SOW Sand filter removal~2.docx
DOCX document 47 KB Posted
- Solicitation number
- 24-422DNR-RESCO-B-40890
- Issued by
- Madison County, Illinois
About this file
This document is a Scope of Work issued by the Illinois Department of Natural Resources for the demolition and removal of 6 industrial-grade sand filters located at the Jake Wolf Memorial Fish Hatchery. The project involves the removal of the filter medium, piping, insulation, and other associated materials, followed by the lifting and transport of the filter housings to a designated garage door area using a 5-ton winch on site. Bids must be submitted electronically or using the attached Bid Form, with the bid due date and time specified in the BidBuy solicitation. The project must be completed by November 1, 2024, unless an extension is agreed upon by the contractor and the Department of Natural Resources. The contractor must have a minimum of 3 years of experience in the commercial demolition industry and be permitted to work in confined spaces. The contract will be awarded to the lowest, responsible, and responsive bidder, and the Department reserves the right to reject any or all bids.
Prevailing wage rates, certified payroll requirements, subcontractor information, insurance, and bonding requirements are specified. The project may be funded in part by tax-exempt bonds, and payments will be made in accordance with the State Prompt Payment Act. Contractors must be participants in approved apprenticeship and training programs, maintain an Illinois office, and comply with the Steel Products Procurement Act.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S and D~5.pdf | ||
| Standard Certifications V23.1~7.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ILLINOIS DEPARTMENT OF NATURAL RESOURCES
SMALL PURCHASE PROCUREMENT
SCOPE OF WORK & PROJECT REQUIREMENTS
Date: November 27, 2023 File# 4-24-032
LOCATION: Jake Wolf Memorial Fish Hatchery
PROJECT TITLE: Demo and remove 6 Industrial Sand filters.
PROJECT NARRATIVE:
There are currently 6, 10-foot-tall industrial grade sand filters at the Jake Wolf Memorial Fish Hatchery that will need to be removed and disposed of. The Sand filters are made of thick steel and are full of gravel, of various sizes and sand. The sand filters are in a precarious spot, situated after our bank of water pumps. There is a 5-ton winch and I beam that will allow for the lift out of material and filter housing. The aggregate will need to be removed and then the filter housing can be removed via the 5 ton lift and placed in front of 12 foot tall garage door.
SCOPE OF WORK:
Per Sand Filter
Remove filter medium from sand filter, through either a vacuum truck, hand removal or other method approved by site supervisor. Media can be disposed of on site at designated locations roughly 3000 feet away. Vendor will be responsible for transport of media to site.
After media is removed, ductile iron piping, insulation and various wires and aluminum piping will need to be removed and disposed of by vendor. Placing haul away dumpsters on site that are removed post job completion is acceptable.
After all other materials are removed, sand filter will be lifted over bay of pumps with the 5-ton winch on site (materials to hoist filters will need to be provided by the vendors) to the 12 foot tall garage door at the far side of the room.
From there the vendor can disassemble with their tools or transport the filters whole either off site or to waiting scrap dumpster.
ATTACHMENTS:
The following documents are included:
1) N/A
PROJECT SPECIFICATIONS & REQUIREMENTS:
| A. | Project Specifications: |
| 1) | The awarded contractor must have a minimum of 3 years of experience in the commercial demolition industry and be able to provide examples of 5 similar projects if asked. Contractor needs to be permitted to work in confined spaces for this project. |
| B. | Project Instructions and Notes: |
| Please coordinate upcoming work schedule with Paul Brown 309 / 968-7531. |
1) Work Completed by Prime Contractor:
A minimum of fifty-one percent of the work shall be completed by the Prime Contractor on this project. Pursuant to (30 ILCS 500/1-15.17) the Contractor is the person having a contract with the Illinois Department of Natural Resources.
2) Coordination of Work Activities:
All work activities and entry to the site must be coordinated with the site superintendent.
3) Deliverables and Staff Training:
N/A
4) Independent Testing:
The Contractor shall pay all independent laboratory testing if so required.
5) Contractor’s Licensing and/or Certifications:
Contractor shall be responsible for compliance with all applicable contractor and trades person licensing with the appropriate State agency. This includes, but is not limited to:
a) Plumbing contractor needs to be permitted to work in confined spaces for this project.
