This is a Statement of Work (SOW) for storm drain repair at the James A. Garfield National Historic Site in Mentor, Ohio. The National Park Service requires a contractor to perform comprehensive storm drainage system maintenance, including locating and releasing catch basin lids, removing debris from catch basin sumps, camera inspecting storm sewer main and branch lines, identifying abnormalities, hydro jetting lines to remove debris, and conducting dye tests on downspouts as needed. The project involves 5 total catch basins and must be completed within 45 calendar days after contract award.

The solicitation (Number 140P6425Q0038) is a 100% small business set-aside with a $19M size standard under NAICS code 238220. The contract will be a firm-fixed price commercial contract with an anticipated award in May/June 2025. Contractors must be registered in the System for Award Management (SAM), have a Unique Entity Identifier, and submit product/material specifications with their quote by the May 12, 2025 response deadline. The project requires compliance with various federal standards, including state and local codes, Uniform Building Code, OSHA regulations, and manufacturer specifications.

View the file

Other files

File Type Posted
Grading-Drainage_Plan.pdf PDF
Wage_Determination_-_Lake_Co.pdf PDF
Provisions_to_be_Completed.pdf PDF
Sol_140P6425Q0038.pdf PDF
Technical_Questionnaire.pdf PDF
Technical_Questionnaire.docx DOCX document
Price_Schedule_-_Storm_Drain_Repair.pdf PDF
Price_Schedule_-_Storm_Drain_Repair.xlsx XLSX spreadsheet
Mechanical-Utilities_Plan.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

JAMES A. GARFIELD NATIONAL

HISTORIC SITE

MENTOR, OHIO

STATEMENT OF WORK:

Storm Drain Repair

DATED: 2 April 2025

NATIONAL PARK SERVICE

INTERIOR REGIONS 3/4/5

OHIO MAJOR ACQUISITION BUYING OFFICE

Page | 2

TABLE OF CONTENTS

Service General Requirements

Service General Requirements

PART 1 – GENERAL

ITEM 1 – LOCATION AND DESCRIPTION OF WORK

ITEM 2 - EXISTING UTILITIES

ITEM 3 - CONTRACTOR’S USE OF PREMISES

ITEM 4 - EXAMINATION OF THE SITE

ITEM 5 – SUBMITTALS

ITEM 6 – TEMPORARY SERVICES

ITEM 7 - PROJECT CLOSEOUT

ADDITIONAL INFORMATION, DRAWINGS and PHOTOGRAPHS

A. Additional Information (End of Document) B. Pictures/Drawings (End of Document)

Page | 3

SERVICE GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 – LOCATION AND DESCRIPTION OF WORK

1.1 In 2018 Park Service employees at James A. Garfield National Historic Site observed storm water pooling in multiple locations on the grounds because of poor drainage somewhere within the system. Over the course of time, and the occasional deluge, the system is still slow to drain, oftentimes taking several days for the affected areas to dry out. It is recommended to have all catch basins and drains on property hydro jetted and video inspected for future projects. Copy of site drainage and mechanical site utilities plan will be provided to contractor by NPS employee – please see attachments.

1.2 Work Covered by the Contract Documents:

A. Project Location:

James A. Garfield National Historic Site 8095 Mentor Ave Mentor, OH 44060 County: Lake

Work consists of: The Contractor shall provide all labor, materials, tools and other equipment necessary to perform the following services:

• Locate each catch basin. (5 total)

• Release the catch basin lids if stuck or frozen.

• Remove/vacuum debris from catch basin sump.

• Camera inspect, size and locate the storm sewer main and branch lines.

• Inspect main and branch lines for debris present and any abnormalities.

• Hydro Jett main and branch lines to remove any debris.

• Dye test downspouts as needed.

B. All work will be performed under a single contract.

C. Period of performance: Work shall be completed 45 calendar days after contract award effective date.

This is inclusive of potential weather days and lead times. The time stated for completion shall include all tasks outlined in this Statement of Work.

Page | 4

ITEM 2 - EXISTING UTILITIES

2.1 Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative (COR) and utility companies to coordinate proposed locations, times for excavation and request location services prior to any digging operation.

2.2 Contractor shall be responsible for locating and preventing damage to known utilities. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government.

If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.

2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:

2.3.1 Notify CO and COR not less than two business days in advance of proposed utility interruptions.

2.3.2 Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the site or within the park unless approved by the Contracting Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Public Use of Site: Contractor shall always conduct operations to ensure the least inconvenience to the public.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of 7 a.m. to

4:30 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day Martin Luther King, Jr’s Birthday Washington’s Birthday

Page | 5

Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site. Limit use of premises to area of service provided as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Limits: N/A

C. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

D. Limit site disturbance, including earthwork and clearing of vegetation, to:

a. 40 feet beyond building perimeter

b. 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter

c. 15 feet beyond primary roadway curbs and main utility branch trenches

d. 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.

E. Utilities

a. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.

b. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for operations without any additional permit costs. Use resources wisely and minimize waste of water.

c. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for operations without any additional permit costs. Power may or may not meet your power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

d. Toilets: Available https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022

Page | 6

F. Security and Protection facilities: Some of this may be relevant and some may not.

1 Environmental Protection: Provide protection, operate temporary facilities, and conduct work in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

2 Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all service equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Disassembly of equipment components or specialized inspection tools are not required.

