Scope of Work Summary: Sliding Glass Door Replacement

This is a Scope of Work document issued by the Department of Homeland Security United States Coast Guard, Base Cleveland Housing Division, for sliding glass door replacement at five residential properties in Sturgeon Bay, Wisconsin. The primary contact is DC2 Tebo, Tristan, reachable at (206)-836-5708 or Tristan.T.Tebo@uscg.mil. The contractor must remove existing sliding glass doors and associated hardware, inspect door frames for damage (rot, insect infestation, warping), report significant findings to the Point of Contact (POC), and perform minor frame repairs as needed. Installation of new energy-efficient, double-paned sliding glass doors must include all necessary hardware, tracks, weather stripping, and trim/molding to match existing aesthetics. All materials must be contractor-supplied, meet or exceed local building codes and USCG standards, and require POC approval for quality and color before use. The contractor is responsible for obtaining permits, providing appropriate insurance coverage, and submitting all required licenses and certifications with the bid.

Project execution requires a mandatory site visit prior to commencing work to assess conditions and provide accurate quotes. Work is restricted to normal business hours of 8:00 AM to 4:00 PM, Monday-Friday, excluding Federal Holidays, with advance coordination required for any outside-hours work. Residents must be notified in advance of work activities. Upon completion, all debris and removed materials must be properly disposed of off-site at the contractor's expense, with the site cleaned to at least its original condition. The contractor bears full financial responsibility for any damages to government property and must provide warranty coverage for materials and workmanship. All work is subject to POC inspection and approval, with compliance required to Federal, State, and Local Laws, Codes, and Regulations, including EPA and OSHA requirements regarding lead paint if housing units predate 1978.

View the file

Other files

File Type Posted
Solicitation 70Z03026QCLEV0072 - SF 1442.pdf PDF
Request for Information (RFI).pdf PDF
70Z03026QCLEV0072 - RFQ for Construction.docx DOCX document
Wage Determination Sturgeon Bay.txt TXT text file
Reference Information Sheet.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Homeland Security United States Coast Guard

Base Cleveland Housing Division

Scope of Work (SOW)

For Sliding glass door Replacement

Point of Contact (POCs)

DC2 Tebo, Tristan

(206)-836-5708

Email: Tristan.T.Tebo@uscg.mil

Site Addresses

221 N 17th Drive, Sturgeon Bay WI 54235

110 N 16th Drive, Sturgeon Bay WI 54235

213 N 16th Place, Sturgeon Bay WI 54235

133 N 16th Drive, Sturgeon Bay WI 54235

353 N. 16th Place, Sturgeon Bay WI 54235

Bidders are strongly recommended to inspect the site where work is to be performed to satisfy them regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award. The contractor shall verify all dimensions and equipment data prior to ordering materials and commencement of work.

Scope of Work: Sliding Glass Door Replacement

1. The contractor is to remove the existing sliding glass doors and dispose of all materials off the

USCG property at the contractor's expense following all local and federal laws. This includes the door itself, any associated hardware (handles, locks, rollers, tracks), and any trim or molding necessary for removal.

2. The contractor will inspect the door frame for any damage (rot, insect infestation, warping) and report any significant findings to the USCG Point of Contact (POC) before proceeding with the installation. The contractor will repair or replace any minor damage to the door frame to ensure proper installation of the new door. Significant damage to framing is to be reported to the POC.

3. The contractor will install new sliding glass doors, including all necessary hardware, tracks, and weather strip. The new doors must be properly aligned and sealed to prevent air and water leaks.

Sliding glass door installation

4. Remove existing sliding glass door and all associated hardware.

5. Dispose of removed materials off-site at an approved disposal location.

6. Inspect the door frame for damage; report significant damage to POC.

7. Repair minor damage to the door frame. “If needed”

8. Install new sliding glass door, hardware, tracks, and weather strip.

9. Ensure proper alignment and sealing to prevent air and water leaks.

10. Install new trim/molding as needed to match existing aesthetics.

11. Provide and install appropriate locking mechanisms.

12. Test operation of the door for smooth and secure function.

Material/ Part Information

13. All materials will be supplied by the contractor and must meet or exceed local building codes and

USCG standards.

14. Sliding Glass Doors: The new sliding glass doors must be energy-efficient, double-paned, and meet or exceed current energy efficiency standards. The color and style of the doors should match the existing aesthetic of the housing units or as otherwise directed by the POC. Specific dimensions will be determined during the site visit.

15. Hardware: All hardware (handles, locks, rollers, tracks) must be of high quality and durable, suitable for exterior use.

16. Sealant/Weather Stripping: High-quality sealant and weather stripping must be used to ensure a tight seal and prevent air and water leaks.

17. Fasteners: Use appropriate corrosion-resistant fasteners for all installations.

18. Trim/Molding: Matching trim/molding to be used as needed for a finished look.

19. All materials planned for use will have to be approved by the POC listed for quality and color.

References

20. All work completed shall comply with Federal, State, and Local Laws, Codes, and Regulations, including those related to window and door installation, safety, and energy efficiency.

Liabilities

21. The contractor will be financially responsible for all damages incurred while working on Government property. This includes damage to the housing unit, landscaping, or any other property.

Coordination

22. All communications will go through the POC listed. No work can be modified or changed without their permission.

23. A site visit is required to provide valuable insight into homes. Allowing the assessment of needs and condition of each unit to ensure quality and precise work. To schedule a site visit prior to commencing work and to accurately quote work needed, please contact the POC listed.

24. Work to be completed should have minimal impact on the unit’s operation. Residents will need to be notified in advance of any work being performed.

25. Normal work hours for the unit are 8:00 AM to 4:00 PM, Monday-Friday, excluding all Federal Holidays.

Any work outside these times needs to be worked out ahead of time.

26. All required Licenses, Certificates, Accreditation Cards, etc. will be submitted with the quote or bid. The contractor must have appropriate insurance coverage.

Project Completion

27. All work completed is up to the POC’s approval. The site is to be at a minimum as clean of the condition it was found in. All trash, debris, materials removed, etc. should be properly disposed of by the contractor.

There will be no on-site storage available for the duration of this project.

28. All work will be inspected and approved by C.G POC. The units will become occupied as specified by the

POC. The contractor will be given a reasonable window to schedule and complete each job. The Coast

Guard POC will attempt to provide sufficient notice prior to the availability timeline.

29. Period of Performance. C.G understands the weather could affect the project and will work with the contractor in scheduling if weather does become a factor.

Important Notes:

30. Safety: The contractor is responsible for maintaining a safe work environment and adhering to all safety regulations.

31. Lead Paint: The contractor must follow all EPA and OSHA regulations regarding lead paint if the housing units were built before 1978. Testing for lead paint may be required.

32. Permits: The contractor is responsible for obtaining any necessary permits for the work.

33. Warranty: The contractor must provide a warranty for the materials and workmanship.