SOW164.pdf
PDF 132 KB Posted
- Attached to
- Jefferson IRA - Bathroom Epoxy Floor Replacement
- Solicitation number
- 2127257
- Issued by
- Jefferson County, New York
About this file
This is a Project Scope document from the New York State Office for People With Developmental Disabilities (OPWDD) for the Jefferson IRA facility located at 9 West Jefferson Street in Dansville, NY. The project involves a Bathroom Epoxy Flooring Renovation, with work to be completed within 90 days of the purchase order issuance. A mandatory site visit is scheduled for Wednesday, October 22, 2025, at 11:00 am, and all prospective bidders are encouraged to attend. The scope includes furnishing all materials and labor to complete the flooring renovation according to architectural blueprints from Peter Morse Associates dated 9/2/25.
The project is classified as a New York State Public Works project requiring prevailing wages. The bid price must include all materials, drywall, labor, disposal fees, and site clean-up, with final acceptance provided by the appropriate Maintenance Supervisor. Work is to be performed Monday through Friday during hours to be determined, with the understanding that the facility is an occupied residential site. Strict safety and logistical requirements are outlined, including maintaining a clean and secure work site, ensuring house safety, preventing lawn and property damage, and coordinating closely with the House Director and Plant Superintendent. Safety Data Sheets and environmental testing documentation must be provided prior to work commencement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Approved for Construction-20250911_JeffersonBathroom.pdf | ||
| Approved Construction Permit10.pdf | ||
| Bid Tab306.pdf | ||
| RFQ187.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SCOPE
DESCRIPTION:
The vendor shall provide all labor and materials necessary to complete the work in a professional manner according to scope of work and architectural drawings if supplied. Work is to be completed within 90 days of the purchase order being issued. This is a NYS Public Works project, and prevailing wages are to be paid. Refer to attached specification for the following scope of work. Site must be cleaned, and all materials secured at the end of each workday. Absolutely no scraps, especially fasteners, are to be left unsecured. Upon completion of Bathroom Renovation, before removal of equipment, contractor is to schedule a quality control and quality assurance inspection with Point of Contact listed above.
SCOPE OF WORK includes, but is not necessarily limited to the following:
1. Furnish all materials and labor to complete the Bathroom Epoxy Flooring Renovation per Architectural/Engineered Blueprints from: Peter Morse Associates dated: 9/2/25
GENERAL REQUIREMENTS:
1. Bid price is to include all materials, drywall, labor, disposal of materials fees and site clean-up. Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor.
2. Work is to be done between the hours of TBD, Monday through Friday. Contractor is advised that this is an occupied home and may be occupied during these times.
3. All tools must be controlled at all times and debris, tools and materials secured and stored at the end of each workday.
4. Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent listed above immediately upon discovery.
5. Smoking is prohibited by contractors at all residential and program sites owned by
OPWDD.
6. Prior to the commencement of the work, there shall be a meeting with FLDDSO Operations and Maintenance staff to discuss specific safety requirements needed to be adhered to during the work period.
7. Safety Data Sheets as applicable will be provided to the Plant Superintendent prior to the start of work and a copy maintained at the property.
8. All applicable environmental testing associated with this work will be provided to the contractor prior to start of work.
Facility:
Jefferson IRA 263-FLA-2299
Facility Address:
9 West Jefferson Street Dansville, NY 14437
Point of Contact:
Jim Colon MS2
Contact Phone Number:
585-335-4119
Project Title:
Bathroom Epoxy Flooring Repair
SCOPE: JC0108
Summary of Work:
Renovation of Bathroom Epoxy Flooring for Jefferson IRA
SITE VISIT
A site visit is mandatory. The site visit date is scheduled for Wednesday, October 22, 2025 @ 11:00am at the project site. All prospective bidders are encouraged to attend.
A. Lawn Damage/Property Damage
• If the delivery of materials or any other work necessitates the contractor, his suppliers, or sub-contractors to drive on the lawn for ANY reason, the contractor shall be held responsible for the repair of the lawn.
• Personal vehicles are not to be parked on the grass.
• Any property damage caused by work performed is to be corrected to the condition existing prior to start of the job.
B. Continuity of Work/Communication/Scheduling
• Once the job has begun, it is to be worked on continuously until completed.
• If there are any delays, even if due to inclement weather, a Work Control Representative
MUST be contacted.
• Work must be completed within 90 days of receiving the purchase order.
C. House Safety
• The residence will be occupied during the job.
• The contractor must take all reasonable care to safeguard the residents and the staff.
• The contractor shall ensure all tools, materials and other items are picked up, removed or stored and are safely secured at the end of each workday.
• Any ladders, scaffolding or lifts used in conjunction with this job are to be stored to the satisfaction of the House Director at the end of the day.
• The work as indicated above shall be scheduled as not to interfered with other functions of the residence. All work performed as part of this job is to be coordinated with the House Director and Plant Superintendent listed above.
| SCOPE OF WORK includes, but is not necessarily limited to the following: |
| 1. Furnish all materials and labor to complete the Bathroom Epoxy Flooring Renovation per Architectural/Engineered Blueprints from: Peter Morse Associates dated: 9/2/25 |
| 1. Bid price is to include all materials, drywall, labor, disposal of materials fees and site clean-up. Final acceptance of completed job will be provided by the appropriate Maintenance Supervisor. |
| 2. Work is to be done between the hours of TBD, Monday through Friday. Contractor is advised that this is an occupied home and may be occupied during these times. |
| 3. All tools must be controlled at all times and debris, tools and materials secured and stored at the end of each workday. |
| 4. Any unforeseen conditions that may alter the established price are to be reported to the Plant Superintendent listed above immediately upon discovery. |
| 5. Smoking is prohibited by contractors at all residential and program sites owned by OPWDD. |
| 6. Prior to the commencement of the work, there shall be a meeting with FLDDSO Operations and Maintenance staff to discuss specific safety requirements needed to be adhered to during the work period. |
| 7. Safety Data Sheets as applicable will be provided to the Plant Superintendent prior to the start of work and a copy maintained at the property. |
| 8. All applicable environmental testing associated with this work will be provided to the contractor prior to start of work. |
SITE VISIT
File details come from the government source that posted it. Updated .