SOW STA Venice Replace Exterior Lighting.pdf
PDF 3 MB Posted
- Attached to
- Replacement of Exterior Lighting
- Solicitation number
- 70Z02926QNEWO008
About this file
This document is a Specifications file for exterior lighting renovation at U.S. Coast Guard Station Venice, Louisiana. The project involves removal of existing exterior lighting and installation of new LED marine-grade light fixtures at three locations: the ANT Building (11 fixtures), Boat House (10 fixtures), and three light poles (6 fixtures total). The contractor must provide all labor, materials, and equipment necessary to complete the work, including running new marine-grade conduit and wiring from an electrical box on the pier to Boat House lighting, replacing broken conduit and faulty wiring, installing new breakers and photocells as needed, and ensuring all fixtures are approved by the Contracting Officer's Representative (COR) before installation. All light fixtures must be industrial-quality, rated for harsh weather and wind-driven rain, and provide adequate lighting for their respective areas. Required delivery is 60 days after contract award.
The contractor must notify Coast Guard one week prior to work commencement and coordinate all activities with COR MK1 Ricky Gonzales (Ricky.j.gonzales@uscg.mil, 504-915-6986). Work must be scheduled to minimize interference with normal facility operations (8:00 AM to 4:00 PM, Monday through Friday, excluding federal holidays). The contractor is responsible for protecting all materials and equipment, repairing any damaged utilities at no additional cost to the government, maintaining a clean work site with daily cleanups, and complying with OSHA safety standards and Coast Guard regulations. Additional requirements include providing identification for all personnel, verifying utility locations before commencing work, submitting a consolidated list of contracted personnel with government-issued identification numbers, and taking precautions against damage during gale-force winds or natural disasters. The contractor must also obtain COR approval for all materials prior to execution and participate in a pre-conference meeting prior to work commencement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
STATION VENICE, LA
SPECIFICATIONS
FOR
Exterior Lighting (ANT Building, Boat House, Light Poles)
General: United States Coast Guard Station Venice is accepting proposals for qualified individuals or firms to complete removal of current exterior lighting around ANT Building, Boat House, and light poles and the instillation of new LED marine grade light fixtures. There is a total of 27 light fixtures. There will be 10 LED light fixtures installed on the Boat house. These light fixtures will need new wiring ran from the electrical box on pier to each light through industry standard marine grade conduit. The ANT Building will have 11 total light fixtures.
Electrical wiring already exists at each location of light fixture. Lastly, there will be 06 LED light fixtures mounted to 03 existing light poles located on base. Contractor shall replace any broken conduit and replace any faulty wiring for light pole lighting. Contractor shall replace or install any breakers or photocells needed within the exterior lighting systems for the ANT Building, Boat House, and Light poles. All light fixtures need to be approved by the COR and shall be industrial quality, rated for harsh weather, wind driven rain, and provide adequate lighting for the area it is located. Prior to submitting a quote, it is mandatory to examine the scope of work, and it is highly recommended to visit the facility to take field measurements, evaluations, etc., and become familiar with existing conditions under which the work will be performed. After the award of contract, a pre-conference will be held prior to starting the work at Coast Guard Station Venice.
Location:
United States Coast Guard Station Venice.
436 Coast Guard Rd. Venice, LA 70091
I. Continuity of Facilities Operation: Schedule work to minimize interference with the facility’s normal operations. Normal operating hours are from 8:00am to 4:00pm Monday thru Friday except federal holidays. Any work during other hours unless otherwise instructed or permitted shall be scheduled and approved with the Contracting Officers Representative.
II. Notification of Start and Completion of Work: The Contractor shall notify Coast Guard one week prior to start of work.
III. Coast Guard Contracting Officers Representative: The Contractor shall contact the COR to coordinate all construction efforts onboard Coast Guard Facilities.
MK1 Ricky Gonzales Ricky.j.gonzales@uscg.mil 504-915-6986
IV: Recycling and Disposal of Refuse: All disposals shall be done in accordance with federal, state, and local laws and regulations. All bulk waste, to include old drywall, deteriorated frame wood, screws, etc shall be disposed of in contractor provided dumpsters.
