Statement of Work Summary: Office Setup in Tegucigalpa, Honduras
This Statement of Work (SOW) details repair, refurbishment, and minor construction services for an approximately 335 square-meter office space in Tegucigalpa, Honduras, to be completed within 120 calendar days from the Notice to Proceed. The project is sponsored by the International Narcotics & Law Enforcement Affairs (INL) bureau of the U.S. Department of State. This is a firm fixed-price contract with no price adjustments for material escalation, labor cost fluctuations, or currency exchange rate variations. The contractor must recruit local suppliers and laborers (no Third Country Nationals), provide worker's compensation insurance, and submit a construction schedule, worker list with identification copies, and proposed pricing based on the provided drawings and technical specifications. All materials must be new and of highest quality; no defective or reused materials are permitted without authorization.
The work encompasses eleven Contract Line Items (CLINs) including: (1) demolition and removal of existing floor systems, gypsum board partitions, suspended ceilings, electrical installations, IT systems, doors, and windows; (2) architectural works including reinforced masonry walls, drywall partitions, floor and ceiling finishes, and painting; (3–4) supply and installation of doors and windows; (5–6) electrical and plumbing installations; (7) minor complementary works such as kitchenette construction; (8) manual roller shades; (9) a comprehensive HVAC system featuring a VRF (variable refrigerant flow) air conditioning system with cassette evaporators, energy recovery ventilation, pre-insulated ductwork, and control systems; (10) emergency and life safety systems including fire extinguishers, emergency lighting, smoke detectors, and exhaust fans; and (11) Defense Base Act (DBA) insurance ($10,000). Payments are approved upon field verification of completed work, with invoices due no later than the 15th calendar day following each month. The contractor must adhere to applicable Honduran building codes and international standards (ASHRAE, SMACNA, NEC, NFPA) and provide comprehensive operation and maintenance manuals, staff training, system testing reports, and as-built drawings prior to final acceptance.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Repair, Refurbishment and
Minor Construction Services
P a g e | 1
PROJECT NAME:
“Office Setup in Tegucigalpa, Honduras”
International Narcotics & Law Enforcement (INL)
October 2026
Office Space Refurbishment
P a g e | 2
TABLE OF CONTENTS
COVER SHEET
TABLE OF CONTENTS
SECTION A – INTRODUCTION
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 DESCRIPTION OF SUPPLIES OR SERVICES
B.2 DESCRIPTION OF PRICES/COSTS
SECTION C – PERFORMANCE WORK STATEMENT
C.1. SCOPE
C.1.1 PURPOSE
C.1.2 LOCATION OF WORK
C.1.3 PERIOD OF PERFORMANCE
C.1.4 APPLICABLE STANDARDS
C.1.5 SPECIAL REQUIREMENTS
C.1.6 MISCELLANEOUS: OTHER PROJECT CONSTRAINTS
C.2. Project description
C.3. BILL OF QUANTITIES (BoQ)
C.3.1. PRE-PROPOSAL SITE VISIT
C.3.2. OTHER SITE VISIT
C.4. DELIVERABLES
C.4.1. DOCUMENTS PROVIDED FOR INFORMATIONAL PURPOSES
C.4.2. CLIN 1 - Demolition, Dismantling, Removal and Disposal C.4.3. CLIN 2 - Architectural Works C.4.4. CLIN 3 – Doors C.4.5. CLIN 4 - Windows C.4.6. CLIN 5 - Electrical Installations C.4.7. CLIN 6 - Plumbing and Sanitary Installations C.4.8. CLIN 7 - Minor and Complementary Works of the Project C.4.9. CLIN 8 - Manual Roller Shades C.4.10. CLIN 9 – HVAC System C.4.11. CLIN 10 - Emergency and Life Safety System C.4.12. CLIN 11 - DBA Insurance
C.5. PAYMENT SCHEDULE
C.6. GENERAL REQUIREMENTS
P a g e | 3
C.7. DEFINITIONS
C.8. task especifications
C.8.1. Demolition of existing floor
C.8.2. Demolition DRYWALL WALLS
C.8.3. EXISTING FALSE CEILING DISMANTLING
C.8.4. REMOVAL OF EXISTING ELECTRICAL SYSTEMS
C.8.5. REMOVAL OF IT SYSTEM (DATA)
C.8.6. REMOVING DOORS AND WINDOWS
C.8.7. DEMOLITION LOGISTICS AND WASTE MANAGEMENT
C.8.8. REINFORCED BLOCK WALLS
C.8.9. DRYWALL WALLS
C.8.10. DUROCK WALLS IN WET AREAS
C.8.11. INSTALLATION OF PORCELAIN TILES
C.8.12. 2X2 MINERAL FIBRE SUSPENDED FALSE CEILING WITH INSULATION
C.8.13. PAINTING
C.8.14. DOORS AND WINDOWS
C.8.15. ELECTRICAL INSTALLATIONS
C.8.16. HYDROSANITARY INSTALLATIONS
C.8.17. STRUCTURED CABLING (DATA)
C.8.18 hvac system
C.8.18.1 EQUIPMENT
C.8.18.2 AIR DISTRIBUTION SYSTEM
C.8.18.3 SUPPORTS
C.8.18.4 DIFFUSERS, GRILLES AND LOUVERS
C.8.18.5 PIPING
C.8.18.6 EXECUTION AND MAINTENANCE
C.8.18.7 MAINTENANCE
C.8.18.8 VRF INSTALLATION CRITERIA
C.8.18.9 COMMISSIONING REQUIREMENTS
C.8.18.10 SUBMITTAL REQUIREMENTS
P a g e | 4
C.8.18.11 EXTENDED WARRANTY RECOMMENDED
C.8.18.12 STANDARDS AND REFERENCES
P a g e | 5
SECTION A – INTRODUCTION
The U.S. Department of State (DoS) is the lead institution for the conduct of
American diplomacy with its mission to advance U.S. national security interests, fight terrorism, protect U.S. interests abroad, and implement foreign policy initiatives that build a freer, more prosperous, and secure world. The Bureau of
International Narcotics and Law Enforcement Affairs (INL), works to keep
Americans safe at home by countering international crime, illegal drugs, and instability abroad.
In Honduras, INL assists the host government by strengthening police, prosecutors, and judges. These efforts reduce the amount of crime and illegal drugs reaching
U.S. shores keeping American communities safe while enhancing Honduras' capacity to deliver security and justice services to its citizens. INL's work in
Honduras supports the country's efforts to combat transnational criminal organizations and disrupt U.S.-bound illicit drugs.
