This is a Statement of Work (SOW) for retention pond vegetation removal services required by the U.S. Department of Agriculture, Agricultural Research Service (USDA-ARS) at their Center for Medical, Agricultural and Veterinary Entomology facility located at 1700 SW 23rd Drive, Gainesville, Florida 32608.

The contractor shall perform a one-time cleanout and vegetation removal of the stormwater retention pond, including removal of all vegetation within the pond and removal of specified trees and vegetation immediately surrounding the pond perimeter. Wet debris may be temporarily piled on-site for removal after drying, with all debris either hauled off-site or mulched on-site as appropriate. The contractor must furnish all necessary personnel, supplies, and equipment to complete the work. The related solicitation (1232SA26Q0567) indicates that interested contractors may attend a mandatory or optional site visit scheduled for Wednesday, May 13, 2026, at 8:00 am EST, with advance notification required by 2:00 pm CST on Tuesday, May 12, 2026, sent to lynn.hults@usda.gov. Quotes should be submitted directly to the point of contact identified in the solicitation documents.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RETENTION POND VEGETATION REMOVAL

USDA-ARS-CENTER FOR MEDICAL, AGRICULTURAL AND VETERINARY ENTOMOLOGY

1700 SW 23rd Drive Gainesville, Florida 32608

The U.S. Department of Agriculture, Agricultural Research Service, requires cleanout/vegetation removal of stormwater retention pond at the above address.

This will be a one-time service.

Service Required:

· Removal of all vegetation in retention pond

· Removal of specified trees and vegetation immediately around retention pond

· Wet debris may be piled for removal after drying

· All debris will either be hauled off site or mulched on site

The contractor will furnish all personnel, supplies and equipment to perform service.