SOW-Solar Panel removal and reinstall McNAir 69.pdf
PDF 189 KB Posted
- Attached to
- Solar Panel removal and reinstall McNAir 69
- Solicitation number
- W9124J-26-C-SOLR
About this file
This is a Scope of Work for the removal and reinstallation of a solar photovoltaic (PV) system at Building 69, Fort McNair, Washington, D.C. The existing PV system has a capacity of 147.7 kWdc / 133.2 kWac and consists of 422 solar modules, 4 inverters, associated DC wiring, and racking distributed across four separate roof locations. The contractor must remove all components to facilitate roof replacement (anticipated to take approximately nine months), store them safely on-site, and then reinstall and recommission the system once roofing work is complete. Removal and reinstallation will be phased over multiple crane operations, with panels electrically disconnected and palletized at predetermined staging locations approved by a Structural Engineer. The total contract performance period may not exceed 18 calendar months. Regular working hours are 0700-1530, Monday through Friday, excluding federal holidays and base closures.
The contractor must provide comprehensive site management including a site-specific safety document, fall protection, roof protection, crane setup with outriggers based on an approved lift plan, interior equipment protection, and daily site cleanup. All work submittal items (Project Schedule, Project Superintendent, Traffic and Safety Plan, and Equipment/Material Laydown Plan) must be approved by the Contracting Officer's Representative (COR) with no less than 14 calendar days review time before installation begins. The contractor is responsible for obtaining a Structural Engineer's signed letter documenting roof point load limitations, all necessary permits, Material Safety Data Sheets for hazardous materials, and proper disposal of debris in accordance with EPA, OSHA, and U.S. Army Corps of Engineers (EM-385-1-1) standards. Additional requirements include mandatory pre-contract initiation meeting with the Contracting Officer, E-Verify screening for all personnel, security clearances and access control passes through the Joint Base Myer-Henderson Hall Visitor Control Center, iWATCH briefing completion within 30 days, and a 365-day workmanship warranty. The contractor must coordinate with the Directorate of Emergency Services for street closures (96 hours minimum notice) and hot work permits from the JBM-HH Fire Department.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W9124J26CSOLR Sources Sought Notice Solar Panel Removal Reinstallation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Solar Panel Removal Bldg. 69 McNair
1. Background
The roof of Building 69 at Fort McNair is at the end of its service life and requires full replacement. The roof consists of multiple levels and currently supports a distributed solar photovoltaic (PV) system. The PV system serving Building 69 has a total capacity of 147.7 kWdc / 133.2 kWac and consists of 422 modules and 4 inverters located in the Electrical Room, along with associated DC wiring and racking.
The solar arrays are situated in four separate locations on the roof, all tied into the same system. To facilitate the roofing replacement, the solar panels and all associated components (including racking and DC wiring, as required) will be removed and reinstalled in coordination with the roofing phasing. The roofing replacement is anticipated to take approximately nine months to complete.
Due to the distributed layout of the arrays, panel removal will be phased over multiple crane days. Prior to each crane operation, the panels will be electrically disconnected, removed from their racking, and palletized in predetermined staging locations on the roof, as identified and approved by the Structural Engineer.
A similar phased process will be used for reinstallation. The crane will place palletized modules in predetermined locations on the roof, after which the pallets will be broken down and the modules, racking, and wiring reinstalled and reconnected in accordance with design documents and applicable codes. Upon completion of the reinstallation, the solar PV system will be tested, inspected, and recommissioned.
The Contractor is responsible for all means, methods, supervision, and coordination to produce a quality-finished project. The Contractor must provide all equipment, material, and labor necessary to complete scope of work, described herein:
Removal:
a. Provide a site-specific safety document to detail safety personnel, project specific safety protocols, safety ratings, roles and responsibilities, training certifications of on-site personnel, site work plan layout, safety manual, hazard analysis, and Contractor obligations.
b. Obtain the services of a Structural Engineer to provide a signed/sealed letter or report to document the point load limitations of the roof.
c. Install protection around interior equipment that remains including transformer, inverters, and panels boxes.
d. Install fall protection as required on roof perimeter per approved safety plan.
e. Install roof protection as required.
f. Set up cranes with outriggers based on crane lift plan for bldg. 69.
g. Remove existing solar panels and store on palettes on completed portions of the roof.
h. Remove and store existing rail system and hardware to allow for roof replacement.
i. Remove all pallets and store via the selected storage means (onsite TBD).
j. Remove all fall protection when the solar panel removal project is completed.