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 DESCRIPTION OF SUPPLIES OR SERVICES
The Contractor shall refurbish an approximate area of 335 m², including the demolition of existing elements, redistribution of spaces, construction of new divisions, installation of electrical systems and necessary adaptations to guarantee optimal operating conditions. Remodeling should follow all technical specifications stated on approved designs. All mechanical, electrical, and plumbing (MEP) systems shall be installed within the walls, floors, shafts, and/or above finished ceilings.
Exposed surface mounted plumbing and electrical components will only be approved on a case-by-case basis. Walls shall be plastered per commercial industry standards and cured before applying surface coatings. Contractor shall not deviate from the design approved by INL and the Client without their prior approval.
The contractor must execute all works in accordance with good civil engineering practices, technical standards applicable in Honduras (including criteria used by
FHIS and local building regulations), as well as international quality standards in interior works.
P a g e | 6
All materials must be new, of the highest quality and suitable for the intended use.
The use of defective materials, reused without authorization or that do not comply with technical specifications will not be allowed.
The contractor will be responsible for verifying on-site dimensions, existing conditions, and compatibility between systems before executing any activity.
The project shall be constructed according to the plans, specifications and the list of requirements provided below.
B.2 DESCRIPTION OF PRICES/COSTS
This is a Firm Fixed Price Contract. No additional sums will be payable due to escalation in the cost of materials, equipment, or labor. Nor will the contract price be adjusted on account of fluctuations in currency exchange rates.
Modifications to the contract pricing or duration of services shall be authorized by the Contracting Officer (CO). The Contractor shall not deviate from the terms of the contract. Any deviation by the Contractor without written documentation and authorization from the CO will put the Contractor at risk. The contract for this work will be awarded to the offeror that is technically acceptable at the best fixed price. The Contractor shall promptly notify the Contracting Officer of all matters that may result in either an increase or decrease in cost of the contract.
SECTION C – PERFORMANCE WORK STATEMENT
C.1. SCOPE
The Embassy of the United States of America in Tegucigalpa, through the
International Narcotics and Law Enforcement Agency (INL), is supporting with the setup of the new offices for an INL-supported unit.
C.1.1 PURPOSE
The objective of the project is to refurbish and secure an office space of an INL supported unit through the execution of architectural, electrical, hydrosanitary and technical interventions that meet the requirements defined by the project. The refurbishment will include office areas, secure communications infrastructure, evidence storage, meeting spaces, etc.
P a g e | 7
C.1.2 LOCATION OF WORK
Place of performance is in Tegucigalpa, Honduras. Exact location will be provided at the time of the award.
C.1.3 PERIOD OF PERFORMANCE
The Period of Performance for this requirement is 120 calendar days from the issuance of the Notice to Proceed. The Bidder is required to provide a Proposed
Construction Schedule that adheres to the estimated timeline. Deviations due to weather or site conditions from the Bidder's Proposed Construction Schedule will be reviewed and considered by the CO on a case by case basis.
C.1.4 APPLICABLE STANDARDS
The standards shown below are not all-inclusive but shall be used for project construction as appropriate:
i. American Concrete Institute (ACI)
ii. Portland Cement Association (PCA)
iii. American Welding Society (AWS)
iv. American Standards for Testing and Materials (ASTM)
v. American Institute for Steel Construction (AISC)
vi. Underwriters Laboratories (UL)
vii. National Electric Code (NEC)
viii. National Electrical Manufacturer Association (NEMA)
ix. National Fire Protection Association (NFPA)
x. Codigo Hondureño de la Construcción (CHOC-08)
C.1.5 SPECIAL REQUIREMENTS
• The Contractor shall recruit local suppliers and laborers. The recruitment of
Third Country Nationals shall not be applicable.
• The Contractor shall provide worker’s compensation insurance covering the performance period
• The price proposal shall be based on the drawings (copy attached) and technical specifications provided in this SOW. The Contractor shall be
P a g e | 8 responsible for completing the work according to the plans and details showed on the drawings. The quantities mentioned in the bill of quantities are not final and shall be verified and confirmed by the Contractor in compliance with the drawings: (See attached)
• Contractor shall submit a list of laborers and workers and copy of their IDs.
In any case where the contractor shall bring on new team members to the project, an updated list of names and ID will be approved by the COR.
C.1.6 MISCELLANEOUS: OTHER PROJECT CONSTRAINTS.
• No other constraints
C.2. PROJECT DESCRIPTION
The Contractor shall refurbish an approximate area of 335 m², including the demolition of existing elements, redistribution of spaces, construction of new divisions, installation of electrical systems and necessary adaptations to guarantee optimal operating conditions. Remodeling should follow all technical specifications stated on approved designs. All mechanical, electrical, and plumbing (MEP) systems shall be installed within the walls, floors, shafts, and/or above finished ceilings.
Exposed surface mounted plumbing and electrical components will only be approved on a case-by-case basis. Walls shall be plastered per commercial industry standards and cured before applying surface coatings. Contractor shall not deviate from the design approved by INL and the Client without their prior approval.
The contractor must execute all works in accordance with good civil engineering practices, technical standards applicable in Honduras (including criteria used by
FHIS and local building regulations), as well as international quality standards in interior works.
All materials must be new, of the highest quality and suitable for the intended use.
The use of defective materials, reused without authorization or that do not comply with technical specifications will not be allowed.
The contractor will be responsible for verifying on-site dimensions, existing conditions, and compatibility between systems before executing any activity.
The project shall be constructed according to the plans, specifications and the list of requirements provided below.
• Demolition, Dismantling, Rem1oval, and Disposal
P a g e | 9
• Architectural Works
• Doors
• Windows
• Electrical Installations
• Electrical Works
• Plumbing and Sanitary Installations
• Minor and Complimentary Works of the Project
• Manual Roller Shades
C.3. BILL OF QUANTITIES (BOQ)
COST ELEMENTS BREAKDOWN
ITEM REF.
