This is a Statement of Work (SOW) for repairs and reconfiguration of an inventory supply cage at U.S. Coast Guard Air Station Detroit. The project encompasses reconfiguration of the current supply cage, completion of a small drywall section, and renewal of the existing epoxy floor at 1461 N Perimeter Road, Selfridge Air National Guard Base, Michigan 48045. The contractor must provide all necessary labor, materials, and equipment to complete the work as specified in the detailed requirements.

This is a total small business set-aside solicitation with NAICS code 236220 and a small business size standard of $45.0 million. The U.S. Coast Guard intends to award a firm-fixed-price contract based on responses to this solicitation. Quotes must be submitted via email to Contract Specialist Kara Davis at kara.a.davis@uscg.mil no later than August 28, 2026, at 4:00 PM Eastern Time. Site visits are highly encouraged and can be scheduled through Project Point of Contact EMC Alexander E Karjala at (603) 852-0384 or Alexander.E.Karjala@uscg.mil. All questions must be submitted to Kara Davis via the attached Request for Information form at least five days prior to the bid deadline, with responses provided via amendment rather than oral communication.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Updated 26MAR2026

In SCOPE OF WORK: AMO Supply Cage Reconfiguration at CG AIRSTA Detroit

1. GENERAL REQUIREMENTS:

The work consists of providing all labor, materials, and equipment necessary to reconfigure current supply cage, finish a small section of drywall, and renew current epoxy floor at USCG AIRSTA Detroit, 1461 N Perimeter Rd, Selfridge Air National Guard Base, MI 48045.

2. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK:

Upon acceptance the contractor shall commence work NLT five (5) calendar days after notice to proceed and work diligently to complete the entire work ready for use by 30 days after contract award.

3. SCOPE OF WORK:

Due to a lack of security measures involving an extensive amount of high-cost items stored for aircraft in our AMO supply cage, work needs to be done to reconfigure and refinish the space. The current cage system follows along the length of the space and has a sliding cage door for access. The cage needs to be reconfigured in order to add more secure storage space. There is also a small section of drywall at the closet in the secured space area that needs to be finished, and the current epoxy floor needs a clean and renewed surface. Contractor will conduct all reconfiguration and installation, repairs, and provide materials necessary to cover these items for operations at USCG AIRSTA Detroit, 1461 N Perimeter Rd, Selfridge Air National Guard Base, MI 48045.

4. DESCRIPTION OF FACILITY:

The AMO supply cage room is located in the southeast corner of the Maintenance Hangar (building 1401) at USCG AIRSTA Detroit located within SELFRIDGE ANGB. The contractor will be escorted to this location by the Contracting Officer’s Representative in order to complete any assessments and will be required to submit for visitor badge approval with SELFRIDGE ANGB.

5. DESCRIPTION OF WORK:

The contractor shall provide labor, equipment, and materials necessary to reconfigure, repair, and renew the following:

1. Conduct work in a safe and professional manner. Ensuring space is properly set for work and communicating the need for any hot work chits at least 2 weeks in advance of the project. Coast Guard AIRSTA Detroit will be responsible for obtaining the hot work chit from the Selfridge ANGB Fire Department located here within the installation.

2. Cage Reconfiguration

· Please see attachment with floor plan drawings at the bottom of this document for reference.

· Current cage in the AV Maint. Shipping and Receiving space runs the length of the space. About halfway down the run, the cage will need to turn 90 degrees towards the AV Supply Logistics Staff Office. Wall should come in perpendicular to the office wall, with about 3 feet of space between the new cage wall and the office door.

· The rest of the cage from the intersection of the new cage wall to the double doors on the north side of the shipping and receiving area, plus the sliding door shall be completely removed.

· In the middle of the new cage wall, a new cage door (swinging) should be installed so that it hinges on the right side (looking north) and swings into the new secured space area. On that door should be a Simplex 1000-style lock that has multiple buttons, requiring a combination style entry.

3. Drywall repairs

· Please see attachment with floor plan drawings at the bottom of this document for reference.

· The small utility closet in the northeast corner of the AMO supply cage needs drywall to be finished. The drywall is installed, but it needs cornerbead and mud on the interior and exterior of the closet.

4. Floor renewal

· Please see attachment with floor plan drawings at the bottom of this document for reference.

· The current floor in the AMO Supply cage area has previously been epoxied and needs to be refreshed and renewed. Floor should be cleaned, and a new topcoat should be put down on the floor. Top coat can be clear and transparent like the current coating.

6. CONTACT ADMINISTRATOR/POINT OF CONTACT:

The following employees of the U.S. Coast Guard identified will use all powers under the contract to enforce its faithful performance: EMC Alexander E Karjala & LT Quinn Hathcock.

7. CONTRACTING OFFICER:

All orders from the U.S. Coast Guard shall be transmitted and communicated through the Contracting Officer. The appointed Contracting Officer is Mr. Timothy Arnold.

8. CONTRACTING OFFICERS TECHNICAL REPRESENTATIVE (COTR):

The COR shall work with the contractor on a daily basis in scheduling and coordinating services, answering questions in conjunction with the scope of work (SOW), and provide general direction under the resulting contract: EMC Alexander E Karjala.

9. INCURRED COSTS:

The contractor shall furnish all supplies including consumable materials and tools to reconfigure/repair/replace all requirements in this scope of work.

10. ENVIRONMENTAL PROTECTION REQUIREMENTS:

Hazardous materials used by a contractor are required to be disposed of by that contractor.

Disposal must be in accordance with federal, state, and local guidelines.

11. ENCLOSURES: