SOW Sinkhole.docx
DOCX document 84 KB Posted
- Attached to
- Emergency Sinkhole Investigation and Repair
- Solicitation number
- 19BE2026Q0106
- Issued by
-
Department of State US Embassy Brussels
About this file
This Statement of Work (SOW) details an emergency sinkhole investigation and repair project for the U.S. Embassy in Brussels. The project requires a contractor to investigate a sinkhole on Rue Zinner within the embassy compound, utilizing diagnostic tools including ground penetrating radar to identify the source and assess street stability. Specific tasks include excavation up to five meters deep, repairing the sinkhole source, and restoring the road to its original cobblestone design, with strict safety requirements for excavation and heavy machinery work.
The project is time-sensitive, with a performance period from 12/10/2025 to 1/9/2026, and is being solicited as a firm-fixed-price purchase order. The U.S. Department of State's Embassy in Brussels will provide limited support including low-voltage electricity and water access. Contractors must be registered in the System for Award Management (SAM) and submit electronic quotations to BrusselsBids@state.gov in PDF format, with a maximum file size of 30MB. Daily site inspections will be conducted by embassy facility managers, and contractor staff will require escort and visitor badges while on-site.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
(SOW)
Sinkhole Investigation and Repair
Requesting Office Name: Megan Byrley Office/Section: Office of Facility Management Email: ByrleyM@state.gov Date of Request: 12/8/2025
1. Background On December 2, 2025 a sinkhole opened on Rue Zinner within the U.S. Embassy compound. The source of the sinkhole has not been identified, and the sinkhole has continued to grow since its discovery. With deflections in the road surface visible throughout the area, Rue Zinner has been closed to vehicle traffic.
2. Purpose / Objective The U.S. Embassy Brussels is in need of contract services to investigate the source of the sinkhole and make any necessary repairs for the street to be reopened to traffic.
3. Scope of Work The contractor must adhere to all applicable safety requirements associated with excavation, work with heavy machinery, and confined spaces. The following tasks are required:
1. Sinkhole investigation utilizing diagnostic tools above and under the surface;
2. Street stability analysis with ground penetrating radar to identify any other areas of concern;
3. Excavation of the immediate sinkhole area until solid ground and/or the sinkhole source is discovered;
4. Repair to the sinkhole source;
5. Backfilling the excavated area, compacting the substrate, and completely surface repair necessary for the road to be returned to its original cobblestone design.
The contractor shall inform the government immediately if excavation beyond five meters of depth is required due to the adjacent building foundation proximity.
4. Deliverables [if applicable or delete] A street stability analysis is required after the ground penetrating radar scan. The contractor shall provide pictures of the sinkhole source once it is located.
5. Period of Performance 12/10/2025-1/9/2026, unless circumstances require additional remediation.
6. Place of Performance [if applicable or delete] Rue Zinner, sinkhole site.
7. Government-Furnished Equipment or Property (GFE/GFP) [if applicable or delete]
· Low-voltage electricity for small hand tools and equipment
· Outdoor hose bib connection for low volume water will be provided
8. Performance Standards & Acceptance Criteria [if applicable or delete] The Senior Facility Manager and Senior Maintenance Supervisor will inspect the job site daily. All issues will be reported in writing to the contractor and U.S. Embassy Brussels is within their rights to stop work if they deem unsafe procedures are being followed.
9. Security / Access Requirements [if applicable or delete] Staff from the contractor who will be on site must be escorted by an Embassy employee. Due to the urgency of this project, only visitor badges will be issued.
10. Other Requirements [if applicable or delete] [Special conditions such as travel, safety measures, licenses, etc.]
11. Attachments Please attach any available supporting documents:
|_| Attached drawings |_| Photos |_| Manufacturer specifications |_| Other (please specify): __________
12. Known Deadlines This is a life safety issue and the contract is needed immediately to reduce the risk of loss of persons or property.