SP_Attachment-2_Cost Sheet.xlsx

XLSX spreadsheet 38 KB Posted

Attached to
NOTICE OF SPECIAL PROCUREMENT AMENDMENT: Pharmacy Automation Equipment, Software and Services
Solicitation number
S-DASOBO-00006947
Issued by
Marion County, Oregon

About this file

This document is related to a state and local contract opportunity for Pharmacy Automation Equipment, Software, and Services. The opportunity is being issued by Marion County and the City of Salem, Oregon. The contract will include the lease and purchase of pharmacy automation equipment, software, and related services. The contract has multiple amendments, with the latest amendment (#4) addressing a lease that rolled over to month-to-month and should have been re-executed. The contract has an original NTE (not-to-exceed) amount of $1,010,963.34, which has been increased through subsequent amendments up to a current NTE of $5,533,082.74 for the lease portion only. There is an additional NTE of $10,309,765.55 for the purchase portion, for a total combined NTE of $10,570,713.74. The contract includes a variety of leased pharmacy equipment, servers, and automated dispensing cabinets. Funding for this contract comes from the participating agencies, and the contract term includes renewal options.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAIN

REQ-DASOBO-00030542
Cost Sheet
SP Attachment - 1
AMENDMENT #PRICING SUPPLEMENTLEASE RENTAL #Month/Unit CostDESCRIPTIONPO#LEASE STARTLEASE ENDCOST ADJUSTPURCHASE ORDER COSTNTE INCREASENTE BALANCE
ORIGINAL CONTRACT
5028170CMS005941$5,214.40MedOne Lease Number 1CONTRACT1/1/1412/31/18$314,281.92
5029897CMS006131$1,942.20MedOne Lease Number 2CONTRACT4/1/143/31/19$119,134.94
5042384CMS006130$9,532.03MedOne Lease Number 3CONTRACT4/1/143/31/19$577,546.48
ORIGINAL CONTRACT TOTAL: $1,010,963.34$1,010,963.34$0.00$1,010,963.34
AMENDMENT #1
See note

Reynolds David O: Reynolds David O:

This is the lease that rolled over to month to month 6/1/20 that we have continued to pay as we require the equipment. A new lease should have been executed.5058861CMS006705$7,037.03MedOne Lease Number 4PO3296646/1/155/31/20$429,229.31$429,229.31
AMENDMENT #1 TOTAL $429,229.31 CONTRACT TOTAL $1,440,192.65$1,440,192.65$429,229.31$1,440,192.65
AMENDMENT #2
5030962CMS007093$1,756.25MedOne Lease Number 5CONTRACT2/1/161/31/21$105,843.75$105,843.75
5148295CMS007282$3,016.09MedOne Lease Number 8 OSH Servers - Original OrderPO3356328/1/167/31/19$111,896.64$109,039.88$109,039.88
5161930N/AOSH Servers - Change Order (Returns)PO335632-$83,922.48--
5161656N/AOSH Servers - Change Order (Adds)PO335632$81,065.72--
5153560CMS007367$2,769.77MedOne Lease Number 9 Atmosera Servers - Original OrderPO33581610/1/169/30/19$111,896.64$101,403.92$101,403.92
5161957N/AAtmosera Servers - Change Order (Returns)PO335816-$83,922.48--
5161956N/AAtmosera Servers - Change Order (Adds)PO335816$73,429.76--
5102537CMS007648$48,657.94MedOne Lease Number 14 Automated Dispensing Cabinets (Adjustments from 5030405)PO3346414/1/173/31/22$2,655,741.89$2,962,186.49$2,962,186.49
5030405N/AADC's from base contractPO3346414/1/173/31/22$2,441,949.16--
5102600N/ADebooks PS#5030405PO334641N/A-$2,135,504.56--
AMENDMENT #2 TOTAL$3,278,474.04$3,278,474.04$4,718,666.69
AMENDMENT #3
5204894CMS007586$386.78MedOne Lease Number 10PO3391342/1/175/31/19$10,829.84$10,829.84
5206097CMS007589$386.78MedOne Lease Number 11PO3391342/1/175/31/19$10,829.84$10,829.84
5206103CMS007587$267.76MedOne Lease Number 12PO3391332/1/175/31/19$11,245.92$11,245.92
5204895CMS007588$386.78MedOne Lease Number 13PO3391332/1/175/31/19$10,829.84$10,829.84
Active Lease, Payment to MedOne5330131CMS008464$98.30MedOne Lease Number 15PO3477329/1/188/31/23$5,898.00$5,898.00
5363251CMS008572$101.89MedOne Lease Number 16PO34922412/1/182/28/22$4,011.82$4,011.82
Active Lease, Payment to MedOne5381860CMS008716$96.44MedOne Lease Number 17PO3501494/1/199/30/23$5,249.61$5,249.61
Active Lease, Payment to MedOne5381861CMS008717$96.44MedOne Lease Number 18PO3501774/1/199/30/23$5,249.61$5,249.61
Active Lease, Payment to MedOne5376672CMS008752$8,898.04MedOne Lease Number 19PO3502364/1/198/31/23$471,596.12$471,596.12
AMENDMENT #3 TOTAL$535,740.60$535,740.60$5,254,407.29
AMENDMENT #4

