SOW Sector SF Bldg 22-27 Head Repairs.pdf
PDF 607 KB Posted
- Solicitation number
- 37270PR260016170
About this file
This is a Statement of Work (SOW) issued by the U.S. Coast Guard, Sector San Francisco, for bathroom renovations at Building 22-27 located at 1 Yerba Buena Island, San Francisco, CA 94130. The objective is to renovate, refresh, and preserve seventeen (17) individual bathrooms with varying degrees of work, ranging from minor cosmetic updates to extensive fixture and tile replacements. The Contracting Officer is CWO3 Joshua Alton, with an initial date of 12AUG26. The work schedule must be agreed upon within 15 days of award, with all work completed within 60 days from the start date.
The scope of work encompasses three primary tasks: (1) Project Management, including designation of a single point of contact and coordination with the Coast Guard Contracting Officer's Representative (COR); (2) Demolition, Prep Work, and Disposal, involving protection of adjacent areas, careful removal of existing fixtures, and responsible debris disposal; and (3) Tile and Grout Repair, Replacement, and Sealing, which includes inspection and replacement of up to 75 square feet of damaged tiles, grout raking and regrouting to minimum depths of 1/8 inch, and application of two coats of professional-grade penetrating sealer. Additional work includes removal and installation of heavy-duty tempered glass shower doors with 100% silicone sealant, replacement of toilet seats with commercial-grade slow-close options, installation of water-efficient (Water Sense certified) vanity faucets and showerheads with longer necks, removal of outdated light fixtures and installation of LED vanity lights (minimum 90+ CRI, 3000K–4000K color temperature), and drywall patching, priming with mold-inhibiting primer, and painting with two coats of premium low-VOC moisture-resistant interior paint in Semi-Gloss White, with one gallon left for future touch-ups.
Submittals required before work approval include product details with color samples for tiles within 10 business days of award and an intended project schedule within 10 business days of award, with the contractor restricted from working in more than half the building at any time to allow tenant partial access. If unexpected hazardous materials (lead, asbestos, heavy metals, or toxic chemical residue) are discovered outside documented survey areas (AESS Job No. 26-092), work must be halted immediately, the area secured, and the COR and Contracting Officer notified verbally within four hours and in writing within twenty-four hours, with work resuming only after formal testing and certification or proper abatement completion. Technical requirements include compliance with federal, state, and local codes; the U.S. Coast Guard Safety and Environmental Health Manual (COMDTINST M5100.47 series); and OSHA Regulations. All contractor personnel require background checks meeting USCG security policies (including potential NCIC checks), with personnel information submitted 14 days prior to project start. Access requests with employee names and birthdates must be submitted at least 72 hours before first site day. Personnel must present Real ID-compliant driver's licenses or federally approved identification (US Government Dependent ID, Federal PIV Card, TWIC Card, Veteran Health ID, US Passport, or Permanent Resident Card). All contractor vehicles must have valid registration and insurance, remain on marked paved roads only, and display company or subcontractor decals. Work hours are 7:00 AM to 5:00 PM, Monday through Friday, excluding Federal Holidays, unless otherwise approved in writing. The Government may furnish potable water and electrical power at no cost where available, with all electrical connections compliant with the National Electric Code and GFCI devices required. Final acceptance is granted by the USCG COR upon final inspection confirming completion of all tasks, compliance with technical and safety standards, and full site restoration, with final payment withheld until all deficient items are corrected. Primary technical point of contact is CWO Joshua Alton (503-939-3816); secondary point of contact is DCC Boe Siefke (510-437-3150).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Construction Solicitation Barracks Bathroom Renovations.pdf | ||
| Sector SF Floor Plans Bldg 22-27.pdf | ||
| BASE ACCESS FORM.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
Sector San Francisco
Statement of Work for
Bldg 22-27 Bathrooms Renovations
PSN:
Work Order:
at
1 Yerba Buena Island, Yerba Buena Island Northgate Rd
San Francisco, CA. 94130
Sector San Francisco Initial Date Contracting Officer (KO) CWO3 Joshua Alton Sector Engineer Officer
JAA
12AUG26
1.0 Introduction/Background
The objective of this project is to renovate, refresh, and preserve seventeen (17) individual bathrooms. The bathrooms require varying degrees of renovation, ranging from minor cosmetic updates and preservation to more extensive fixture and tile replacements. The overall goal is to modernize the aesthetics, improve energy and water efficiency, address localized wear and tear, and apply preventive sealant to extend the life of the floor tile.