Reinstall:
a. Perform existing condition survey of the roof to document any pre-existing deficiencies.
b. Install fall protection as required on roof perimeter as per approved safety plan.
c. Install roof protection as required.
d. Setup crane in loading dock area with outriggers on 5th Ave.
e. Crane all pallets to the roof.
f. Reassemble rail system after the roof repairs are completed.
g. Reinstallation to include new DC wiring and connections.
h. Reinstall solar panels.
i. Remove protection for interior equipment.
j. Commission reinstalled Solar Rooftop Array.
k. Remove all roof protection and fall protection upon completion of the reinstallation project.
1. Project Submittals:
1.1. The Contractor shall certify that submittals meet the requirements of the plans, specifications, and the above SOW. The Contractor shall allow for no less than 14 calendar days for submittal review by the government. THE CONTRACTOR SHALL NOT BE PERMITTED TO INSTALL ANY AND ALL
ITEMS LISTED BELOW WITHOUT AN APROVED SUBMITTAL MATCHING WHAT IS TO BE
INSTALLED IN ALL RESPECTS. Submittal Logs shall be provided. Shop drawings, product data, and samples shall be submitted for all equipment and materials related to the following list (written submittals shall be sent in hard-copy form as well as electronically in Adobe Acrobat readable format to the COR):
1.1.1. Project Schedule.
1.1.2. Project Superintendent.
1.1.3. Traffic and safety Plan.
1.1.4. Equipment and Material laydown plan
2. General Conditions:
2.1. All work to shall be completed at Building 69 Fort McNair, DC.
2.2. Contractor is responsible for all means, methods, supervision, and coordination to produce a quality, finished product. The Contractor must provide all equipment, material, and labor necessary to complete the scope of work, described herein.
2.3. Contractor's Agent/Representative is required to be on-site at any time work is being executed in conjunction with the project and is responsible for and must be able to report on the location and number of employees working on the installation when requested.
2.4. Any discrepancy or inconsistency between the scope of work and actual job conditions found during the project, shall be reported immediately to the KO & COR, followed by a written record within 36 hours. Written notification from the Contractor/Designer of Record shall include the discovery, direction, circumstances, options, recommendations with alternatives showing costs, for review and acceptance to accomplish a completed project. Contractor is responsible for providing any Request for Information (RFI) in written form to the KO and COR to clarify any and all portions of the work that may be in question.
2.5. Any unforeseen site conditions shall be brought to the immediate attention of the KO & COR for direction on how to proceed. Written notification from the Contractor and/or Designer of Record shall occur within 36 hours of discovery, and shall include the discovery, circumstances, options, recommendations and/or alternatives for review and acceptance to accomplish a completed project. NO additional work will be permitted without first being recommended for approval by the COR and authorized by the KO.
2.6. Contractor shall be paid through Wide Area Workflow (WAWF; for more information see https://wawf.eb.mil/ ) unless otherwise indicated by the Director of Contracting. The Contractor shall submit a completed Application and Certification for Payment for this project to the COR for review and acceptance prior to entering an Invoice into the WAWF system (in addition to any notification provided through the WAWF system). Failure to ensure that the COR is notified by email and that a return receipt acknowledges its receipt, may be grounds for forfeiture of any late fees the Contractor may otherwise be owed.
2.7. Contractor agrees to workmanship warranty for a period of 365 calendar days (or twelve (12) months whichever is longer) from the date of acceptance by the COR. Warranty shall be furnished in writing prior to the Contractor’s final invoice under this Contract.
2.8. Materials. All materials required for the entire project shall meet industry standards, shall be new, free from all defects, of the best grade and quality, and entirely satisfactory for the purpose intended and shall be furnished in sufficient quantities to prevent delay.
https://wawf.eb.mil/
2.9. Total Contract Performance Period. No more than 18 calendar months.
2.10. Regular Working Hours. The government’s regular (normal) working hours are from 0700 to
1530, Mondays through Fridays, except (a) federal holidays (b) Base closure, and (c) other days specifically designated by the Contracting Officer. Federal holidays are listed below:
Date Holiday
January 02 New Year’s Day
January 16 Birthday of Martin Luther King, Jr.