V: Safety: During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction. The contractor shall have a written safety plan as required in FAR 5.236-13. The plan shall unequivocally assign responsibility and authority for safety to the superintendent by name. Immediate notification to the Contracting Officer’s Representative of lost time due to accidents is required. Provide two copies of workman’s compensation accident reports by noon of the day following the accident. The Coast Guard reserves the right to bar any workers or supervisors from the premises should they be documented as violating set safety standards and regulations.
VI. Inspection: The Contracting Officer’s Representative has the right to reject defective workmanship or materials or work not performed as per the project specifications. Only the Contracting Officer or his/her representative may accept work performed by the contractor.
VII. Operations and Storage: The contractor is to take whatever steps necessary to ensure that their materials are protected. The Coast Guard has no responsibility for receipt, storage, or protection of contractor’s materials. All equipment, materials and supplies shall be addressed to the contractor. The Coast Guard or its members will not accept shipments. The contractor is responsible for the protection of existing structures, utilities, work and vegetation that may be in and around the work sites. Any damage shall be repaired at the contractor’s expense.
VIII. Contractor Identification: The contractor and subcontractor personnel shall, at all times, wear company identification.
IX. Existing Utilities: The Contractor shall field verify all utility locations before commencing work. This shall include, but not be limited to, the use of visual, sonic, electronic or magnetic detection devices. Contractor shall be responsible for repairing any utilities damaged during demolition or work throughout the project at no additional cost to the Government.
X: Regulations while onboard Coast Guard Station Venice:
1. Daily colors and the raising/lowering of the American flag will take place every morning at 0800 and every evening at sunset. All personnel on Base will face the main flagpole & maintain silence and all vehicles & equipment will halt during these brief events.
2. The work site shall be maintained in a clean condition at all times. This includes daily clean-ups of the work and storage areas. The site shall be well lit and well barricaded/cordoned off as appropriate.
3. Absolutely no firearms or weapons of any kind are allowed onboard Station Venice.
4. Only American citizens and permanent resident aliens are allowed onboard Station
Venice Facilities. Absolutely no foreign nationals are permitted on the premises.
5. Notice shall be given to the Coast Guard’s representative 1 week in advance of any planned power, water, and sewage or lighting outages.
6. The contractor shall provide a consolidated list of all contracted personnel including their driver’s license numbers (or other valid gov’t issued ID number) who will be working on Facilities either the day of or prior to the notice to proceed date.
7. Should warnings of gale force or stronger winds, or other inbound natural disasters be issued, the contractor shall take every practicable precaution to minimize the danger to persons, to the work, and the adjacent property. These precautions shall include closing all openings, removing all loose materials, tools and equipment from exposed locations, and removing or securing scaffolding, securing field trailers, and other appropriate equipment and other temporary work.
8. No personnel other than the contracting officer has the authority to alter the terms of any contract or to issue any change orders.
9. All contractor vehicles, equipment and gear onboard Coast Guard properties are subject to search at all times. Additionally at all times due to security and operational needs, the contractors are subject to orders to evacuate the property at any time.
10. Due to the nature of operations & support functions ongoing on-board Station Venice, all efforts within reason to minimize the size and footprint of the contractor’s lay down area shall be taken. The boat ramp, government vehicles, and small boats shall not be obstructed or blocked.
VIII: SCOPE OF WORK: All materials are subject to COR approval prior to execution. The contractor shall discuss plans to complete the exterior lighting project with COR to create a schedule of areas to be worked on to minimize disruption of operations. The contractor shall provide all labor, materials, and equipment necessary to complete the following unless noted below:
A. Base Bid
1. Contractor shall remove existing exterior lighting on the ANT Building, Boat House, and from 03 light poles on base.
2. Contractor shall remove any broken conduit or faulty wiring from Boat House and the 03 light poles.
3. Contractor shall install new breakers and photocell in electrical panel on pier and run new proper size wiring and conduit to Boat House lighting.
4. Contractor shall replace any broken conduit or faulty wiring, replace photocell, and replace existing breaker in electrical panel under main building for the 03 light poles.
5. Contractor shall install ANT Building lighting fixtures in location of existing lighting and replace any photocells located within the system.
6. Required delivery 60 days after award.
7. Contractors shall protect all equipment and merchandise in work locations.
8. All work must be approved by the Contracting Officer’s Representative.
Reference Pictures: Some but not all spaces to be completed
ANT Building
Boat House
Light Poles
File details come from the government source that posted it. Updated .