2.0 Scope of Work
2.1 Tasks
The contractor shall:
Task 1: Project Management
Designate a single point of contract for all project communications.
Coordinate all work with USCG Contracting Officer’s Representative
(COR) or designated POC.
Task 2: Demolition, Prep Work, and Disposal
Protection of Property: Protect all adjacent floors, hallways, and furniture using drop cloths, plastic sheeting, and ram board.
Removal: Carefully remove designated existing shower doors, faucets, toilet seats, old plumbing fixtures, and damaged wall/ceiling/flooring materials as specified per bathroom tier.
Disposal: Responsibly haul away and legally dispose of all construction debris, old fixtures, and packaging. Keep the job site clean and clear of hazards daily.
Task 3: Tile and Grout Repair, Replacement, and Sealing Tile Replacement: Inspect all wall and floor tiles. Remove and replace up to 75sqft of loose, cracked, or damaged tiles. Contractor must match existing tiles in color, size, and finish as closely as possible, utilizing client-approved matching stock.
Grout Repair & Regrouting: Rake out damaged, cracked, or mold-infested grout to a minimum depth of 1/8 inch (or half the depth of the tile, whichever is greater). If this method is not needed, discuss options with CG POC prior to work. This applies to the cleaning of the showers and floor pans.
Tile and Grout Sealing (Preservation): Thoroughly deep-clean and dry all existing and new tile/grout surfaces. Apply two (2) coats of professional-grade, breathable penetrating/impregnating sealer to all tiled walls and floors to protect against water penetration, staining, and mold growth. This applies to sealing the shower walls and floor pans.
Remove existing shower doors: Installation: Supply and install heavy-duty tempered glass shower doors (thickness, frame finish, and style to be finalized by CG POC. Waterproofing: Apply high-quality, mold-resistant 100% silicone sealant along all metal-to-surface boundaries to guarantee a completely watertight seal.
Plumbing Fixtures: Toilet Seats: Replace existing seats with new, commercial-grade, slow-close, ergonomic, solid plastic toilet seats matching the existing toilet bowls (elongated or round-front). Replace vanity faucets, showerheads, with water-efficient (Water Sense certified) options. Install goose necks in all showers to provide more height and install faucets with longer necks to better wash hands.
Replace p-traps where necessary and install insulated covers to prevent condensation.
Electrical & LED Lighting: Remove existing outdated light fixtures in showers and dressing areas and in the overhead. Leave all lighting above the sinks. Install energy-efficient LED vanity lights or wet-rated LED recessed downlights (minimum 90+ CRI, color temperature to be selected by Client, recommended 3000K–4000K).
Patching, Painting, and Drywall Repair: Patch all drywall holes, dents, cracks, and moisture-damaged areas (using moisture-resistant greenboard where replacements are required). Sand smooth.
Priming: Apply one (1) coat of high-quality, mold-inhibiting primer to all repaired areas, walls, and ceilings. Painting: Apply two (2) coats of premium, low-VOC, moisture- and mildew-resistant interior paint (Semi-Gloss White) to all walls, ceilings, and trim. Leave 1 gallon of paint for future touch-ups.
2.2 Submittals
The contractor shall submit the following for Coast Guard Approval before getting approval to start work:
Indented product details with color samples for tiles - due to Coast Guard Technical
POC within 10 business days from award.
Intended Project Schedule - contractor shall provide initial written project schedule to
Coast Guard Technical Representative indicating intended series of tasks in different space within 10 business days of award. The Coast Guard and contractor shall work together to determine when to start/finish the schedule to least impact the Coast Guard operations within the building. The contractor shall not be working in more than ½ the building at any time to allow the tenant partial access to their space.