3.4 Storage - Staging Areas:

A. N/A

3.5 Preservation of Natural Features: N/A

3.6 Hauling Restrictions: Contractor to verify path to site and meet state and county road requirements and height restrictions for all park work/access.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

a. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters

b. Address Recycling: Government goal is to salvage and recycle as much nonhazardous waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

3.8 Photo Documentation:

N/A

3.9 Fire and Life Safety:

3 Comply with the requirements of NFPA.

4 Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

i. Immediately report all spills of hazardous materials to the CO, COR, and park.

ii. Maintain a spill emergency response kit.

iii. Train employees how to respond to a spill and use an emergency response kit.

3.10 Noise and Acoustics Management

A. Noise Control: N/A

B. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.

https://www.osha.gov/laws-regs/regulations/standardnumber/1926

Page | 7

1. Do not exceed the following dB(A) limitations at 50 feet:

Sound Level in dB(A) Time Duration of Impact Noise 70 More than 12 minutes in any hour 80 More than 3 minutes in any hour

2. Maximum permissible equipment noise levels at 50 feet:

EARTHMOVING dB(A) MATERIALS HANDLING dB(A) Compressors 75 Pneumatic Tools 80 Pumps 75 Saws 75 Generators 75 Vibrators 75

C. Ambient Noise:

1. Maximum noise levels (dB) for receiving noise area at property line shall be as follows:

a. Residential receiving area :

Daytime: 65 dB Nighttime: 45 dB

b. Commercial/Industrial receiving area:

Daytime: 67 dB Nighttime: 65 dB

ITEM 4 - EXAMINATION OF THE SITE

4.1 All interested contractors are urged to visit the job site and examine existing conditions before submitting quotes. Contractors will be expected to complete the work outlined in this Statement or Work.

ITEM 5 – SUBMITTALS

5.1 General Submittal Procedures:

A. General: Prepare and submit submittals for approved equipment as specified

1. All submittals shall be transmitted via electronic email to COR.

5.2 Shop Drawings, Product Data, and Samples:

A. Product Data: Provide component and specification data sheets, anchorage requirements and any other product specific data.

1. Product/material specifications are required to be submitted with Contractor’s quote by the close date set forth for this request for quote (RFQ) – please see below product/material specifications.

B. For submittals specified above, forward submittals to Contracting Officer Representative at least 5 days before need for approval (depends on length of project).

Page | 8

C. After approving submittals, Contracting Officer Representative will return one copy to the Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

5.3 Approved Equals: If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification.

A. For each item proposed as an “approved equal,” submit supporting data, including:

1. Drawings and samples as appropriate.

2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.

3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendor.

5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.

B. A request for approval constitutes a representation that Contractor:

1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

2. Will provide the same warranties for the proposed item as for the item specified.

3. Has determined that the proposed item is compatible with interfacing items.

4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

C. Approved Equals will be evaluated and approved/disapproved during the submittal process.

ITEM 6 – TEMPORARY SERVICES

6.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.

Page | 9

ITEM 7 - PROJECT CLOSEOUT

7.1 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for intended use.

7.2 Completion: When project is complete, contractor shall request in writing or verbally onsite a final inspection.

Upon receipt of this request, the Contracting Officer Representative will proceed with inspection within 5 days of receipt of request or will advise the contractor of items that prevent the project from being designated as complete.

1) Areas rejected by the Contracting Officer Representative shall be made good at the expense of the contractor.

2) If following final inspection, the work is determined to be not complete; the Contracting Officer Representative will notify contractor in writing. The Contracting Officer Representative will prepare a list of deficiencies to be corrected. The Contractor shall complete the work described on the list of deficiencies within 10 calendar days. After completing work, the contractor shall request a new final inspection.

3) After all deficiencies have been corrected, project work will be fully accepted.

7.3 Warranty Requirements:

A. A one-year warranty is required on all contractor and sub-contractor labor and workmanship. When applicable, this one-year warranty for labor and workmanship does not include the individual manufacturer’s parts or product implied warranties. The contractor will also support manufacturer warrantied items and repair work during this period.

B. Manufacturer’s product warranty will apply to all other parts, fixtures, and products as applicable.

Provide all manufacturer’s product warranty information of products installed. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

Information shall include operation and maintenance manuals for each warranted product.

C. All material will be applied/installed in accordance with manufacturer’s instructions.

END OF SECTION

Page | 10

ADDITIONAL INFORMATION

Other Applicable Standards: Contractor must be a certified installer and possess all applicable certifications to perform the work outlined in this SOW. All pertinent services shall comply with the policies and standards of the governing bodies and applicable regulations which include but are not limited to:

a. State and local codes [latest editions]

b. Uniform Building Code [ICBO, latest edition]

c. Occupational Safety and Health Act [OSHA, latest edition]

d. Manufacturers Specifications and recommendations.

PICTURES/DRAWINGS

Page | 11

Page | 12

STATEMENT OF WORK:
E. Utilities
F. Security and Protection facilities: Some of this may be relevant and some may not.
1 Environmental Protection: Provide protection, operate temporary facilities, and conduct work in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or p...
2 Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all service equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Disassembly of equipment componen...
3 Comply with the requirements of NFPA.
4 Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for...
i. Immediately report all spills of hazardous materials to the CO, COR, and park.
ii. Maintain a spill emergency response kit.
iii. Train employees how to respond to a spill and use an emergency response kit.
A. Noise Control: N/A
B. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
1. Do not exceed the following dB(A) limitations at 50 feet:
2. Maximum permissible equipment noise levels at 50 feet:
C. Ambient Noise:
1. Maximum noise levels (dB) for receiving noise area at property line shall be as follows:
a. Residential receiving area : Daytime: 65 dB Nighttime: 45 dB
b. Commercial/Industrial receiving area: Daytime: 67 dB Nighttime: 65 dB