6) Shop Drawings:
Submit for the approval of the DNR Project Architect/Engineer, shop drawings and product data for the following items:
N/A
7) As-Built Markups:
The Contractor shall hand mark one set of drawings with corrections, dimensions, and "As-Built" notes. These Drawings shall be delivered to the DNR Project Architect/Engineer upon construction completion and prior to final payment request.
| 8) | Extended Warranty: |
| a) | N/A |
| 9) | Contractor’s Schedule of Values: |
| The Contractor shall provide to the DNR Project Architect/Engineer, a cost breakdown of | |
| each item of work required to fulfill the contract. The breakdown shall be identified on | |
| the Contractor’s Schedule of Values (CSV) form included in the Attachments. |
10)
| C. | Project Requirements: |
| 1) | Project Meeting |
| PROJECT MEETING TO BE HELD: YES |_| NO |_|X | |
| MANDATORY ATTENDANCE: YES |_| NO |_|X |
| 3) | Duration |
| Bids shall be good for ninety (90) calendar days after the submittal date, or | |
| for an extended period, if agreed to in writing by the Bidder and DNR. |
| 4) | Prevailing Wage Rates |
| This contract [or agreement] calls for the construction of a “public work,” within the meaning of | |
| the Illinois Prevailing Wage Act, 820 ILCS 130/.01 et seq. (“the Act”). The Act requires | |
| contractors and subcontractors to pay laborers, workers and mechanics performing services on | |
| public works projects no less than the current “prevailing rate of wages” (hourly cash wages | |
| plus, amount for fringe benefits) in the county where the work is performed. The Illinois | |
| Department of Labor (IDOL) publishes the prevailing wage rates on its website at | |
| http://labor.illinois.gov/. IDOL revises the prevailing wage rates and the | |
| contractor/subcontractor has an obligation to check the IDOL’s web site for revisions to | |
| prevailing wage rates. For information regarding current prevailing wage rates, please refer to | |
| IDOL’s website. All contractors and subcontractors rendering services under this contract must | |
| comply with all requirements of the Act, including but not limited to, all wage requirements and | |
| notice and record keeping duties. |
| 5) | Certified Payroll |
| State law 820 ILCS 130/5 requires all contractors and sub-contractors working on state | |
| construction projects to submit certified payroll records to the Department of Natural | |
| Resources. The payroll records must include all workers employed by contractors on the | |
| project. |
In accordance with 820 ILCS 130/5, the contractor and sub-contractor(s) shall make and keep, for a period of 5 years from the date of the last payment made on or after January 1, 2014 (the effective date of Public Act 98-328) on a contract or subcontract for public works, records of all laborers, mechanics, and other workers employed by them on the project.
No later than the 15th day of each calendar month, the contractor shall file a certified payroll for the immediately preceding month with the Department of Natural Resources.
7) Apprenticeship-in-Training When applicable, the contractor and all subcontractors must be participants in apprenticeship and training programs that are both approved by and registered with the U.S. Department of Labor’s Bureau of Apprenticeship and Training. The program(s) must be in the same trade(s) in which the contractor or subcontractor performs work. For information on how to participate in or set up a program, contractors may call the U.S. Department of Labor at 312/596-5508 or visit their website http://www.doleta.gov/oa/ .
8) Illinois Office The bidder must certify that the bidder will maintain an Illinois office as the primary place of employment for persons employed in the construction authorized by the contract.
| 9) | Subcontractors |
| The Contractor shall identify the names of all subcontractors to be utilized by them in the | |
| performance of this contract, together with the anticipated amount of money that each | |
| subcontractor is expected to receive pursuant to this contract. Pursuant to Illinois Procurement | |
| Code (30 ILCS 500/1-15-108), a person or entity is not a “subcontractor” if that person only | |
| Provides goods or supplies that are incidental to the performance of a contract by a person | |
| who has a contract subject to the Code. |
| 10) | Insurance |
| Contractor shall, at all times during the term of this contract and any renewals or extensions, maintain and provide a Certificate of Insurance naming the State as an additionally insured for all required bonds and insurance. Certificates may not be modified or canceled until at least thirty (30) days’ notice has been provided to the State. Contractor shall provide: (a) General Commercial Liability insurance in the amount of $1,000,000 per occurrence (Combined Single Limit Bodily Injury and Property Damage) and $2,000,000 Annual Aggregate; (b) Auto Liability, including Hired Auto and Non-owned Auto (Combined Single Limit Bodily Injury and Property Damage), in amount of $1,000,000 per occurrence; and (c) Worker’s Compensation Insurance in the amount required by law. Insurance shall not limit Contractor’s obligation to indemnify, defend, or settle any claims. |
11) Performance Bond/Labor and Material Payment Bond Pursuant to the Public Construction Bond Act (30 ILCS 550/), a performance bond and a labor and material payment bond covering the faithful performance of the contract and the payment of all obligations arising thereunder, shall be required if the project cost exceeds $50,000. Each bond shall be in the full amount of the contract. The bond must be from a surety licensed to do business within the State of Illinois and acceptable to IDNR.