2.3 Unexpected Hazardous Materials Protocol
If, during the performance of work under this contract, the contractor encounters any previously unidentified material that is suspected to be hazardous (including, but not limited to, lead, asbestos, heavy metals, or toxic chemical residue) outside of the areas already documented in the provided survey report (AESS Job No. 26-092), the contractor shall:
Immediately halt work in the affected area and secure the immediate vicinity to prevent personnel exposure or disturbance of the suspect material.
Implement appropriate local controls to isolate the area.
Notify the Unit Point of Contact (POC) and the Contracting Officer (KO) verbally within four (4) hours, followed by written notification within twenty-four (24) hours.
Do not resume work in the affected area until the material has been formally tested, characterized, and certified safe, or until proper abatement is completed and the Contracting Officer issues written authorization to proceed.
3.0 Period of Performance
A schedule for work shall be agreed upon within 15 days of award. All work shall be completed within 60 days from the start date.
4.0 Laydown and Material Storage
The Coast Guard POC will coordinate an appropriate amount of storage space as necessary for equipment and material storage during the project. The contractor is responsible for maintaining the security of this space and their equipment. This space shall be kept tidy at all times.
5.0 Technical Requirements
5.1 Codes and Standards
All work shall comply with the most current editions of all applicable federal, state, and local codes, all applicable industry standards, and the following USCG-specific standards:
U.S. Coast Guard Safety and Environmental Health Manual, COMDTINST M5100.47(series)
OSHA Regulations
6.0 Personnel Security and Base Access
Background Checks: All contractor personnel requiring access to the USCG facility must successfully pass a background check as required by USCG security policies, which may include a National Crime Information Center (NCIC) check. The contractor shall submit personnel information to the USCG COR 14 days prior to the project start date.
Access Request: For access to the USCG facility, the contractor is required to submit the name and birthdate for each employee on the approved access request form at least 72 hours before their first day on site (this form will be provided after award).
Personnel not listed may be denied access to the Coast Guard facility.
Identification: A Real ID-compliant driver's license or other federally approved identification is required for base access. Acceptable forms of ID include: US Government Dependent ID, Federal PIV Card, TWIC Card, Veteran Health Identification Card, US Passport, or Permanent Resident Card. Driver's licenses from states that are not Real ID compliant will not be accepted.
Vehicle Requirements: All contractor vehicles must have valid registration and insurance, and all vehicle operators must have a valid driver's license. Vehicles shall always stay on marked and paved roads – vehicles are not permitted to drive or park on the grass at any point in this project performance without written approval from the Coast Guard. Any damage from driving or parking on the grass, to include the sprinkler system, shall be the responsibility of the contractor to repair.
Conduct: Contractor personnel shall adhere to all base regulations, traffic laws, and security protocols. Contractors must wear company identifying clothing/badging/safety gear, and all contractor vehicles must display company or subcontractor decals.
7.0 Work Hours
Work shall be performed between the hours of 7:00 AM and 5:00 PM, Monday through Friday, excluding Federal Holidays, unless otherwise approved in writing by the Contracting Officer, COR or USCG POC.
8.0 Safety and Environmental Protection
All operations must comply with the USCG Safety and Environmental Health Manual, COMDTINST M5100.47 (series). The contractor is responsible for proper handling and disposal of any hazardous materials and for immediately reporting and containing any spills.
9.0 Government Furnished Services
The Government may furnish potable water and electrical power at no cost to the contractor where available. All electrical connections shall be in accordance with the National Electric Code. The contractor shall provide and use ground fault circuit interrupter (GFCI) devices when connecting to Government power sources.
10.0 Travel Requirements
There are no travel requirements away from the primary performance location of Yerba Buena Island, San Francisco, CA.
11.0 Acceptance Criteria
Final acceptance of the work will be granted by the USCG COR after a final inspection confirms that all tasks in this SOW have been completed, the installation meets all technical and safety standards, and the site has been fully restored. Final payment will not be released until all deficient items have been corrected.
12.0 Coast Guard Technical Point of Contact
Primary POC for this Task is: CWO Joshua Alton – 503-939-3816
Secondary POC for this Task is: DCC Boe Siefke – 510-437-3150