Woods Jill S: Woods Jill S:

This is the lease that rolled over to month to month 6/1/20 that we have continued to pay as we require the equipment. A new lease should have been executed.

Reynolds David O: Reynolds David O:

This is the lease that rolled over to month to month 6/1/20 that we have continued to pay as we require the equipment. A new lease should have been executed.

Payment made to OmniCellVP2518417145.71LS# CMS006705 JUNE 2020 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2518417145.71LS# CMS006705 JULY 2020 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2507787145.71LS# CMS006705 AUG 2020 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2507787145.71LS# CMS006705 SEPT 2020 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2507787145.71LS# CMS006705 OCT 2020 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2517327145.71LS# CMS006705 NOV 2020 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2531057145.71LS# CMS006705 DEC 2020 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2556937145.71LS# CMS0006705 JAN 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2584257145.71LS# CMS006705 FEB 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2583857145.71LS# CMS006705 MARCH 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2605867145.71LS# CMS006705 APR 2021$7,145.71$7,145.71
Payment made to OmniCellVP2619897145.71LS#CMS006705 MAY 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2639847145.71LS# CMS006705 JUNE 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2667867145.71LS# CMS006705 JULY 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2713147145.71LS# CMS006705 AUGUST 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2713147145.71LS# CMS006705 SEPT 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2753007145.71LS# CMS006705 OCT 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2753007145.71LS# CMS006705 NOV 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2767537145.71LS# CMS006705 DEC 2021 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2777257145.71LS# CMS006705 JAN 2022 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2802547145.71LS# CMS006705 FEB 2022 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2824757145.71LS# CMS006705 MAR 2022 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2900367145.71LS# CMS006705 APR 2022 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2900367145.71LS# CMS006705 MAY 2022 OSH$7,145.71$7,145.71
Payment made to OmniCellVP2912887145.71LS# CMS006705 JUNE 2022 OSH$7,145.71$7,145.71
JC MTM7145.71Month to Month Rental Expired CMS0067057/1/228/31/23$100,039.94$100,039.94
AMENDMENT #4 TOTAL$278,682.69$5,533,089.98

Lease NTE by EXE

140842 Leases ONLY
PS in which KT ExecutionMed One Lease #Pricing SupplementPOMed One Lease Rental #AdjustmentsNTELease Start DateNotes
Base Contract15028170N/ACMS005941$ - 0$ 314,281.921/1/14-
Base Contract25029897N/ACMS006131$ - 0$ 119,134.944/1/14-
Base Contract35042384N/ACMS006130$ - 0$ 577,546.484/1/14-
$ 1,010,963.34
NTE Prior to AMD1$ 1,010,963.34
AMD145058861PO329664CMS006705$ 429,229.316/1/15This is the lease that rolled over to month to month 6/1/20 that we have continued to pay as we require the equipment. A new lease should have been executed.
NTE Prior to AMD2$ 1,440,192.65
Base Contract55030962N/ACMS007093$ 105,843.752/1/16-
AMD285148295PO335632CMS007282$ 111,896.64$ 109,039.888/1/16OSH Servers - Original Order
AMD2-5161930PO335632N/A$ (83,922.48)-OSH Servers - Change Order (Returns)
AMD2-5161656PO335632N/A$ 81,065.72-OSH Servers - Change Order (Adds)
AMD295153560PO335816CMS007367$ 111,896.64$ 101,403.9210/1/16Atmosera Servers - Original Order
AMD2-5161957PO335816N/A$ (83,922.48)-Atmosera Servers - Change Order (Returns)
AMD2-5161956PO335816N/A$ 73,429.76-Atmosera Servers - Change Order (Adds)
AMD2145102537PO334641CMS007648$ 2,655,741.89$ 2,962,186.494/1/17Automated Dispensing Cabinets (Adjustments from 5030405)
Base Contract-5030405PO334641N/A$ 2,441,949.16-ADC's from base contract
AMD2-5102600PO334641N/A$ (2,135,504.56)-Debooks PS#5030405
$ 3,278,474.04
NTE Prior to AMD3 (NTE on 118 for AMD2)$ 4,718,666.69