12) Minority Contractor Opportunity Initiative The State requires a fee of $15 to cover Expenses related to the administration of the Minority Contractor Opportunity Initiative. Any Vendor awarded a contract under Section 20-10, 20-15, 20-25 or 20-30 of the Illinois Procurement Code (30 ILCS 500) of $1000 or more is required to pay a fee of $15. The Comptroller shall deduct the fee from the first check issued to the Vendor under the contract and deposit the fee in the Comptroller’s Administrative Fund.
13) Permits and Licenses Permits and licenses necessary for the execution of the work shall be secured and paid for by the Contractor.
14) Utilities Before starting excavation, establish location and extent of underground utilities occurring in the work area. Contractor shall contact Joint Utility Locating Information for Excavators (J.U.L.I.E.) 800-892-0123.
15) Highway Permits The Contractor is responsible for contacting the appropriate County Superintendent(s) of Highways and/or other appropriate local officials concerning the proposed work activities on the project as they may relate to use of the County and local road system. Coordination of any activities of concern to the County or Township shall be the responsibility of the Contractor. Special attention shall be given to load limits and seasonal restrictions.
16) New Products Unless otherwise specifically provided in the contract documents, all materials, equipment and products incorporated in the work under the contract shall be new and of a suitable grade for the purpose intended.
| 17) | Steel Products |
| Any steel product(s) used or supplied in the performance of this contract shall be manufactured or produced in the United States, in accordance with the Steel Products Procurement Act, unless a waiver is granted by IDNR (30 ILCS 565/). |
18) Specified Materials Bids shall be based on providing all products/materials exactly as required by the project specifications. Contractor may select from the list of acceptable manufacturers, offer an “equal” product and provide proof of its capabilities to meet the project specifications or, for products specified only by reference or performance standards, select any product which meets or exceeds the specified standards, by any manufacturer, subject to the approval of DNR.
19) Final Cleaning Contractor shall clean-up all work related debris and construction materials and properly dispose off-site. The Contractor shall repair and otherwise make good any damage caused by the work and leave the premises in the equivalent of the original condition.
20) Warranties The Contractor warrants that all work provided under the contract will be in conformance with the contract and free from defects in workmanship, materials, and equipment for a period of one year from the goods acceptance date. See Section B. Project Instructions and Notes, for any extended warranties that may apply.
22) Inducement Resolution All or a portion of this project may be paid or reimbursed from the proceeds of tax-exempt bonds subsequently issued by the State.
23) Payment Payments, including late payment charges, will be paid in accord with the State Prompt Payment Act and rules when applicable, 30 ILCS 540/; 74 III. Adm. Code 900. This shall be the Contractor’s sole remedy for late payments by the State. Payment terms contained in Contractor’s invoice(s) shall have no force or effect.
| 24) | Contract Award |
| Contract award will be made to the lowest, responsible, responsive bidder. The Department of Natural Resources reserves the right to reject any or all bids. |
| 25) | Term of Contract |
| All work shall be completed by November 1, 2024 unless agreed to by both the Contractor and | |
| DNR, that a time extension is warranted. |
26) Bid Submittal Bids may be submitted electronically on BidBuy or by submitting the attached Bid Form.
| 27) | Bid Submittal Date and Time |
| Refer to the BIDBUY solicitation for the bid date and time. |
| Project Architect/Engineer: | ||
| Engineer: John Cronin | ||
| Illinois Department of Natural Resources |
Address: One Natural Way Springfield, IL 62702
| Phone: 217 / 782 - 3484 |
| E-mail: john.cronin@illinois.gov |
| Site Superintendent: | ||
| Name: Paul Brown | ||
| Illinois Department of Natural Resources |
Address: 25353 Fish Hatchery Road Topeka, IL 61567
| Phone: 309 / 968 - 7531 |
| E-mail: Paul.p.brown@illinois.gov |
| Billing: | |||||
| Erick Huck | |||||
| Illinois Department of Natural Resources | One Natural Resources Way | Springfield, IL 62702 | |||
| Phone: 217-782-5694 | |||||
| Fax: | 217-782-9599 | ||||
| E-mail: erick.huck@illinois.gov |