DESCRIPTION OF THE
CONSTRUCTION ACTIVITIES
UNIT QUANTITY
UNIT
PRICE
COST
TOTAL
PRICE
COST ($)
CLIN 1 Demolition, Dismantling, Removal, and Disposal
1.1 Demolition and removal of existing floor system
1.1.1 Demolition and removal of existing floor
system m2 333.43
Sub-Total - Demolition and removal of existing floor system
1.2 Demolition and removal of existing gypsum board partitions
P a g e | 10
1.2.1 Demolition and removal of existing gypsum
board partitions m2 215.03
Sub-Total - Demolition and removal of existing gypsum board partitions
1.3 Dismantling and removal of existing suspended ceiling system
1.3.1 Dismantling and removal of existing
suspended ceiling system m2 333.43
Sub-Total - Dismantling and removal of existing suspended ceiling system
1.4 Removal and disposal of existing electrical installations
1.4.1 Removal and disposal of existing electrical
receptacles each 73.00
1.4.2 Removal and disposal of existing single-pole
switch each 19.00
1.4.3 Removal and disposal of existing double-pole
switch each 9.00
1.4.4 Removal and disposal of existing triple-gang
switch assembly each 2.00
1.4.5 Removal and disposal of existing 2x4 LED
panel fixture each 39.00
1.4.6 Removal and disposal of existing recessed
spotlight fixture each 17.00
1.4.7 Removal and disposal of existing electrical
panelboard each 3.00
1.4.8 Removal and disposal of existing electrical
wiring and conduit system lump sum 1.00
Sub-Total - Removal and disposal of existing electrical installations
1.5 Removal and disposal of existing air-conditioning installations
1.5.1 Removal and disposal of existing exhaust fans each 3.00
1.5.2 Removal and disposal of existing smoke
detectors each 2.00
1.5.3 Removal and disposal of existing air diffusers each 11.00
1.5.4 Removal and disposal of existing ductwork lump sum 1.00
Sub-Total - Removal and disposal of existing air-conditioning installations
1.6 Removal and disposal of existing IT installations
1.6.1 Removal and disposal of existing data outlet each 34.00
P a g e | 11
1.6.2 Removal and disposal of existing structured
cabling lump sum 1.00
Sub-Total - Removal and disposal of existing IT installations
1.7 Dismantling, removal, and proper disposal of existing doors
1.7.1 Dismantling, removal, and proper disposal of
P-1 (1.00m × 2.14m) each 1.00
1.7.2 Dismantling, removal, and proper disposal of
P-2 (1.06m × 2.13m) each 1.00
1.7.3 Dismantling, removal, and proper disposal of
P-3 (0.70m × 2.09m) each 4.00
1.7.4 Dismantling, removal, and proper disposal of
P-4 (1.08m × 2.12m) each 1.00
1.7.5 Dismantling, removal, and proper disposal of
P-5 (0.75m × 2.10m) each 3.00
1.7.6 Dismantling, removal, and proper disposal of
P-6 (0.80m × 2.10m) each 1.00
1.7.7 Dismantling, removal, and proper disposal of
P-7 (0.81m × 2.10m) each 1.00
1.7.8 Dismantling, removal, and proper disposal of
P-8 (0.96m × 2.08m) each 4.00
1.7.9 Dismantling, removal, and proper disposal of
P-9 (1.41m × 2.13m) each 1.00
1.7.10 Dismantling, removal, and proper disposal of
P-10 (1.84m × 2.12m) each 1.00
1.7.11 Dismantling, removal, and proper disposal of
P-11 (0.76m × 2.13m) each 1.00
1.7.12 Dismantling, removal, and proper disposal of
P-12 (0.81m × 2.08m) each 1.00
1.7.13 Dismantling, removal, and proper disposal of
P-13 (0.86m × 2.13m) each 1.00
1.7.14 Dismantling, removal, and proper disposal of
P-14 (0.79m × 2.02m) each 2.00
Sub-Total - Dismantling, removal, and proper disposal of existing doors
1.8 Dismantling, removal, and proper disposal of existing windows
1.8.1 Dismantling, removal, and proper disposal of
V2-01 (1.25m × 1.02m) each 2.00
1.8.2 Dismantling, removal, and proper disposal of
V2-02 (3.02m × 1.50m) each 1.00
P a g e | 12
1.8.3 Dismantling, removal, and proper disposal of
V2-03 (1.07m × 1.50m) each 2.00
1.8.4 Dismantling, removal, and proper disposal of
V2-04 (1.45m × 1.50m) each 1.00
1.8.5 Dismantling, removal, and proper disposal of
V3-01 (2.00m × 1.80m) each 2.00
1.8.6 Dismantling, removal, and proper disposal of
V3-02 (1.00m × 1.80m) each 1.00
Sub-Total - Dismantling, removal, and proper disposal of existing windows
TOTAL - DEMOLITION, DISMANTLING, REMOVAL, AND DISPOSAL
CLIN 2 ARCHITECTURAL WORKS
2.1 Walls
2.1.1
Drilling and anchoring in existing slab, including installation of 3/8" rebar anchor pins with epoxy adhesive, minimum embedment depth 5 cm, spaced at 30 cm
Global 1.00
2.1.2
Construction of lower beam (15×25 cm), reinforced with #4 and #3 bars @ 15 cm, including side formwork, concrete placement, and curing ml 1.23
2.1.3
Construction of reinforced concrete columns
(15×15 cm), reinforced with #4 and #3 bars @
20 cm, anchored to slab with epoxy (minimum
5 cm embedment), including side formwork and concrete placement ml 4.90
2.1.4
Construction of 8" concrete block walls, reinforced with 1#3 @ every 2 cores and 1#3
@ every 3 horizontal ties m2 3.85
2.1.5
Construction of upper beam (15×15 cm), reinforced with #4 and #3 bars @ 15 cm, including side formwork, concrete placement, and curing ml 1.23
2.1.6 Construction of regular gypsum board walls m2 132.26
2.1.7 Construction of moisture-resistant gypsum
board walls (Durock) m2 13.01
Sub-Total - Walls
2.2 Finishes
2.2.1 Cement–sand plaster on concrete block walls, mortar mix 1:4 (cement:sand) m2 3.85
P a g e | 13
2.2.2 Smooth finish on concrete block walls using
pre-mixed compound m2 3.85
2.2.3
Ceramic wall tile installation in kitchen walls, 30×60 cm format, semi-gloss finish, 8–10 mm thickness, installed with porcelain adhesive and epoxy grout m2 6.05
2.2.4
Ceramic wall tile installation for shower walls, 30×60 cm or 25×40 cm format, light anti-slip or matte finish, 8–10 mm thickness, installed with porcelain adhesive and moisture-resistant epoxy grout m2 12.60
Sub-Total - Finishes
2.3 Floor Finishes
2.3.1
Porcelain floor tile PURE/POLAR WHITE, 60×60 cm, 7–9 mm thickness, installed with porcelain-grade adhesive and recommended grout, glossy finish, high-traffic, low-absorption m2 333.43
2.3.2
Non-slip ceramic floor tile, unspecified format, installed with ceramic-grade adhesive and recommended grout, beige or cream color m2 11.68
2.3.3 Shower curbs (includes installation of non-slip
ceramic tile) ml 2.12
2.3.4 Floor baseboard (interior areas) ml 181.71
2.3.5 10 cm sanitary baseboard ml 12.11
Sub-Total - Floor Finishes
2.4 Ceiling Finishes
2.4.1
Supply and installation of suspended ceiling system with gypsum–mineral fiber tiles, 2×2 ft panels m2 333.43
2.4.2 30 mm glass wool thermal-acoustic insulation m2 333.43
Sub-Total Ceiling Finishes
2.5 Wall Painting
2.5.1 High-standard eggshell or satin finish paint for
interior walls m2 481.70
Sub-Total - Wall Painting
TOTAL ARCHITECTURAL WORKS
CLIN 3 DOORS
P a g e | 14
3.1
Supply and installation of Door P-1, steel swing door, natural finish or as per project specification, high-strength type for main access. Includes steel frame, reinforced leaf, hydraulic arm (door closer), lockset, bar-type pull handle, and heavy-duty pivot set.