Woods Jill S: Woods Jill S:

Mike Adamson's tracker had the NTE at $4,798,666.69. He had this amount as the NTE on the 118 submitted for AMD2 as well. However, he had the NTE on lease 2, CMS006131 as $199,134.94 in error instead of the $119,134.94 the lease was executed for. This $80,000 difference is the NTE for lease 2 explains the $80,000 difference in Mike's calculations and mine at the execution of AMD2.

New Amd105204894PO339134CMS007586$ 10,829.84
New Amd115206097PO339134CMS007589$ 10,829.84
New Amd125206103PO339133CMS007587$ 11,245.92
New Amd135204895PO339133CMS007588$ 10,829.84
New Amd155330131PO347732CMS008464$ 5,898.00
New Amd165363251PO349224CMS008572$ 4,011.82
New Amd175381860PO350149CMS008716$ 5,249.61
New Amd185381861PO350177CMS008717$ 5,249.61
New Amd195376672PO350236CMS008752$ 471,596.12
$ 535,740.60
Total NTE of Executed Leases$ 5,254,407.29

SFMA NTE

Med One Executed Lease #Pricing SuppPOMed One Lease Rental #AdjustmentsCorrect NTENTE in SFMA
1 - Expired5028170N/ACMS005941$ 314,281.92$ 314,281.92
25029897N/ACMS006131$ 119,134.94

Woods Jill S: Woods Jill S:

Mike Adamson had this lease NTE at $199,134.94. But, I double checked the PS and past payments for this lease.$ 199,134.94
35042384N/ACMS006130$ 577,546.48$ 577,546.48
45058861PO329664CMS006705$ 429,229.31$ 429,229.31
55030962N/ACMS007093$ 105,843.75$ 105,843.75
85148295PO335632CMS007282$ 111,896.64

Woods Jill S: Woods Jill S:

All cells highlighted yellow reflect the change orders done and final execution on lease CMS007282$ 109,039.88$ 109,039.88
-5161930PO335632adjustment to -8$ (83,922.48)N/AN/A
-5161656PO335632adjustment to -8$ 81,065.72N/AN/A
95153560PO335816CMS007367$ 111,896.64

Woods Jill S: Woods Jill S:

All cells highlighted orange reflect the change orders and final executed lease for CMS007367$ 101,403.92$ 101,403.92
-5161957PO335816adjustment to -9$ (83,922.48)N/AN/A
-5161956PO335816adjustment to -9$ 73,429.76N/AN/A
105204894PO339134CMS007586$ 10,829.84

Woods Jill S: Woods Jill S:

All cells highlighted green reflect leases that I have not added their NTE into the contract NTE in SFMA as I was unaware of them until I discovered Mike's tracker. However, I cannot add this amount now as the NTE in SFMA is arleady overstate due to the excess $80,000 recorded for lease CMS006131 as this overage was built into the SFMA NTE at AMD2

115206097PO339134CMS007589$ 10,829.84RECON COLUMN G TO F, LINE 27
125206103PO339133CMS007587$ 11,245.92
135204895PO339133CMS007588$ 10,829.84$ 5,308,399.11G 27NTE SFMA
145102537PO334641CMS007648$ 2,655,741.89

Woods Jill S: Woods Jill S:

