SOWork AC units and Cooling Tower Coils replacement STA Lake Work Inlet.doc
DOC document 77 KB Posted
- Solicitation number
- 70Z028-21-Q-PMV05900
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 52.212-5.docx | DOCX document | |
| 52.212-1.docx | DOCX document | |
| 52.212-3.docx | DOCX document | |
| 52.212-4.docx | DOCX document | |
| DOL Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK FOR Station Lake Worth Inlet A/C and Cooling Tower Coil Replacement CG STA Lake Worth Inlet, FL
1 DESCRIPTION OF WORK
1.1 Remove and dispose of:
· Old cooling tower coils and stainless steel casing
· Drift eliminators
· Inlet Louvers
· All piping connections at tower
· six (6) existing air conditioners which service the duty rooms 130A, 133A, 134A, 138A, 140A, and 143A
1.2 Provide and install:
· New Stainless steel casing with galvanized coils
· (2)Drift eliminators
· Inlet louvers
· All piping located at tower (closed/open loop)
· (2) 4” cast iron butterfly valves with stainless steel bolt kits
· Six (6) new air conditioner units IAW standard industry practice, with new commercial quality heat pumps. The units that service the duty rooms 130A, 133A, 134A, 138A, 140A, and 143A should be one (1) Ton or greater.
All replacement equipment shall be “in kind” with the equipment it’s replacing so not to require unnecessary design and fabrication work. If unnecessary design and fabrication work is required due to the contractor procuring equipment which is not “in kind”, the contractor shall absorb all costs associated with said design and fabrication work to make that equipment function for the space it’s intended. All aspects of installation shall be straight, level, plumb, square or 45 degree, and of the highest quality. If any added work due to existing interferences, I.E. fabrication of ducting be required which would deviate from the cost outlined in the perspective quote, approval from the Civil Engineering Unit would be required.
Contractor shall in addition:
· Provide all crane services
· Remove and reset top fan section with electrical hook-ups
· Clean and wire brush bottom sump section
· Pressure test and bleed system
· Run and test cooling tower controls
· Run and test new air conditioner units
· Provide a licensed electrical contractor to conduct all work
· Provide unit with all warranty documentation as per industry standard
All work shall be installed iaw best industry practice and comply with all pertaining code.
2 SUBMITTALS AND OUTCOMES
2.1 Safety Plan (see 20.3)
2.2 The Contractor shall submit a work schedule including all milestones within seven (7) calendar days following contract award.
2.3 Submit installation details showing method of acid wash.
2.4 Submit product data and installation instruction.
2.5 Provide Florida notice of product approval indicating the product meets wind pressure requirements for the installation location.
3 PROJECT PERFORMANCE TIME
The contractor must complete all work, deliverables and outcomes within 30 calendar days after notice to proceed is given by the Government.
4 LOCATION
All work shall take place at the following location:
CG STA Lake Worth Inlet 4400 Lake Shore Drive Riviera Beach, FL 33404
5 POINT OF CONTACT
The Government Point of Contact (POC) for this work is MKC Kevin Thomas, (561) 844-4470, kevin.l.thomas@uscg.mil, facility engineer DC3 Baltz Jason, jason.w.baltz@uscg.mil . The Contractor shall coordinate with the POC to minimize interference with Coast Guard operations or personnel. All work shall be coordinated with other trades involved in the project and carefully laid out in advance.
6 WORK PHASING
6.1 Work shall be completed as expeditiously as possible; Contractor shall coordinate with the POC to coordinate phasing and job sequencing. Contractor shall submit construction schedule for Government review and approval prior to commencing in any work to be performed.
6.2 The facility shall remain in operation throughout the service. Contractor access to the service site shall be limited to the following: 8:00am to 4:00pm, Monday through Friday, excluding holidays. Access to the site shall not be permitted on the weekends without prior approval from the Coast Guard (COR).
7 AVAILABILITY OF UTILITIES
7.1 Reasonable amounts of the following utilities will be made available to the Contractor without charge.
7.1.1 Electricity
7.1.2 Potable Water
7.2 The Contractor shall pay all costs incurred in connecting, converting, and transferring the utilities to the work. The Contractor shall be responsible for making connections including providing back flow preventer devices on connections to domestic water lines, providing transformers, and for disconnections. The POC shall designate the outlets available to the Contractor.