Armored type. Height: 2.10 m, Width: 1.00 m
(single leaf).
each 1.00
3.2
Supply and installation of Door P-2, aluminum frame and sub-frame, black color, with 1/4" thick reflective privacy glass on one side.
Includes hydraulic arm, security lockset with nylon handle, and stainless-steel pull handle.
Height: 2.10 m, Width: 1.00 m (single leaf).
each 2.00
3.3
Supply and installation of Door P-3, wooden sub-frame and jambs, thermoformed metal leaf with smooth appearance, three 3" hinges, lockset with latch and stainless-steel handle.
Door sub-frame width shall match finished wall thickness. Height: 2.10 m, Width: 1.00 m
(single leaf).
each 2.00
3.4
Supply and installation of Door P-4, aluminum frame and sub-frame, black color, with 1/4" thick reflective privacy glass on one side.
Includes hydraulic arm, security lockset with nylon handle, and stainless-steel pull handle.
Height: 2.10 m, Width: 1.95 m (double swing door).
each 1.00
3.5
Supply and installation of Door P-5, aluminum frame and sub-frame, black color, with 1/4" thick natural glass and sandblast stripe finish.
Includes hydraulic arm, security lockset with nylon handle, and stainless-steel pull handle.
Height: 2.10 m, Width: 0.90 m (single leaf).
each 5.00
3.6
Supply and installation of Door P-6, aluminum frame and sub-frame, black color, with 1/4" thick natural glass and sandblast stripe finish.
Includes hydraulic arm, security lockset with nylon handle, and stainless-steel pull handle.
Height: 2.10 m, Width: 1.00 m (single leaf).
P a g e | 15
3.7
Supply and installation of Door P-7, wooden sub-frame and jambs, thermoformed metal leaf with smooth appearance, three 3" hinges, lockset with latch and stainless-steel handle.
Door sub-frame width shall match finished wall thickness. Height: 2.10 m, Width: 0.90 m
(single leaf).
each 2.00
3.8
Supply and installation of Door P-8, wooden sub-frame and jambs, thermoformed metal leaf with smooth appearance, three 3" hinges, lockset with latch and stainless-steel handle.
Door sub-frame width shall match finished wall thickness. Height: 2.10 m, Width: 0.71 m
(single leaf).
each 2.00
3.9
Supply and installation of Door P-9, wooden sub-frame and jambs, thermoformed metal leaf with smooth appearance, three 3" hinges, lockset with latch and stainless-steel handle.
Door sub-frame width shall match finished wall thickness. Height: 2.10 m, Width: 0.80 m
(single leaf).
each 2.00
3.1
Supply and installation of Door P-10, aluminum frame and sub-frame, black color, with 1/4" thick natural glass and sandblast stripe finish. Both leaves slide over each other, with recessed hook lockset and stainless-steel handle, plus recessed aluminum pull handle on both doors. Height: 2.10 m, Width: 2.00 m
(double sliding door).
each 2.00
TOTAL - DOORS
CLIN 4 WINDOWS
4.1
Supply and installation of Window V-01, heavy-duty aluminum frame and sub-frame, black color, with 1/4" thick natural glass and sandblast stripe finish, two-section window.
Height: 2.45 m, Width: 2.60 m.
each 2.00
4.2
Supply and installation of Window V-02, heavy-duty aluminum frame and sub-frame, black color, with 1/4" thick natural glass and sandblast stripe finish, three-section window.
Height: 2.45 m, Width: 3.50 m.
P a g e | 16
4.3
Supply and installation of Window V-03, heavy-duty aluminum frame and sub-frame, black color, with 1/4" thick natural glass and sandblast stripe finish, two-section window.
Height: 2.45 m, Width: 3.17 m.
each 1.00
4.4
Supply and installation of Window V-04, heavy-duty aluminum frame and sub-frame, black color, with 1/4" thick natural glass and sandblast stripe finish, three-section window.
Height: 2.45 m, Width: 3.91 m.
each 1.00
4.5
Supply and installation of Window V-05, heavy-duty aluminum frame and sub-frame, black color, with 1/4" thick natural glass and sandblast stripe finish, two-section window.
Height: 2.45 m, Width: 2.09 m.
each 1.00
4.6
Supply and installation of Window V-06, heavy-duty aluminum frame and sub-frame, black color, with 1/4" thick natural glass and sandblast stripe finish, three-section window.
Height: 2.45 m, Width: 4.14 m.