February 20 Washington’s Birthday
May 29 Memorial Day
June 19 Juneteenth National Independence Day
July 04 Independence Day
September 04 Labor Day
October 09 Columbus Day
November 10 Veterans Day
November 23 Thanksgiving Day
December 25 Christmas Day
2.11. The Contractor is to provide a schedule for all work activities to the COR for acceptance prior to the initiation of any and all work and/or mobilization on the project site. This schedule is to account for all activities involved in the work, any and all administrative requirements required to execute the work described herein, and any and all supply, coordination, or subcontract efforts that may be required to execute the work. This schedule shall be provided in written hard copy format and electronically in Adobe Acrobat readable format.
2.12. If required, road closures and/or traffic disruptions shall be coordinated with the COR and
Directorate of Emergency Services (DES) with a minimum 96 Hours (4 Days) in advance and all safety measures shall be followed.
2.13. The Contractor is advised this installation is the premier installation for the United States
Military. As such, there are times of heightened security measures (as result of threats, visiting dignitaries, and other reasons); the Contractor may not have access to the installation or portions thereof.
Many of these events can and will be coordinated with the Contractor prior to the event by the COR;
however, this may or may not be the case. If it is determined that the Contractor cannot work, the government shall furnish a time extension on a day for day basis for such interruptions as approved and agreed upon by the KO, however, the Contractor will not be entitled to any additional compensation for such delays.
2.14. The Contractor must be aware that Fort McNair of Joint Base Myer – Henderson Hall (JBM-
HH) is a controlled access installation, and as a result requires photographic identification and the potential of vehicle inspection to gain entrance onto the installation. Detention, delay, and or other challenges presented to the Contractor because of this fact are the sole responsibility of the Contractor.
2.15. The Contractor shall ensure that all Contractor and Sub-Contractors’ employees who require physical access to JBM-HH and Fort McNair are provide all information required for a check of records through databases including, but not limited to, the National Crime Information Center (NCIC) Interstate Identification Index (III) and the Terrorist Screening Database. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at the installation change, the Government may require changes in Contractor security matters or processes.
2.15.1. All Contractor and associated Sub-Contractor employees who require physical access to
JBM-HH and Fort McNair for contract performance shall present an Acceptable Identity Source Document, as identified in Section 2 of Attachment 4 of DoD Directive-Type Memorandum 09-012, “Interim Policy Guidance for DoD Physical Access Control” (available at http://www.dtic.mil/whs/directives/corres/pdf ), filename “DTM-09-012.pdf” to access the installation.
2.15.2. All Contractor and Sub-Contractor personnel required to have access to the Base must complete “Request for a Joint Base Myer-Henderson Hall Installation Access Control Pass” (See: DES Form 190-16a 16 May 2018 Appendix).
2.15.3. The Contractor shall maintain awareness of all Prime and Sub-Contractor employees who are vetted and approved for access onto the Base. Contractor shall notify the KO and COR in writing within 48 hours of any Contractor or Sub-Contractor employees who resigns, is terminated, or for any other reason and no longer authorized to access JBM-HH and Fort McNair for the purpose of performance of this contract. For contracts with a performance period longer than three months, the Contractor shall reconcile his roster of approved personnel with the JBM-HH, Fort McNair Visitor Control Center (VCC) to ensure that both the Contractor and COR maintain accurate awareness of the Contractor and Sub-Contractor employees who are authorized to access the installation.
2.15.4. All Contractor and all associated Sub-Contractors employees requiring physical access to
JBM-HH and Fort McNair for contract performance shall be pre-screened by the Contractor using the E-verify Program at http://www.dhs.gov/E-Verify website to meet the established employment eligibility requirements and shall provide only eligible employees for contract performance while on the installation.