8 CONTRACTOR USE OF PREMESES
The Contractor will be working on a Coast Guard operational military installation. Become familiar with and obey installations’ fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work nor direct avenues of ingress and egress unless authorized in advance by the Government.
9 LAYDOWN AREA
The Contractor will be provided with an uncovered lay-down area in the immediate vicinity of the work. The Contractor shall be responsible for restoring the area to its original condition at the completion of the work. The Contractor shall be responsible for repair of any damage incurred to buildings or pavement as a result of storage activities.
10 STORM PROTECTION
Should warnings of extreme weather (such as high waves, storm surge, wind of gale force) be issued, the Contractor shall take every practicable precaution to minimize danger to personnel, the work and adjacent property. Precautions shall include, but not be limited to, relocating barges, closing all openings, removing all loose materials, tools and equipment from exposed locations, and removing or securing fencing, scaffolding and other temporary work.
11 ENVIRONMENTAL PROTECTION
All Federal, State and local laws must be strictly adhered to. Demolition and construction debris shall be disposed of at a permitted facility.
12 DELIVERY AND STORAGE
Equipment and materials shall be carefully handled, properly stored, and adequately protected to prevent damage before and during installation, in accordance with the manufacturer's recommendations. Damaged or defective items shall be replaced. Location of storage and staging area shall be designated by the POC. The contractor will be responsible for security of all materials and equipment.
13 RECEIPT OF MATERIALS
Shipment of equipment, materials, and supplies shall be addressed to the Contractor - not the Government. The Contractor must be on hand to accept shipments; the Government will not accept shipments.
14 CLEANUP
The Contractor shall keep the work area, including storage areas, free from accumulations of waste materials on a daily basis and comply with all federal, state and local regulations pertaining to the storage, transport and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles or dumpsters.
15 UTILITY OUTAGES
Before interrupting or shutting down any utility, make a request for the interruption to the POC at least two (2) working days before the anticipated interruption. Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the POC.
16 SECURITY
16.1 Working Personnel List.
The Contractor shall provide the COR with a list of names of all personnel who will be working on the site. The Contractor may submit a revised list at any time during the project. Only personnel on the approved listing will be allowed on the site.
16.2 Personnel Identification
All personnel shall carry proper identification (ID) when on site. Proper ID is defined as either the individual’s driver’s license, or a company issued ID. The identification must be laminated, and show facial picture of the individual. Individuals without proper ID will be escorted off the Coast Guard premises.
17 QUALITY
Quality of Contractor Furnished Material. Materials supplied by the Contractor shall be of a quality conforming to applicable Federal specifications.
18 WARRANTIES
All warranties and/or guarantees, either implied or expressed, for individual equipment shall be endorsed to the Government.
19 FINAL INSPECTION AND ACCEPTANCE
When the work is complete and ready for final inspection, submit a written request to schedule final inspection to the Government. Prior to such requests, all submittals must be complete and approved. Such requests shall allow a minimum of two (2) weeks notice prior to final inspection date.
20 SAFETY
20.1 General
The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. The Contractor shall provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable Federal, State and Local safety laws, rules and regulations.
20.2 Compliance
The Contractor is specifically required to comply with the requirements of the U. S. Army Corps of Engineers "Safety and Health Requirements Manual" (EM 385-1-1, latest version available) and the “Accident Prevention” clause (FAR 52.236-13). Once accepted, this safety plan shall become part of the contract requirements. Note: This review/acceptance does not in any way relinquish the Contractor from responsibility for work site safety nor the obligation to comply with the OSHA regulations found in 29 CFR 1910 & 1926 or any other State or Local safety law, rule or regulation applicable to the contract work. The Coast Guard will cooperate fully with the Department of Labor (Occupational Safety and Health Administration) in their enforcement of OSHA regulations.
20.3 Safety Plan
The Contractor shall submit a written safety plan within seven (7) calendar days following contract award. At a minimum, this plan shall describe the Contractor's general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, working over water, working from floating work platforms, overhead crane operations or similar conditions of the work. This Safety Plan shall be approved prior to commencing any work on site.