each 1.00
TOTAL - WINDOWS
CLIN 5 ELECTRICAL INSTALLATIONS
5.1
Supply and installation of electrical service connection from the building’s main panelboard to the project lump sum 1.00
5.2 Supply and installation of main disconnect
switch for project power supply lump sum 1.00
5.3 Supply and installation of feeder for lighting
panelboard (24 spaces) lump sum 1.00
5.4 Supply and installation of lighting panelboard
(24 spaces) each 1.00
5.5 Supply and installation of feeder for power
panelboard (36 spaces) lump sum 1.00
5.6 Supply and installation of power panelboard
(36 spaces) each 1.00
5.7 Supply and installation of lighting fixture Type
“A” each 33.00
5.8 Supply and installation of lighting fixture Type
“B” each 32.00
5.9 Supply and installation of lighting fixture Type
“F” each 8.00
P a g e | 17
5.1 Supply and installation of outlet box for
single-pole switch each 11.00
5.11 Supply and installation of outlet box for
double switch each 6.00
5.12 Supply and installation of outlet box for 3-way
switch each 10.00
5.13
Supply and installation of metal outlet box, conduit, wiring, and standard duplex receptacle (TD Duplex), including faceplate, accessories, and functional testing each
40.00
5.14
Supply and installation of metal outlet box, conduit, wiring, and isolated-ground duplex receptacle (TD IG), including faceplate, accessories, and functional testing each 54.00
5.15
Supply and installation of metal outlet box, conduit, wiring, and dedicated duplex receptacle (TD Dedicated), with independent circuit from the distribution panel, including faceplate and functional testing each 5.00
5.16
Supply and installation of metal outlet box, conduit, wiring, and 220V dedicated receptacle (TD/ST 220), including faceplate, protections, and functional testing each 3.00
5.17
Supply and installation of metal outlet box, conduit, wiring, and GFCI duplex receptacle
(TD GFCI), including faceplate and functional testing each 6.00
5.18
Supply and installation of metal outlet box, conduit, wiring, and isolated-ground GFCI duplex receptacle (TD IG GFCI), including faceplate and functional testing each 3.00
5.19
Supply and installation of metal outlet box, conduit, CAT 6e structured cabling, RJ-45 connector, faceplate, and labeling in accordance with TIA/EIA-568 standards, including continuity testing each 53.00
5.20
Supply and installation of Wall-Mounted
Water Heater (on-demand type) for shower area, including mounting hardware, electrical connection, hydrosanitary connection, safety valve, and functional testing each 2.00
P a g e | 18
5.21
Supply and installation of Electric Water
Heater for Kitchenette sink, including mounting hardware, electrical connection, hydrosanitary connection, safety valve, and functional testing each 1.00
TOTAL ELECTRICAL INSTALLATIONS
CLIN 6 PLUMBING AND SANITARY INSTALLATIONS
6.1
Supply and installation of new lavatory, including removal of existing unit, installation of faucet, trap, control valves, sanitary seals, and connection to existing piping (Bathrooms
1 and 2) each 2.00
6.2
Supply and installation of new toilet, including removal of existing unit, sanitary seal, supply valve, seat, accessories, and connection to existing piping (Bathrooms 1 and 2) each 2.00
6.3
Supply and installation of new lavatory with faucet, trap, control valves, accessories, and connection to cold-water and drainage piping, including short PVC/CPVC pipe section as per design (Bathrooms 3 and 4) each 2.00
6.4
Supply and installation of new toilet with sanitary seal, supply valve, seat, accessories, and connection to existing piping, including short PVC pipe section for drainage if applicable (Bathrooms 3 and 4) each 2.00
6.5
Supply and installation of complete shower system, including mixer valve, shower arm, showerhead, control valves, access box, connection to cold and hot water piping (if applicable), and drainage with trap and PVC piping, maximum length 3 m as per design each 2.00
6.6
Supply and installation of waterproofing membrane on shower walls and floor, applied in two coats, moisture-resistant and compatible with ceramic tile lump sum 1.00
TOTAL - PLUMBING AND SANITARY INSTALLATIONS
CLIN 7 MINOR AND COMPLEMENTARY WORKS OF THE PROJECT
7.1
Construction of kitchenette (Kitchen cabinet shall be provided and installed according to the measurements shown in the blueprint, including a preformed high-pressure Formica
1.00
P a g e | 19 worktop, lower kitchen cabinet with doors, sink basin and accessories, wall-mounted upper cabinet, and open microwave space.
Cabinetry shall be finished in wood or solid-color LPAP, include post-formed top with backsplash/fender, internal shelves, stainless-steel metal fixing accessories, door pulls/knockers, with all materials new, durable, cleanable, moisture-resistant, and suitable for office kitchenette use.)
7.2
Construction of bathroom sink basin with shower area
2.00
TOTAL - MINOR AND COMPLEMENTARY WORKS OF THE PROJECT
CLIN 8 MANUAL ROLLER SHADES
8.1
Supply and installation of manual roller shades
(Sunscreen/Blackout), including manual mechanisms, metal brackets, bottom bar, and accessories, for existing perimeter windows.
Installation will depend on the final configuration of gypsum board office partitions. Measurements shall follow existing window sections or permissible lengths for proper roller shade operation m2 80.00
CLIN 9 HVAC SYSTEM
9.1 CONDENSING UNIT
9.1.1
Supply and installation of a VRF type condensing unit under AHRI standard regulations. UC‐01 electrical specifications
208/230V‐60HZ‐3ph, refrigerant R‐410a. LG brand, model ARUV241BTE (Similar or superior to reference brand). Includes support bases, electrical connections, control connections, copper pipe connections, coolant charge, neoprene type anti-vibrators, labeling, testing and adjustment. All as indicated in plans, equipment table and technical specifications.
Lot 1.00
Sub-Total - Condensing Unit
9.2 EVAPORATOR UNITS-UC-01
P a g e | 20
9.2.1
Supply and installation of cassette evaporator unit type VRF nomenclature CS‐01, CS-02, CS-03, CS-10, CS-07. LG brand, model
ARNU18GTTB4 (Similar or superior to reference brand and model). With electrical specifications of 230V‐60Hz‐1ph. Includes mounting, brackets, electrical and control connections, labeling, functional testing and final adjustment. All work will be carried out in accordance with the plans, equipment table and technical specifications.
each 5.00
9.2.2
Supply and installation of evaporator unit
Cassette type VRF nomenclature CS-08, CS‐
11. LG brand, model ARNU12GTUB4
(Similar or superior to reference brand and model). With electrical specifications of 230V‐
60Hz‐1ph. Includes mounting, brackets, electrical and control connections, labeling, functional testing and final adjustment. All work will be carried out in accordance with the plans, equipment table and technical specifications.
each 2.00
9.2.3
Supply and installation of evaporator unit
Cassette type VRF nomenclature CS-04, CS-
06. LG brand, model ARNU24GTBB4
(Similar or superior to reference brand and model). With electrical specifications of 230V‐
60Hz‐1ph. Includes assembly, brackets, electrical and control connections, labeling, functional testing and final adjustment. All work will be carried out in accordance with the plans, equipment table and technical specifications.
each 2.00
P a g e | 21
9.2.4
Supply and installation of evaporator unit
Cassette type VRF nomenclature CS‐05. LG brand, model ARNU48GTAB4 (Similar or higher than reference brand and model).