2.15.5. All Contractor and Sub-Contractor employees shall attend a briefing on the local iWATCH program provided by the JBM-HH ATO or Security Office. This locally developed briefing will be used to inform employees of the types of suspicious behavior to report to the COR or the JBM-HH Police Department. This briefing shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees' commencing performance with the results reported to the COR no later than 30 days after contract award and new employees' commencing performance.
http://www.dtic.mil/whs/directives/corres/pdf
2.15.6. The Contractor shall ensure that all Contractor and Sub-Contractors employee Common Access Cards (CACs), badges, passes or other access credentials which were issued under this contract are surrendered to the COR upon completion of the contract. CACs, badges, passes and other access credentials are DoD property and failure to surrender them are punishable under 18 USC § 701.
2.16. The Contractor shall execute such work over whatever hours are required, inclusive of normal, weekend, overtime, alternate work time, as required to complete the work at no additional cost to the government within the prescribed period of performance.
2.17. The Contractor shall comply with local noise ordinances.
2.18. Contractor shall have access to the site through the 2nd Street Gate, Washington D.C.
2.19. Quality Control (QC) in accordance with the Contractor Quality Control Procedures and Plan.
The Contractor shall furnish a copy of their QC Plan to the government prior to the start of work for review and acceptance. The Contractor shall appoint a quality control person. The project superintendent and quality control person cannot be the same individual. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The government will periodically evaluate the Contractor’s performance and compliance with this SOW. Any and all discrepancies and/or non-compliance discovered regarding work executed for this SOW will require the Contractor to reperform the task at no additional cost to the Government.
2.20. Safety in accordance with the Contractor’s Safety Program. Prior to the beginning of any work, the Contractor shall submit their safety plan and site specific safety plan in accordance with EM 385-1-1, to the KO, COR and JBM-HH Safety Office for review and acceptance. The Contractor shall be responsible for safety of employees, Sub-Contractor employees (who must follow the Prime's Mishap Prevention Plan), Government employees and visitors within the work site premises during all operations, including the Contractor providing and supervising the appropriate use of all personal protective equipment.
2.21. Any incident involving injury to Contractor’s employees or property damage shall immediately be reported to the DPW COR, JBM-HH Safety Office, and/or Directorate of Emergency Services (DES) and/or 911.
2.22. Safety Requirements and Reports. During the performance of work under this contract, the
Contractor shall strictly adhere to Environmental Protection Agency Regulations (EPA), Federal Occupational Safety and Health Regulations (OSHA), U.S. Army Corps of Engineers Safety and Health Handbook (EM-385-1-1), as well as all applicable state and local requirements.
2.23. Fire Protection. The Contractor shall handle and store all combustible supplies, materials, waste, and trash in a manner that prevents fire hazards to persons, facilities, and materials. Contractor must coordinate with the COR and DES to receive hot work permits from the JBM-HH Fire Department;
Contact James Dansereau at 703-696-3483 for the permits.
2.24. Environmental Protection:
2.24.1. The Contractor shall comply with all applicable federal, state, and local laws, and with the regulations and standards. All environmental protection matters shall be coordinated with the KO and COR. Inspection of any of the facilities operated by the Contractor are accomplished by DPW Environmental Division and/or Safety personnel, or authorized officials on a no-notice basis at any time.
2.24.2. In the event a regulatory agency assesses a monetary fine against the Government for violations caused by Contractor negligence, error or omission, the Contractor shall reimburse the Government the amount of that fine and other costs. The Contractor shall also clean up any oil spills that result from the Contractor’s operations. The Contractor shall comply with the instructions from the JBM- HH Safety Office with respect to avoidance of conditions which create a nuisance, or which may be hazardous to the health of military of civilian personnel.
2.24.3. The Contractor shall provide a list of all Hazardous Materials used on the Post under this
Project and provide an MSDS for each material listed.
2.25. All demolished material shall be accounted for by the Contractor and reported to the COR.
2.26. Before completion of work each day, the Contractor shall secure all supplies, materials and equipment. The Contractor shall daily remove all scrap, debris, etc. and dispose off-post, unless otherwise directed elsewhere in this SOW and leave the job site in a clean, orderly and safe manner for each calendar day.
2.27. Disposal:
2.27.1. Debris, rubbish, hazardous waste and unusable material resulting from the work under this contract shall be daily disposed of by the Contractor legally and in compliance with all regulations as may pertain at the Contractor’s expense off of Government property. Work areas shall be kept clean and always provide clear access to and through the site.
