SOW VBDZ242109 Clean Oil and Water Separators.pdf
PDF 299 KB Posted
- Attached to
- Stratton ANGB - Clean Oil Water Separators Federal contract opportunity
- Solicitation number
- W50S8J-24-Q-A017
About this file
This document is a Scope of Work (SOW) for a federal contract opportunity to clean eight underground oil water separators (OWSs) at Stratton Air National Guard Base. The SOW provides details on the specific OWSs that need to be cleaned, including the nominal and usable volumes, spill capacity, materials, manufacturers, and installation dates. The contractor will be required to pump out the oil and water, remove and dispose of the sludge and solids, inspect the tanks, and refill the OWSs with fresh water. The contractor must also establish a contained work area to prevent any discharge or wash water from reaching the ground or stormwater system. The project is expected to start 14 days after the Notice to Proceed and be completed within 60 days. The related federal contract opportunity is Solicitation Number W50S8J-24-Q-A017 for "Stratton ANGB - Clean Oil Water Separators", with a site visit scheduled for 7 May 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Visit Sign In Sheet.pdf | ||
| Wage Determination.pdf | ||
| Solicitation - W50S8J24QA017.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
29 April 2024
Project Number VBDZ242109 Clean Oil Water Separators
DESCRIPTION:
Clean eight (8) functional underground Oil Water Separators (OWSs). The last time the OWSs were cleaned was in 2015. The location and description of the OWSs are shown below. All but
35.1 OWS are outdoors with easy truck access. The 35.1 OWS interceptor is inside the building, approximately 30 feet from the overhead door entrance (photo below). All of the OWSs, except 35.1, have electronic leak detection. For OWS 18.2, assume 6” of sludge as the depth could not be read.
OWS Description
Floor Plan for 35.1 Picture for 35.1
ID
Nominal Volume
Usable Volume
Spill capacity
Material Manufac.
Model
Number Config.
Ancillary Equipment
Date Instal
Sludge Depth
2.2 2500gal 2250gal 1250gal Fiberglass Ow ens Corning
DWT-Type 11 (6) 2500
Coalescing
OWS (PPI)
High Oil Level Alarm
1997 6"
8.1 2000gal 400gal - Steel Highland
Tank
HT-200-,
STI P3
Coalescing High Oil
Level Alarm 1997 6"
12.2 600gal 540gal 330gal Fiberglass Ow ens- Corning
DWT-11 (4)
Coalescing
OWS (PPI)
High Oil Level Alarm
1995 2"
18.2 600gal 540gal 330gal Fiberglass Ow ens- Corning
DWT-11 (4)
Coalescing
OWS (PPI)
High Oil Level Alarm
Can't read, assume 6"
31.1 1,000gal 900gal 530gals Fiberglass Ow ens Corning
DWT-Type 11 (4) 1000
Coalescing
OWS (PPI)
High Level Alarm
1995 4"
35.1 Interceptor 200gal N/A Steel
Ancon (Watts)
OI-410-X(F)
Gravity
Separator None 1992 N/A
35.3 550 gal - 440 gal - - - - - 2020 6"
3200.1 600gal 540gal 330gal Fiberglass Ow ens- Corning
DWT-11 (4)
Coalescing
OWS (PPI)
High Oil Level Alarm
2010 0"
Overhead door
Intercept
Interceptor
OWS access points
1. SCOPE
1.1. Contractor shall pump the oil and water out of all of the OWSs and transport the waste to a disposal or treatment facility.
1.2. Contractor shall remove and place sludge and solids into separate drums or totes and dispose of appropriately following State and Federal environmental regulations.
Contractor shall supply the drums or totes.
2.2
8.1
12.2
3200.1 18.2
31.1
35.1 – inside building
35.3
1.3. Some tanks may not have a way to remove the media plates/coalescers for exterior cleaning (the base does not know which ones). Contractor shall enter the tanks as a confined space to remove sludge and rinsing of the coalescers.
1.4. Contractor is to create a bermed, contained, poly-lined area outside of each OWS to contain wash plates and collect all wash water and discharged contaminants. No discharge or wash water shall reach the pavement ground surface or neighboring stormwater system.
1.5. Contractor shall inspect the tank for damage and condition of the internal coating.
Provide the results to the base. No repairs will be performed under this contract.
Inspection checklist is provided below and shall be filled for each OWS. Provide pictures of any damage along with the checklist.
1.6. Contractor shall fill the OWS with fresh, not recycled, water. Base water supply can be used.
1.7. Contractor shall not shut down any utilities without letting COR know. Contractor shall work with COR to schedule the utility shutdown.
1.8. Contractor shall dispose, or recycle, all trash and debris incurred during the project, off-base at an authorized recycle or disposal site by local, state, and federal requirements.
1.9. 1.10 Contractor shall report any spill outside of contained work area that reached the ground or stormwater within 15 minutes to the environmental manager (518-344-2114), or the fire department (518-344-2100).
1.10. 1.11 Contractor shall clean up any spills during pumping or transporting operations at no additional cost to the Government.
2. PROPOSED PROJECT SCHEDULE
The Project shall begin 14 days after the Notice to Proceed is issued. The start date may be changed with approval of Contracting Officer. The project shall be completed within 60 days following the Notice to Proceed or agreed start date.
3. CONTRACTOR REQUIREMENTS
3.1. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
3.2. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (DODIO 2000.16V1_DAFI 31-145, DAFI 31-101 and DODM 5200.08v3_DAFMAN 31-101v3), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at
OCONUS locations, in accordance with status of forces agreements and other theater regulations.
3.3. All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on Joint Knowledge Online (JKO) at https://jkodirect.jten.mil/Atlas2/page/login/Login.jsf. For those without a CAC, select "Non-CAC" user on the JKO site. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative.
3.4. Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/SMO/SMNCOs/Coordinators will provide OPSEC training or training materials to contract employees within 30 days of employees’ initial assignment to the contract and prior to having access to any critical information (CI) and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) located on the Defense Counterintelligence and Security Agency website:
https://securityawareness.usalearning.gov/opsec/index.htm and the OPSEC Annual training- DAF-Operations Security Awareness Training located on My Learning https://lms-jets.cce.af.mil/moodle/course/view.php?id=11654#section-1.
3.5. The Contractor shall provide all personnel and necessary equipment to establish an adequate and safe work zone. OSHA is applicable at the site and inspectors appear unexpectedly.
3.6. Contractor is responsible for site cleanliness and shall remove any waste or debris after the work is complete. All materials shall be secured to prevent loose objects from blowing and hindering flying operations in any manner.
3.7. The Contractor shall recycle to the greatest extent possible and turn in weigh slips to 109 Environmental Management Office for construction debris.
3.8. The Contractor shall bring any unforeseen project conditions to the attention of the COR immediately. Unexpected or differing site conditions, which may alter the scope of work, shall be approved by the contracting officer (KO) prior to such work being performed.
3.9. The Contractor must get approval from the COR prior to any utility shutdowns. (do not have contractor contact production control directly)
3.10. The Contractor shall notify the COR prior to delivery of any material or equipment to the site. The contractor shall ensure someone is available to receive delivered materials and able to store them safely in an area to be coordinated with the government project manager. Any materials delivered without prior coordination and without having someone to take receipt, shall not be accepted and turned away.
3.11. Contractor shall repair or replace in kind any property that is damaged.
3.12. Contractor hours are 0700-1530 Monday thru Friday, excluding Government holidays. No work shall be performed on holidays.