SOW Wheelhouse windows and doors.pdf
PDF 179 KB Posted
- Solicitation number
- 31040QPR250000179
About this file
This Scope of Work details a construction project for the U.S. Coast Guard Base in Portsmouth, VA, involving the replacement of exterior windows and doors. The project requires the contractor to remove 8 existing exterior windows, 4 storefront doors (2 with sidelights), and 1 small service window, and subsequently install new windows and doors with specific requirements. The new windows will be solid, non-opening with bronze-tinted glass, while the doors will include exterior storefront doors with insulated glass, a side storefront door with frosted glass, a rear storefront door with frosted glass, and a small service window.
The project has a tight timeline, with the contractor required to commence work within 5 calendar days after the notice to proceed and complete the entire project within 10 calendar days of contract award. Strict safety and environmental regulations must be followed, including compliance with OSHA standards, obtaining necessary permits, and coordinating with the Base Safety Officer and Environmental Protection Specialist. The contractor must provide a detailed employee list, ensure proper disposal of removed materials, maintain a clean work site, and follow specific guidelines for work hours, vehicle identification, and base entry procedures.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DBA VA20250161.txt | TXT text file | |
| Construction Provisions_and_Clauses FAC 2025-05.pdf | ||
| SF25A - Payment Bond.pdf | ||
| SF1442-22.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Updated August 2025
SCOPE OF WORK
1. GENERAL REQUIREMENTS: The work consists of providing all labor, materials and equipment as required to install New Exterior Doors and Windows located at USCG Base Portsmouth, 4000 Coast Guard Blvd, Portsmouth, VA, 23451
2. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK: Upon acceptance the contractor shall commence work NLT five (5) calendar days after notice to proceed and work diligently to complete the entire work ready for use by 10 calendar days after contract award.
3. SCOPE OF WORK:
• Demolition Work:
o Exterior Windows:
Carefully remove 8 existing exterior windows and their frames.
Ensure that the surrounding structure, including walls and sills, is not damaged during removal.
Remove all caulking, sealant, and any other materials used to secure the old windows.
o Exterior Storefront Doors:
Remove 2 existing exterior storefront doors with sidelights.
Ensure the removal process does not damage the surrounding door frames or building structure.
Detach and safely store the existing handicap door closer for reuse.
o Side Storefront Door:
Remove 1 existing storefront door on the side of the building.
Ensure the surrounding structure is not damaged during the removal process.
o Rear Storefront Door:
Remove 1 existing single rear storefront door.
Ensure the removal process does not damage the surrounding structure.
o Service Window:
Remove 1 small existing service window and its frame.
Ensure the surrounding structure is not damaged during the removal process.
o Disposal:
Collect all removed doors, windows, frames, and debris.
Transport and dispose of all materials in accordance with local regulations and environmental guidelines.
• Exterior Windows:
o Installation:
Install 8 new solid, non-opening windows with new frames.
Use glass with a bronze tint to match the specified aesthetic and functional requirements.
Ensure each window is securely fitted into the opening, properly aligned, and leveled.
Apply high-quality sealant around the perimeter of each window to prevent air and water infiltration.
Inspect each window to ensure proper installation and functionality.
• Exterior Storefront Doors:
o Installation:
Install 2 new exterior storefront doors with sidelights and insulated glass.
Ensure each door and sidelight is securely fitted into the opening, properly aligned, and leveled.
Reuse the existing handicap door closer, ensuring it is properly installed and functional.
Apply high-quality sealant around the perimeter of each door and sidelight to prevent air and water infiltration.
Inspect each door and sidelight to ensure proper installation and functionality.
• Side Storefront Door:
o Installation:
Install 1 new storefront door on the side of the building with frosted glass, non-insulated.
Ensure the door is securely fitted into the opening, properly aligned, and leveled.
Apply high-quality sealant around the perimeter of the door to prevent air and water infiltration.
Inspect the door to ensure proper installation and functionality.
• Rear Storefront Door:
o Installation:
Install 1 new single rear storefront door with frosted glass.
Ensure the door is securely fitted into the opening, properly aligned, and leveled.
Apply high-quality sealant around the perimeter of the door to prevent air and water infiltration.
Inspect the door to ensure proper installation and functionality.
• Service Window:
o Installation:
Install 1 new small service window with a solid window and frame.
Ensure the window is securely fitted into the opening, properly aligned, and leveled.
Apply high-quality sealant around the perimeter of the window to prevent air and water infiltration.
Inspect the window to ensure proper installation and functionality.
• Materials and Disposal:
o Materials:
The installer will supply all necessary materials for the installation, including windows, doors, frames, glass, seals, and any other required hardware.
o Disposal:
The installer will ensure all old doors, windows, frames, and debris are removed from the site and properly disposed of in accordance with local regulations and environmental guidelines.
4. SITE VISIT: All bidders are strongly encouraged to visit the site to field verify any/all quantities before submitting bids. Interested parties shall make arrangements for a site visit with Christopher.p.dollahon@uscg.mil
5. DESIGNATED CONTRACTING OFFICER’S QUALITY ASSURANCE
EVALUATOR (QAE) REPRESENTATIVE: The designated contracting officer’s QAE representative and Point of Contact for this project is Kevin Byrum (757) 646-2892. Inquiries concerning any phase of the specification before or after award shall be made to CSC Christopher Dollahon.
