This statement of work outlines the requirements for a contract to remove asbestos and lead from a residence and adjacent structures at the Kern National Wildlife Refuge in California. The contractor will remove siding, facia, eaves, and vinyl flooring from a 3-bedroom, 1-bath house and attached garage/shed after inspection found asbestos and lead present. The contractor must properly dispose of all removed materials at an approved waste site. Work must be completed by September 30, 2023. The contractor will provide all necessary equipment and labor for the removal and disposal, while refuge personnel will provide site access and be available during demolition. The technical point of contact is the refuge manager.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Removal and Disposal of Asbestos and Lead in Residence 64

1. GENERAL:

The U.S. Fish & Wildlife Service, Kern National Wildlife Refuge (KNWR) has a need to remove the siding, facia, eaves, and vinal flooring of a single story 3 bedroom 1 bath house 64 (approx. 1700 sq.ft) and the adjacent garage/shed (750 sq. ft). The site is approx. 20 miles west of Delano, CA. The buildings were inspected/tested for asbestos and lead on 4/29/23. The inspection report will be attached at the end of this statement of work. This contract will include the removal of the siding, facia, eaves, and vinal flooring in accordance with Federal/State/County asbestos and lead removal and its proper disposal.

2. SCOPE:

Contractor will provide any equipment and labor for the removal of the siding, facia, eaves, and vinal flooring. Contactor will properly disposal of all material that is removed.

Access to site is by gravel/dirt road and a gated chain-link fence, see attached photos.

KNWR personnel will be available to provide access to the site and will be available during the demolition process. A site inspection is recommended and available upon request.

3. PLACE/DELIVERY AND PERIOD OF PERFORMANCE:

Kern NWRC 10811 Corcoran Rd.

Delano, CA 93216

Work needs to be completed no later than September 30, 2023.

4. INSPECTION AND ACCEPTANCE:

All work included in the contract specifications shall be subject to inspections by the U.S.

Fish and Wildlife Service at periodic intervals during performance of this contract. Final acceptance shall be based upon satisfactory completion of the work in accordance with the specifications on a task by task basis.

5. AVAILABILITY:

Normal office duty hours are Monday thru Friday, 7:00 AM – 4:30 PM. In the event of emergencies, the Vendor shall provide contact information. FWS Non-duty hours include weeknights, weekends, and Government holidays but FWS personnel can be available if weekend or extended hours are needed by the contractor for job completion.

6. MATERIAL:

Vendor will supply all needed equipment and labor for removal and remove/haul all debris/materials to an approved county or state waste disposal site.

7. TECHNICAL COORDINATOR:

Miguel Jimenez, Refuge Manager 661-477-7023 Miguel_Jimenez@fws.gov