to be performed by the contractor; the contractor will be responsible to power down the transformers.

Question 3:

Are there any overhead high tension wires powered and active serving other buildings?

Answer:

Existing overhead distribution lines are energized and serve other buildings. Any required outages shall be coordinated with the Contracting Officer Representative (COR) that will be assigned to the awarded contract.

Question 4:

Will the water system be shut off and capped by the base?

Answer:

The Government will shut off the water, but it is the contractor’s responsibility to cap the water line.