All cells highlighted grey reflect the change orders and final execution of lease CMS007648$ 2,962,186.49$ 2,962,186.49$ (17,727.26)G26Less Cost overun
-5030405PO334641adjustment to -14$ 2,441,949.16N/AN/A$ (80,000.00)G28less over statement
-5102600PO334641adjustment to -14$ (2,135,504.56)N/AN/A$ 43,735.44sum F14-F17plus column F 14-14 leases
155330131PO347732CMS008464$ 5,898.00$ 5,898.00$ 5,254,407.29TOTALmatches F27
165363251PO349224CMS008572$ 4,011.82$ 4,011.82
175381860PO350149CMS008716$ 5,249.61$ 5,249.61
185381861PO350177CMS008717$ 5,249.61$ 5,249.61
195376672PO350236CMS008752$ 471,596.12$ 471,596.12$5,272,134.55
Cost Overrun for April, May and June 2022 Payments of Off Lease for CMS006705-$ 17,727.26
Totals:$ 5,254,407.29$ 5,308,399.11Current KT NTE in SFMA Under 140842 (lease portion ONLY)difference between F27 and G27 SEE TABLE ABOVE
$ (80,000.00)

Woods Jill S: Woods Jill S:

To Correct $80,000 NTE in SFMA for Overstatement on lease CMS006131 (lease #3 on line 5) Woods Jill S: Woods Jill S:

All cells highlighted green reflect leases that I have not added their NTE into the contract NTE in SFMA as I was unaware of them until I discovered Mike's tracker. However, I cannot add this amount now as the NTE in SFMA is arleady overstate due to the excess $80,000 recorded for lease CMS006131 as this overage was built into the SFMA NTE at AMD2$5,308,399.11
$ 5,228,399.11$5,254,407.29
$ 43,735.44

Woods Jill S: Woods Jill S:

increase for Leases on Mikes list that I didn't know existed but found PO's for in ADPIX and found 2017 invoice from Med One that included these leases. See leases 10-13 on lines 14-17.

Woods Jill S: Woods Jill S:

All cells highlighted grey reflect the change orders and final execution of lease CMS007648 Woods Jill S: Woods Jill S:

Mike Adamson had this lease NTE at $199,134.94. But, I double checked the PS and past payments for this lease.

Woods Jill S: Woods Jill S:

All cells highlighted yellow reflect the change orders done and final execution on lease CMS007282 Woods Jill S: Woods Jill S:

All cells highlighted orange reflect the change orders and final executed lease for CMS007367$53,991.82
$ 5,272,134.55What should be SFMA NTE 140842 (lease portion ONLY) Currently
$ 5,037,631.00NTE for Purchase in SFMA as 140842-4(purchase portion ONLY)

$ 10,309,765.55 Current Total NTE for Leases and Purchase Combined. (G31+G32)

$ 178,642.51Funds expended to pay expired lease CMS006705 from June 2020-June2022 (amount applied against 140842 in error)
$ (17,727.26)Less amount of Cost Overrun already added to KT for May 2020-June 2020 payments to Omnicell for expired lease CMS006705
$ 160,915.25Total additonal funds needed to cover payments already made to Omnicell from June 2020-June 2022 for expired lease CMS006705
$ 100,032.94Plus funds required to pay expired lease CMS006705 for 14 months (July 2022-August 2023 to match other carousel lease CMS008752/PS5376672)
$ 260,948.19TOTAL approx additional amount needed in NTE to cover expired lease CMS006705. That currently does NOT have an executed Pricing Supplement and PO. This amount would cover a term of 6/1/20-8/31/23, including payments already made to Omnicell while lease was expired from June 2020-June2022. Plus an addtional POTENTIAL 14 months of future payments from 7/1/22-8/31/23 at the same off lease rate of $7,145.71, if the lease is re-instated and the term is extending to match the expiration of lease CMS008752.

$ 5,533,082.74 TOTAL NEW NTE for Leases ONLY - IF New AMD Done to Reinstate Lease CMS006705 Eff: 6/1/2020-8/31/2023 (G31+G41)

$ 10,570,713.74 TOTAL NEW Total NTE for Leases and Purchase Combined. IF New AMD Done to Reinstate Lease CMS006705 Eff: 6/1/2020-8/31/2023 (G32+G43)

Spent to Date on Purchase Expenditures for Purchase 140842-1 Woods Jill S: Woods Jill S:

To not comingle funds we set up the purchase portion of the contract as 140842-1 in SFMA

PURCHASE: 140842 AMD 3
NTE for Purchase Portion of KT 140842$ 5,037,631.00
Funds Spent on Equipment and Software to Date on Purchase Portion of KT 140842$ 3,686,388.07
Funds Spent on Support Services to Date on Purchase Portion of KT 140842:$ 104,048.00
Total Expenditure to Date on Purchase Portion of KT 140842$ 3,790,436.07