2.27.2. All recyclable materials: aluminum and metal cans, glass bottles and jars, plastic bottles, newspapers, cardboard, high grade paper, mixed paper, scrap metal, scrap lumber, pavement debris, and vegetation wastes shall be segregated, removed from the Post, and disposed of in accordance with Department of Defense recycling and solid waste management regulations.
2.27.3. Hazardous waste must be disposed of in accordance with the Resource Conservation and
Recovery Act.
2.28. Permits: The Contractor shall, without additional expense to the Government, obtain all appointments, licenses, and permits required for the performance of the work. The Contractor shall comply with all applicable federal and District laws. Evidence of such permits and licenses shall be provided to the KO and COR before work commences.
2.29. Notwithstanding any other provisions of this scope of work, the Contractor shall comply with applicable rules, laws, regulations, and policies, in effect at Joint Base Myer – Henderson Hall (JBM- HH), and all US laws.
2.30. Contractor shall ensure they comply with any and all additional provisions as applicable to the Contractors working at JBM-HH. The Contractor is to be fully aware and have full knowledge of all policies, procedures and requirements to work on this installation, and is to seek clarification on any specific provision that they are unclear about from the COR.
2.31. Unless otherwise indicated, the Government is represented by the Project Manager (PM)
/COR.
2.32. Work shall be completed in one phase per area of work.
2.33. Contractor shall have access to all work areas at one time.
2.34. Contractor shall not be allowed to use Government restroom facilities in the Government buildings where work is to take place. The Contractor shall be allowed to locate Port-O-Johns near the work site and shall coordinated suitable location with the COR.
2.35. Government will provide and/or coordinate a location convenient to the work for a temporary site storage container with the Contractor, if deemed necessary.
2.36. Contractor shall provide protection to all areas adjoining or within the area of the work that are not to be affected or damaged.
2.37. The Contractor is fully and totally responsible for the condition of the work and the work site until the work is formally accepted by the government.
2.38. If the work requires any shutdown or disruption of any utility/service outside of the immediate area of the work/the area under the Contractor’s control, the Contractor shall coordinate and provide a minimum 14 days notice with the COR and KO, prior to making any such disruption and follow any and all procedures provided by the DPW for such disruptions. To the extent possible, the Contractor must note on his schedule planned shutdowns or disruptions that will be required as a part of the work (inclusive of timeframe and any logical connections t other tasks of the work).
2.39. Contractor shall provide Movement of Traffic (MOT) and applicable Traffic control measures as required for review and approval, prior to mobilization to the site. Coordination of these measures shall be with the COR and Fort Myer Directorate of Emergency Services (DES), Traffic Division.
2.40. The Contractor shall coordinate any oversized deliveries with the COR and DES in order to allow access to the installation through the proper gate.
2.41. The Contractor is to be present for and participate fully in a pre-contract initiation meeting held by the KO prior to any work beginning or ordering of any materials, unless otherwise directed by the KO. The information discussed and clarifications made in this meeting will be made biding on the contract as indicated by the KO.
3. Reference
DES Form 190-16a May 2018, Addendum Contractor Schedule
The proposed Contractor project schedule is tentatively as follows:
Project Schedule Duration:
Mobilization & Establish Site Safety Plan - +/- 3 Weeks
Removal of Existing System - +/- 5-7 Days
Reinstall of Existing System - +/- 12-15 days
Commissioning - +/- 2 days
Addendum - Notes
Proposal is based on their being (3) parking spaces available for vehicles and a lull.
a. Removal will be performed by a crane that will be situated as specified in the Bldg. 69 Crane Lift Plan with outriggers.
b. Will require a street closure for the duration of the crane lift. This work is assumed to occur during regular working hours.
c. Onsite storage will require 10-12 parking spaces and will be enclosed with a fence that will be kept locked.
d. All work including deliveries to occur during normal working hours which is assumed to be 6am to 3pm Monday through Friday
e. Existing racking and ballasting systems will be reinstalled. It is assumed that existing hardware on Solar Panels can be disassembled and reassembled without any modifications or replacement.
f. Protection of the interior equipment is included and is based on plywood and foamboard being installed to cover up equipment. Removal and storage of interior equipment is excluded.
g. Commissioning by our own workforce at the completion of the reinstall is included.
Commissioning support for a 3rd party commissioning agent is excluded.
End of Scope of Work