With electrical specifications of 230V‐60Hz‐
1ph. Includes mounting, brackets, electrical and control connections, labeling, functional testing and final adjustment. All work will be carried out in accordance with the plans, equipment table and technical specifications.
each 1.00
9.2.5
Supply and installation of evaporator unit
Cassette type VRF nomenclature CS‐09. LG brand model ARNU36GTAB4 (Similar or superior to reference brand and model).
With electrical specifications of 230V‐60Hz‐
1ph. Includes mounting, brackets, electrical and control connections, labeling, functional testing and final adjustment. All work will be carried out in accordance with the plans, equipment table and technical specifications.
each 1.00
9.2.6
Supply and installation of ø 1/4" diameter flexible copper pipe. Haike brand. Includes mounting, 3/4" thick thermal insulation, bracket, fittings, nitrogen oxyacetylene welding, leak testing, vacuum testing, and adjustments. All as indicated in plans, equipment table and technical specifications.
Ft 80.70
9.2.7
Supply and installation of ø 3/8" diameter type
L ACR copper pipe. Haike brand. Includes mounting, 3/4" thick thermal insulation, bracket, fittings, nitrogen oxyacetylene welding, leak testing, vacuum testing, and adjustments. All as indicated in plans, equipment table and technical specifications.
Ft 126.00
P a g e | 22
9.2.8
Supply and installation of ø 1/2" diameter type
L ACR copper pipe. Haike brand. Includes mounting, 3/4" thick thermal insulation, bracket, fittings, nitrogen oxyacetylene welding, leak testing, vacuum testing, and adjustments. All as indicated in plans, equipment table and technical specifications.
Ft 84.40
9.2.9
Supply and installation of ø 5/8" diameter ø L-type ACR copper pipe. Haike brand. Includes mounting, 3/4" thick thermal insulation, bracket, fittings, nitrogen oxyacetylene welding, leak testing, vacuum testing, and adjustments. All as indicated in plans, equipment table and technical specifications.
Ft 92.20
9.2.10
Supply and installation of ø 3/4" diameter type
L ACR copper pipe. Haike brand. Includes mounting, 3/4" thick thermal insulation, bracket, fittings, nitrogen oxyacetylene welding, leak testing, vacuum testing, and adjustments. All as indicated in plans, equipment table and technical specifications.
Ft 36.70
9.2.11
Supply and installation of ø 7/8" diameter ø L-type ACR copper pipe. Haike brand. Includes mounting, 3/4" thick thermal insulation, bracket, fittings, nitrogen oxyacetylene welding, leak testing, vacuum testing, and adjustments. All as indicated in plans, equipment table and technical specifications.
Ft 15.70
9.2.12
Supply and installation of ø 1 1/8" diameter L-type ACR copper pipe. Haike brand. Includes mounting, 3/4" thick thermal insulation, bracket, fittings, nitrogen oxyacetylene welding, leak testing, vacuum testing, and adjustments. All as indicated in plans, Ft 3.60
P a g e | 23
9.2.13
Supply and installation of ø 1 3/8" diameter type L ACR copper pipe. Haike brand. Includes mounting, 3/4" thick thermal insulation, bracket, fittings, nitrogen oxyacetylene welding, leak testing, vacuum testing, and adjustments. All as indicated in plans, equipment table and technical specifications.
Ft 18.00
9.2.14
Wireless remote control supply and programming. LG brand model PWLSSB21C
(Similar or superior to reference brand and model).
each 11.00
Sub-Total - Evaporator Units-UC-01
9.3 SERVER AREA
9.3.1
Supply and installation of 24,000 BTU MS-01 split wall air conditioner . LG frame model
VK242C31 (Similar or superior to reference brand and model). With electrical specifications of 230V‐60Hz‐1ph. Includes installation of condenser and evaporator assembly, installation of refrigeration circuit
(consider 60 ft distance between evaporator and condenser), installation of drain, brackets, electrical and control connections, labeling, functional tests and final adjustment. All work will be carried out in accordance with the plans, equipment table and technical specifications.
each 1
Sub-Total - Server Areas
9.4
EXTRACTION AND INJECTION
SYSTEM
9.4.1
HR-01 heat exchanger system. SICFLUX brand model CRS-200 of 300 CFM (Similar or superior to reference brand and model) for injection and extraction. With electrical specifications of 230V‐60Hz‐1ph. Includes mounting, brackets, electrical and control connections, labeling, functional testing and final adjustment. All as indicated in plans, Lot 1
P a g e | 24
9.4.2
Supply and installation of injection duct batch for the HR‐01 unit. manufactured with rigid polyisocyanurate (PIR) foam panel coated with aluminum foil on both sides, 1" thick. Includes shoes, reductions, elbows, Lump
Sum support, putty, and DB-01 balance dampers. All as indicated in plans, equipment table and technical specifications.
9.4.3
Supply and installation of exhaust duct batch for the HR‐01 unit. manufactured with rigid polyisocyanurate (PIR) foam panel coated with aluminum foil on both sides, 1" thick. Includes shoes, reductions, elbows, support, putty, and DB-01 balance dampers. All as indicated in plans, equipment table and technical specifications.
9.4.4
Supply and installation of a batch of flexible ducts of ø6" in diameter. Includes supports, connection bands. Includes system balancing.
All as indicated in plans, equipment table and technical specifications.
9.4.5
Supply and installation of a batch of flexible ducts of ø4" in diameter. Includes supports, connection bands. Includes system balancing.
All as indicated in plans, equipment table and technical specifications.
Sub-Total - Extraction and Injection System
9.5 DIFFUSERS, GRILLES AND LOUVERS
9.5.1
Supply and installation of DR-01 round diffuser. SICFLUX brand model RVA 4"
(Similar or superior to reference brand and model).
Lump
Sum
Includes box for installation with the same specifications as the duct, brackets. All as indicated in plans, equipment table and technical specifications.
P a g e | 25
9.5.2
Supply and installation of DR-02 round diffuser. SICFLUX brand model RVA 6"
(Similar or superior to reference brand and model).
Includes box for installation with the same specifications as the duct, brackets. All as indicated in plans, equipment table and technical specifications.
9.5.3
Supply and installation of RE-01 extraction grid. AIRGUIDE brand model RA 6"x6"
(Similar or superior to reference brand and model). Includes box for installation with the same specifications as the duct, brackets. All as indicated in plans, equipment table and technical specifications.
9.5.4
Supply and installation of RD-01 ejection grid.
Brand AIRGUIDE model HV
12"x12"(Similar or superior to reference brand and model). Includes box for installation with the same specifications as the duct, brackets. All as indicated in plans, equipment table and technical specifications.