6. CONDITIONS AFFECTING THE WORK: The Offeror should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, the general and local conditions which can affect the cost of the work thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The government will assume no responsibility for any understanding or misrepresentations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the request for quotes, the specification or related documents.
7. AFTER AWARD OF THE CONTRACT: The contractor must immediately notify the contracting officer’s QAE representative of his intended start date. The work shall be done in accordance with the specification.
8. ORAL MODIFICATION: No oral statement of any person other than the contracting officer shall in any manner or degree, modify or otherwise affect the terms of this contract.
9. WORKMANSHIP: All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory to the Contracting Officer.
10. PERMITS: The contractor shall without additional expense to the government, obtain all appointments, licenses, and permits required for the prosecution of the work. The contractor shall comply with all applicable federal, state and local laws.
11. CLEAN UP: All trash and debris shall be removed from the site daily. The job site shall be left in a clean and neat manner.
12. WORK OUTSIDE REGULAR HOURS: If the contractor desires to carry on work on Saturday, Sunday, holidays or outside the station’s regular hours, he may submit his request in writing to the Contracting Officer’s QAE Representative for approval consideration. The contractor shall allow ample time to enable satisfactory arrangements to be made by the government for inspecting the work in progress.
13. UPON COMPLETION OF WORK: Contact the Contracting Officer QAE Representative to arrange for inspection/acceptance of work.
14. IDENTIFICATION OF CONTRACTOR PERSONNEL AND VEHICLES: The contractor shall provide a detailed list of all employees to the QAE Representative five (5) days prior to commencing work. The employee list shall contain the employee’s full name, date and place of birth, current address and last four (4) of SSN. The Base Portsmouth Security Officer will be given a copy of the employee list and a pass will be issued for entry. Each contractor provided vehicle or towed trailer shall show the contractor’s name so that it is clearly visible on the vehicle. A valid state license plate and safety inspection sticker is required. All vehicles operated on government property shall be maintained in a good state of repair.
15. SAFETY REQUIREMENTS:
1. Responsibilities:
a. All contractors working on CG Base Portsmouth shall abide by all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series), 29 CFR 1925 (series) and 29 CFR 1926 (series). Contractor written safety programs shall be reviewed by the Base Safety Officer prior to starting work.
b. Written notification must be provided to the Base Safety Officer, Noah Reinhart (757.638.2793 or C 757.641.7854) in their capacity as Base Fire Marshal of any activity that could potentially cause fire or explosion or that changes or reduces the capability of fighting a fire or explosion. Some examples of qualifying activities are:
a fire hydrant or fire suppression system that must be taken out of service for any reason, electrical work that affects fire alarm systems, introduction of hazardous or flammable material onto the Base, and blocking of any egress routes or emergency vehicle routes. Inclusion of this information in the contract constitutes written notification as long as the outsource review sheet is signed by Base Safety Officer.
c. Copies of the following must be provided to the Base Safety Officer prior to starting work in affected areas: Confined Space Entry Permits, Hot Work Chits, and Dig Chits. Confined space clearance must be conducted by a certified marine chemist and permit required spaces will have a copy of the permit posted on site during work. Hot work will only be conducted with permission and a fire watch must be posted during work. A facility dig chit is required in addition to a Miss Utility dig chit. The systems on Base Portsmouth are not limited to what the City of Portsmouth has on file. In order to ensure electrical safety and integrity of systems, a facility chit is required.
d. Lock Out/Tag Out requires notification and coordination with facilities and will not be conducted by a contractor on Base Portsmouth. A Facilities Division representative is required for all contractor Lock Out/Tag Out needs.
2. Rights:
a. Every employee working on Base Portsmouth has the right to a safe and healthy work place. The contractor has the responsibility and right to stop unsafe work. QAE’s and the Safety Officer may also institute a work stoppage relating to unsafe practices or immediate danger to life and health situations.
16. ENVIRONMENTAL PROTECTION REQUIREMENTS:
a. All contractors working on CG Base Portsmouth shall abide by all federal environmental regulations as published by the Environmental Protection Agency, 40 CFR (series). Contractor written environmental management and pollution prevention programs shall be reviewed by the Environmental Protection Specialist, Jonathan Cooper 757.483.8593 or C 757.373.2558 prior to starting work and must be in accordance with ICSPORTSVA INSTM5090.2, the Unit Environmental Guide.
b. Written notification must be provided to the Environmental Protection Specialist of any activity that could potentially cause a permit violation on Base Portsmouth.
Some examples of qualifying activities are: any activity that could result in a spill or discharge into a waterway or introducing a hazardous material into the environment.
c. Copies of the following must be provided to the Environmental Protection Specialist prior to starting work in affected areas: Material Safety Data Sheets, permits, and notices of intent.
d. Hazardous materials used by a contractor are required to be disposed of by that contractor. Disposal must be in accordance with federal, state, and local guidelines.
1. GENERAL REQUIREMENTS: The work consists of providing all labor, materials and equipment as required to install New Exterior Doors and Windows located at USCG Base Portsmouth, 4000 Coast Guard Blvd, Portsmouth, VA, 23451