SOW Watermain Supply for the Cutter.pdf
PDF 863 KB Posted
- Solicitation number
- 70Z02926QNEWO04
About this file
This is a Contract Specifications document for water main repair services at the United States Coast Guard Cutter Chena facility in Hickman, Kentucky (Project Number 32949935).
The contractor must locate and repair a water main leak at the USCG Cutter Chena moorings within a 14 calendar day performance period. Key work requirements include: locating and marking all private utilities before excavation (potable water, firefighting water, 480v and 240v underground electric, sewer/septic, and telecommunications); trenching a 10-foot by 10-foot section through asphalt to locate the leak source; procuring and installing replacement water piping of equal size; providing terminations at the water meter with flow and pressure verification; providing appropriate pipe fittings and sealants; excavating and removing damaged piping with proper disposal; restoring and patching disturbed surfaces including asphalt and galvanized steel C-Channel replacement; and providing a temporary steel plate for equipment access during cutter loading operations. The contractor must be a Kentucky-certified plumbing contractor complying with the National Plumbing Code and applicable city code. Normal working hours are Monday through Friday, 7:00 AM to 4:00 PM, with special scheduling required to prevent operational interruptions. The contractor is responsible for all labor, materials, equipment, permits, safety measures, utility coordination, waste disposal, and personnel security clearances. Required submittals include personnel roster, construction progress schedule, safety plan, product data sheets, and operation/maintenance manuals. The Coast Guard will provide reasonable potable water at no charge; the contractor must provide temporary toilet facilities and pay all connection costs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage Rates for Fulton County.pdf | ||
| SF 1442 - Repair Piping.pdf | ||
| Construction Clauses.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT SPECIFICATIONS
Watermain Supply to Cutter
AT
UNITED STATES COAST GUARD
Cutter Chena, 503 Hall St. Hickman, KY 42050
PROJECT NUMBER 32949935
SUMMARY OF WORK
PART 1 GENERAL
1.1. GENERAL DESCRIPTION
1.1.1. General Work Requirements
A. United States Coast Guard is accepting proposals for qualified individuals or firms to locate and repair a water main leak at USCG Cutter Chena moorings in Hickman, KY. Prior to submitting a quote, it is mandatory to examine the scope of work, and it is highly recommended to visit the facility to take field measurements, evaluations, etc., and become familiar with existing conditions under which the work will be performed. After the award of contract, a pre-conference will be held prior to starting the work at Cutter Chena moorings in Hickman, KY. Contractor shall acquire all necessary permits for project and provide all labor, materials, and equipment necessary to complete the following unless noted below:
(1) The contractor shall locate and mark ALL private utilities before any excavation. Public utility locating services (Call 811) cannot identify all utilities. Possible utility interferences include:
i. Potable Water
ii. Firefighting Water
iii. 480v underground electric
iv. 240v underground electric
v. Sewer and septic
vi. Telecommunications
(2) Procure and replace water main piping of equal size.
(3) Trench or dig a 10Ft by 10FT through the asphalt to locate the source of the leak. Known interferences include asphalt road and galvanized steel C-Channel for removable retaining wall.
(4) Provide a temporary steel plate at the excavation site for unit’s own heavy equipment to safely travel to the loading pad during cutter loading operations when contractor work is not in progress.
(5) Procure and install water piping of equal size. Route piping in dug out section, buried to proper depth and bedded in appropriate substrate.
(6) Procure and install water piping to be routed within the current depth.
(7) Provide terminations of all water flow at water meter.
Verify water flow and pressure prior to refilling dug out section.
(8) Provide appropriate pipe fittings and sealant for proper application to existing appliance terminations.
(9) Provide excavation and removal of damaged piping. Provide adequate disposal of materials.
(10) Restore/patch all disturbed surfaces to original condition, repair asphalt and replace galvanized steel C-Channel.
1.1.2. SPECIFIC WORK REQUIREMENTS
A. Qualifications
(1) The installation shall be performed by an plumbing contractor certified in the state of Kentucky.
(2) The installation shall comply with the most current edition of the National Plumbing Code and City code.
(3) The Contractor shall field verify all utility locations before commencing work. This shall include, but not be limited to, the use of visual, sonic, electronic or magnetic detection devices.
B. Additional Performance Requirements
(1) Contractor shall be responsible for disposing of the existing materials.
(2) The contractor is responsible for the protection of existing structures, utilities, work and vegetation. Any damage shall be repaired at the contractor’s expense.
1.1.3. SPECIAL WORK REQUIREMENTS
A. Coordinate all staging and laydown areas with the Coast Guard prior to work starting.
B. The contractor and subcontractor personnel shall, at all times, wear company identification.
1.2. TEMPORARY FACILITIES OR UTILITIES
None required.
1.3. PROJECT PERFORMANCE PERIOD
A. The total contract performance period shall include not only the time needed to complete the base bid and approved option items, but it also includes the time needed to submit, review, and approve all material submittals, and complete all project record (closeout) documents. After work begins at the site, perform the work continuously during normal working hours and show daily progress until all work is complete.
B. The total contract performance period is 14 calendar days.
1.4. LOCATION
The work is located at:
U.S. Coast Guard Cutter Chena 503 Hall St. Hickman, KY 42050
Arrangements for visiting the site may be made by contacting:
MKC Brandon Upchurch Email: brandon.m.upchurch@uscg.mil Telephone:(907) 942-7653
1.5. DRAWINGS ACCOMPANYING SPECIFICATION
There are no drawings accompanying this specification. Reference section 1.25 FIELD PICTURES.
