This document is a scope of work (SOW) for a New York State public works project to install a generator and transfer switch system at a residential facility called Cobblestone 105 IRA in Newark, New York. The vendor will be responsible for furnishing all materials and labor to completely install the generator and transfer switch as per the engineered drawings, and must comply with all New York State and Federal regulations, as well as the 2023 NEC code. The work must be completed within 90 days of receiving the purchase order, and is subject to mandatory inspections. A site visit is scheduled for June 5, 2024 at 9:30 AM, and bids will not be accepted from vendors who do not attend this visit.

The contract opportunity is a NYS public works project, and prevailing wages must be paid. Pricing is to include all materials, labor, disposal fees, and site clean-up. This is not a Service-Disabled Veteran-Owned Set Aside contract. The contract term is 30 days after completion of the project, and the award will be made to the Finger Lakes DDSO, which is located in Wayne County, New York.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DESCRIPTION:

Generator and Transfer Switch Installation at Residence. The vendor shall provide all labor and materials necessary to complete the work in a professional manner according to scope of work and architectural / engineered drawings. Work is to be completed within 90 days of award, unless modified below. This is a NYS Public Works project and prevailing wages are to be paid. Refer to attached specification for the following scope of work. Site must be cleaned and all materials secured at the end of each work day. Absolutely no scraps, especially fasteners, are to be left unsecured.

Upon completion of Generator Installation, before removal of equipment and scaffolding, contractor is to schedule a quality control and quality assurance inspection with Plant Superintendent.

SCOPE OF WORK includes, but is not necessarily limited to the following:

1. Furnish materials and labor to Completely Install the Generator and Transfer Switch System as per engineered drawings by: Patriot Designs Dated 12-1-23, Electrical

2. -submit to Emergency Power Systems (EPS). A technician will be assigned to the job to review the work and start-up of generator for warranty purposes.

3. All work to be inspected by: Middle Department Inspection @ (585) 454-5191, or Atlantic Inland @ 607-753-7118 and Inspection documents must be submitted to the DDSO contact listed above.

4. No splicing of service conductors is allowed in the system. Lug to lug connections are strictly enforced.

5. Panels must be re-wired as sub-panels for isolating neutrals.

6. All work to be done per New York State, Federal Regulations, and 2023 NEC code.

7. Test and tune equipment for optimal performance. Submit startup documentation for warranty verification.

8. Generator and Transfer switch to be picked up by vendor @ Newark Transportation Building, Newark, NY.

9. No payment will be processed until all necessary documentation and inspections are satisfactorily on file.

10. Work to be completed and invoiced within 90 days of receipt of P.O.

GENERAL REQUIREMENTS:

Facility: Cobblestone 105 IRA Facility Address: 105 Cobblestone Terrace Newark NY 14513

Point of Contact:

David Greco Maintenance Supervisor IIl

Contact Phone Number:

585-259-4122

Project Title:

Generator Installation

Summary of Work:

Completely Install Generator, and Transfer Switch for residence.

1. Bid price is to include all materials, labor, disposal of materials fees and site clean-up.

Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor.

2. Work is to be done between the hours of TBD, Monday through Friday.

Contractor is advised that this is an occupied home and may be occupied during these times.

3. All tools must be controlled at all times and debris, tools and materials secured and stored at the end of each work day.

4. Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent listed above immediately upon discovery.

5. Smoking is prohibited by contractors at all residential and program sites owned by

OPWDD.

6. Prior to the commencement of the work, there shall be a meeting with FLDDSO Operations and Maintenance staff to discuss specific safety requirements needed to be adhered to during the work period.

7. Safety Data Sheets as applicable will be provided to the Plant Superintendent prior to the start of work and a copy maintained at the property.

8. All applicable environmental testing associated with this work will be provided to the contractor prior to start of work.

SITE VISIT

A site visit is mandatory. The site visit date is scheduled for Wednesday, June 5, 2024 @ 9:30am at the project site. All prospective bidders are encouraged to attend.

A. Lawn Damage/Property Damage

If the delivery of materials or any other work necessitates the contractor, his suppliers, or sub-contractors to drive on the lawn for ANY reason, the contractor shall be held responsible for the repair of the lawn.

Personal vehicles are not to be parked on the grass.

Any property damage caused by work performed is to be corrected to the condition existing prior to start of the job.

B. Continuity of Work/Communication/Scheduling Once the job has begun, it is to be worked on continuously until completed.

If there are any delays, even if due to inclement weather, a Work Control Representative MUST be contacted.

Work must be completed within 90 days of receiving the purchase order.

C. House Safety The residence will be occupied during the job.

The contractor must take all reasonable care to safeguard the residents and the staff.

The contractor shall ensure all tools, materials and other items are picked up, removed or stored and are safely secured at the end of each workday.