9.5.5
Supply and installation of louver LV-01 .
AIRGUIDE brand model OL2-FLANGE J
12"x12". Includes box for installation with the same specifications as the duct, brackets. All as indicated in plans, equipment table and technical specifications.
Sub-Total - Diffusers, Grilles and Louvers
9.6 DRAINAGE PIPE NETWORK
9.6.1
Supply and installation of schedule 40 PVC drainage network. Includes all diameters and accessories, condensate traps, connection to all evaporators, 1/2" thick thermal insulation, bracket, accessories, leak testing and adjustments. All as indicated in plans, equipment table and technical specifications.
Lot 1
Sub-Total - Drainage Pipe Network
9.7 CONTROL CIRCUIT
P a g e | 26
9.7.1
Supply and installation of centralized intelligent control for VRF system, includes, color LCD touch screen, weekly time programming, individual monitoring and control by zones, real-time alarms and diagnostics, friendly interface with intuitive navigation, BMS network connection (Modbus
/ BACnet available). includes control cable, EMT piping, electrical boxes, BX type ducting in the connection to equipment, support, control connections, labeling, testing and adjustments, all as indicated in drawings, equipment table and technical specifications of the project.
Lot 1
9.7.2
Supply and installation of control circuit for all
VRF system units, thermostats and central controller. Includes control cable, EMT pipe, electrical boxes, Bx type ducting in the connection to equipment, support, control connections, labeling, testing and adjustment.
All as indicated in plans, equipment table and technical specifications.
Lot 1
Sub-Total - Control Circuit
9.8 VOLTAGE MONITORS
9.8.1 Supply and installation of three-phase voltage
monitor for capacitor.
each 1
9.8.2 Supply and installation of single-phase voltage
monitor for evaporator.
each 12
Sub-Total - Voltage Monitors
9.9 MAINTENANCE
9.9.1
Preventive maintenance for VRF system installed at the American Embassy Office in location to be provided to the award recipient.
Every 3 months for one year.
Visits 4
Sub-Total - Maintenance
TOTAL HVAC SYSTEM
CLIN 10 EMERGENCY AND LIFE SAFETY SYSTEMS
10.1
Supply and installation of portable fire extinguisher, ABC type, 10 lbs, including wall bracket, identification label, and placement according to NFPA 10 each 6.00
P a g e | 27
10.2
Supply and installation of illuminated emergency exit sign with LED lighting and built-in backup battery (minimum 90 minutes), including mounting hardware and functional testing each 15.00
10.3
Supply and installation of LED emergency light with dual adjustable heads and integrated backup battery (minimum 90 minutes), including mounting hardware and functional testing each 25.00
10.4
Supply and installation of photoelectric smoke detector, 24V or standalone as required, including base, wiring or battery, and functional testing according to NFPA 72 each 20.00
10.5
Supply and installation of fixed-temperature heat detector for kitchen area, including base, wiring or battery, and functional testing according to NFPA 72 each 1.00
10.6
Supply and installation of wall-mounted or ceiling-mounted exhaust fan, including ducting (if required), electrical connection, mounting hardware, and functional testing each 8.00
TOTAL EMERGENCY AND LIFE SAFETY SYSTEMS
CLIN 11 DBA INSURANCE
11.1 DBA Insurance $10,000.00
Contact Information: SUBTOTAL $0.00
Date: Taxes (Exempt) $0.00
Signature: Overhead/Profit $0.00
TOTAL $0.00
C.3.1. PRE-PROPOSAL SITE VISIT
Prior to submitting the price proposal, and in coordination with the COR, the
Contractor shall visit the site for the verification of the design and construction practicality of the project. All measurements provided in this solicitation are estimates. The contractor is responsible for verifying all measurements by taking field measurements, confirm all necessary measurements and quantity takeoffs, discuss and request needed clarifications to develop the proposal and the BoQ.
Any substantial discrepancies between estimates provided in this document and field measurements that could alter the contract price must be reported immediately to the CO.
P a g e | 28
C.3.2. OTHER SITE VISIT
a. The initial site visit shall be conducted in conjunction with either the CO or the COR.
b. The final visit will be initiated upon completion of the project. The focus of the final visit is to verify the quality of work and that the work was performed in compliance with the contract documents and design drawings as approved by CO.
C.4. DELIVERABLES
Deliverable Section Due Date Frequency Distribution
CLIN 1 - Demolition, Dismantling, Removal and Disposal
C.4.2.
No later than 120 days after NTP
In accordance with the due date
INL COR
CLIN 2 - Architectural
Works
C.4.3.
after NTP
In accordance with the due date
INL COR
CLIN 3 - Doors
C.4.4.
after NTP
In accordance with the due date
CLIN 4 - Windows
C.4.5.
after NTP
In accordance with the due date
INL COR
CLIN 5 - Electrical
Installations
C.4.6.
after NTP
In accordance with the due date
INL COR
CLIN 6 - Plumbing and
Sanitary Installations
C.4.7.
after NTP
In accordance with the due date
INL COR
CLIN 7 - Minor and
Complementary Works of the Project
C.4.8.
after NTP
In accordance with the due date
INL COR
CLIN 8 - Manual Roller
Shades
C.4.9.
after NTP
In accordance with the due date
CLIN 9 – HVAC System
C.4.10.
after NTP
In accordance with the due date
INL COR
CLIN 10 – Emergency and Life Safety System
C.4.11.
after NTP
In accordance with the due date
INL COR
CLIN 11 - DBA
Insurance
C.4.12.
30 days after Contract award
In accordance with the due date
P a g e | 29
C.4.1. DOCUMENTS PROVIDED FOR INFORMATIONAL PURPOSES
The Employer shall provide the contractor with a complete package of construction drawings and technical documents that are an integral part of this project, which contain the information necessary for the proper execution of the activities.