1.6. WORK HOURS
1.6.1. Normal Working Hours
A. Perform all work at the site from Monday through Friday from 7:00am to 4:00 pm, unless otherwise approved. This project requires a special schedule to prevent operational interruptions during the installation process. Please refer to the scope section for detailed coordination of working hours. The contractor shall plan a schedule to minimize disruptions to building and Cutter operations.
B. Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.
1.7. SPECIFIC ENVIRONMENTAL REQUIREMENTS
There are no specific environmental requirements. Refer to section titled Environmental for general environmental requirements.
1.8. SAFETY PROGRAM
1.8.1. General
The Contractor is wholly responsible for work site safety.
Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.
1.9. AVAILABILITY OF UTILITY SERVICES
A. Reasonable amounts of the following utilities will be made available to the Contractor without charge.
(1) Potable Water.
B. The Contractor shall pay all costs incurred in connecting, converting, and transferring the utilities to the work. The contractor shall be responsible for making connections. The contractor shall provide temporary toilet facilities for their personnel.
1.10. UNDERGROUND AND CONCEALED UTILITIES
A. Any utility locations provided are diagrammatic, not exact.
B. Physically verify the location and elevation of the existing underground and concealed utilities local to the work area.
Employ techniques to scan the construction site including electromagnetic and sonic equipment prior to commencing the work. Mark the surface of the ground where existing underground utilities are discovered.
1.11. UTILITY OUTAGES
Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).
1.12. CONTRACTOR USE OF PREMISES
The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Isolate each construction area with temporary partitions and dust controls. Provide movable high-visibility safety fencing about all work areas and equipment laydown areas located outdoors. Provide temporary covers on excavations that remain open overnight.
1.13. CLEANUP
The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The
Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.
1.14. ENVIRONMENTAL
1.14.1. Protection of the Environment
The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment, including but not limited to the Endangered Species Act (ESA), Bald and Golden Eagle Protection Act (BGEPA), the Migratory Bird Treaty Act (MBTA), National Historic Preservation Act (NHPA), the Resource Conservation and Recovery Act (RCRA), and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).
1.14.2. Generated Waste
A. Any waste generated because of the project shall either be recycled or be disposed of in accordance with RCRA requirements.
B. Any hazardous waste shall be manifested off site with the Coast Guard unit listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of in accordance with RCRA and all applicable federal, state, and local laws and ordinances.
C. Hazardous waste shall be properly transported and delivered to an appropriate facility. The Contractor shall submit for COR approval the proposed disposal facility, qualifications of the transporters, and the draft hazardous waste manifest.
1.15. DISPOSITION OF MATERIALS
A. All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.
B. The Contractor shall submit the disposal receipt from the landfill within 10 working days of disposal.
1.16. STORM PROTECTION
The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property. Precautions shall include, but not be limited to, closing all opening, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.
1.17. RECEIPT OF MATERIALS
The Contractor is responsible to receive all equipment, materials, and supplies. The contractor is to take whatever steps necessary to ensure that his materials are protected. The Coast Guard has no responsibility for receipt, storage, or protection of contractor’s materials. All equipment, materials and supplies shall be addressed to the contractor. The Coast Guard will not accept shipments.
1.18. DELIVERY AND STORAGE
The Contractor is responsible for the proper transport and storage of all equipment and materials.
1.19. SECURITY
A. Submit a list of the names of all personnel working on the project site prior to the preconstruction conference for approval. The roster shall be submitted via email, and at a minimum, include the first name, last name, job description, and company of employment.
B. Immediately submit a new list upon a change in on-site project personnel. Refer to the paragraph titled, Special Notice Prior Notification, for notification requirements. Only personnel on the approved list are allowed onto the project site.
C. All approved personnel shall carry a valid, Government-issued identification while on Government property in conformance with the Real ID Act of 2005. Non-compliant personnel shall be escorted off Government property.
1.20. FINAL INSPECTION AND ACCEPTANCE
A. Electronically submit a written request for final acceptance to the Coast Guard. The Contracting Officer’s Representative has the right to reject defective workmanship or materials or work not performed as per the project specifications. Only the Contracting Officer or his/her representative may accept work performed by the contractor. Final Inspection will be performed in the presence of the unit POC.
1.21. WARRANTIES
A. Endorse all warranties or guarantees to the Government.
1.22. TRAINING
A. The Contractor shall provide training to unit personnel in the operation of the equipment. The Operation and Maintenance Manuals shall be approved and provided to the unit prior to the training.
1.23. SUBMITTALS
A. Submittals will be reviewed by the Coast Guard and returned within 10 working days after receipt, unless otherwise stated.
1.24. SUBMITTAL LIST
A. ROSTER OF PERSONNEL
(1) As required by the paragraph titled Security.
B. PROJECT SCHEDULE
(1) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.
C. SAFETY PLAN
(1) At a minimum, describe the general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, or similar conditions of the work. Comply with the paragraph titled Safety Program.
D. PRODUCT DATA
(1) Submit the product data sheet for each manufactured item.
It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts.
Submit complete descriptive data for each type of material.
Clearly mark data to indicate the type of material to be provided.
1.24.2. OPERATION AND MAINTENANCE MANUALS
A. Submit electronically and provide the following:
(1) Contact information for the prime contractor, sub-contractor, and major equipment vendor/supplier;
(2) Warranty information;
(3) Test procedures;
(4) Results of all testing and commissioning procedures;
(5) Performance data;
(6) A control sequence describing start-up, operation and shut-down instructions;
(7) Installation instructions;
(8) Maintenance instructions;
(9) Operating instructions;
(10) Parts list.
1.25. FIELD PICTURES
-- End of Section --