The blueprint set includes, but is not limited to:
• A-01 Existing Condition Plan Demolition plans of floors, walls and false ceiling
• A-02 Gypsum Board Wall Demolition Plan Plans of existing electrical installations
• A-03 Existing Floor Demolition Plan Intervention construction plans
• A-04 Door and Window Removal, Dismantling, and Final Disposal Plan
Lighting and control plans
• A-05 Existing Suspended Ceiling Removal Plan
• A-06 Existing Electrical System Uninstallation Plan
• A-07 Proposed Architectural Plan
• A-08 Proposed Construction Plan
• A-09 Suspended Ceiling Installation Plan
• A-10 Lighting and Control Electric Plan
• A-10.1 (Technical Details of Electrical, Lighting, and Control Installations
• A-11 Electrical Power Plan
• A-11.1 Electrical Load Schedule and Technical Notes
• A-12 Floor Finish Plan
• A-13 Fire and Evacuation Plan
• A-14 Door Details and Hardware Schedule
• A-14.1 Door Hardware Details and Technical Notes
• A-15 Window Details and Schedule
• A-16 Hydro sanitary Plan
• A-17 HVAC Drainage and Control Plan
• A-18 HVAC Refrigerant Circuit Plan
• A-19 HVAC Ventilation System Plan
• A-20 HVAC Construction Details
• A-21 HVAC Equipment Schedule
P a g e | 30
These documents contain technical details, construction criteria, symbology, load charts and engineering guidelines that must be considered during the execution of the project. The contractor shall be responsible for reviewing, interpreting, and verifying all information contained in these documents prior to commencing work.
C.4.2. CLIN 1 - Demolition, Dismantling, Removal and Disposal
The Contractor shall execute all demolition, dismantling, and removal activities as a controlled and sequential technical process aimed at preparing the project area for new construction works. These activities shall include, but not be limited to, the demolition of existing floor finishes, gypsum board partitions, suspended ceilings, and the removal of electrical, IT, doors, windows, and associated systems.
Execution shall be carried out in a manner that prevents damage to the structural elements of the building, including slabs, columns, and beams, as well as any systems that are to remain operational. The Contractor shall perform a prior site verification to identify existing conditions, active systems, and potential interferences, ensuring that all removals are executed safely and without unintended impacts.
Demolition of floor finishes shall include the complete removal of all layers down to a sound substrate, ensuring that no residual materials remain that could affect the adhesion of new finishes. The process shall be performed using controlled methods to avoid structural vibrations or surface damage.
Dismantling of gypsum board walls shall be executed progressively, beginning with the removal of embedded electrical and data systems, followed by panels and supporting metal framing. All anchoring elements and residues shall be removed, leaving surfaces clean and ready for subsequent works.
The removal of suspended ceilings shall be carried out systematically, ensuring that all integrated systems such as lighting, ductwork, and wiring are identified prior to removal. Panels and structural components shall be dismantled in a controlled manner to prevent accidental detachment or damage.
Electrical and IT systems shall be removed only after verification of de-energization, ensuring safety at all times. All components, including conduits, wiring, devices, and accessories, shall be fully removed.
P a g e | 31
Doors and windows shall be carefully dismantled to avoid damage to structural openings. Their final disposition shall be determined solely by the Employer.
All waste materials shall be handled in accordance with building regulations, ensuring proper containment, transportation, and disposal in authorized locations.
The Contractor shall coordinate logistics for waste removal, including the controlled use of elevators or emergency stairways, ensuring compliance with load limitations and protection of building infrastructure.
Hazardous Materials Investigation
No intrusive hazardous material survey has been performed as part of this project.
Based on visual inspection, no evidence of damaged asbestos-containing materials, lead paint deterioration, mold, pipe insulation deterioration, or other hazardous building materials was observed within the intervention area.
If any suspect hazardous material is encountered during demolition or construction activities, the Contractor shall immediately stop work in the affected area, notify the
COR, and shall not resume work until written authorization is provided. Handling, removal, transportation, and disposal of hazardous materials shall comply with applicable Honduran regulations and internationally accepted safety practices.
C.4.3. CLIN 2 - Architectural Works
The Contractor shall execute all architectural construction works required to develop the new spatial configuration of the project, including structural and non-structural elements, partitions, finishes, and integration of systems.
The construction of reinforced masonry walls shall be carried out as a structural extension anchored to the existing slab. This shall involve drilling and installing reinforcing steel bars using structural epoxy adhesives, ensuring proper load transfer between new and existing elements. Concrete elements such as tie beams and columns (soleras and castillos) shall be constructed using appropriate formwork, controlled material quality, and proper curing procedures to ensure structural integrity.
Gypsum board partitions shall be constructed as complete modular systems consisting of galvanized metal framing, double-sided panels, internal reinforcements, and fully treated joints. The Contractor shall coordinate all embedded installations prior to closing the walls, ensuring that electrical conduits, devices, and other systems are properly integrated.
P a g e | 32
Cement board (durock) walls shall be installed in wet areas such as bathrooms, using moisture-resistant materials and corrosion-resistant fasteners. All joints shall be properly treated, and the system shall be prepared to receive ceramic finishes.
Floor finishes shall be installed over properly prepared substrates, ensuring that surfaces are level, clean, and free of voids. Porcelain tiles shall be installed using appropriate adhesives and spacing systems, guaranteeing alignment, uniform joints, and long-term durability. No installation shall proceed without prior approval of materials, colors, and finishes by the Employer.
Ceramic finishes in bathrooms shall include anti-slip flooring and wall tiles, installed using suitable mortars and adhesives, ensuring proper bonding and resistance to moisture.
Suspended ceilings shall be installed at the design height, approximately 2.45 meters, using a metal suspension system and modular panels. The installation shall be coordinated with electrical and HVAC systems to ensure all components are in place prior to closing the ceiling. The system shall allow accessibility for maintenance and remain free of deflections.
Painting works shall be executed using high-quality acrylic latex paint, suitable for interior environments, ensuring durability, uniform finish, and ease of maintenance.
All surfaces shall be properly prepared, including sealing and priming, prior to final application.
C.4.4. CLIN 3 – Doors
The Contractor shall supply and install all doors required for the project, ensuring proper alignment, leveling, and functionality in accordance with the design requirements.
Doors shall be installed considering actual site conditions, including finished wall thicknesses, floor levels, and structural supports. Installation shall ensure proper anchorage to surrounding elements, particularly in cases where doors are integrated into reinforced walls.
All hardware, including hinges, locks, handles, and accessories, shall be installed in accordance with manufacturer specifications, ensuring durability and smooth operation. Special doors, such as security or reinforced doors, shall be properly integrated into structural elements to guarantee stability and performance.
P a g e | 33
C.4.5. CLIN 4 - Windows
The Contractor shall supply, fabricate (if applicable), and install all window systems required for the project, including fixed glass panels, framed windows, and any associated aluminum or metal profiles, in accordance with the architectural design and project drawings.
All window installations shall be executed considering actual site conditions, including wall thickness, finished floor levels, and structural openings. Prior to installation, the Contractor shall verify all dimensions in the field to ensure proper fitting and alignment with surrounding elements.
Window systems shall be installed plumb, level, and square, ensuring proper anchorage to the structural or partition elements.