SOW Replace Interior Doors - Building 200 _19Apr2023.pdf

PDF 347 KB Posted

Attached to
Z2DA--Project Number: 662-23-122 Replace Interior Doors - Building 200 Federal contract opportunity
Solicitation number
36C26123R0043
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 21

About this file

This scope of work document outlines requirements for a construction project to replace interior doors at the San Francisco VA Medical Center Building 200. The contractor will be responsible for removing existing doors, frames, hardware, and installing new fire-rated doors and institutional grade resilient laminate doors along with mortise locks, hinges, closures, and crash hardware. A total of 240 corridor doors on four floors, 10 partition door sets, and 7 fire doors requiring 90-minute ratings must be replaced. The contractor must provide plans identifying door locations and a phasing plan. The period of performance is 278 days with work expected outside normal hours. The related federal contract opportunity is solicitation number 36C26123R0043 from the Department of Veterans Affairs for this interior door replacement project at the San Francisco VA Medical Center Building 200.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Project Number: 662-23-122 Replace Interior Doors - Building 200, newest first.
File Type Posted
Site Visit Presentation-11 July 2023.pdf PDF
36C26123R0043 0001.docx DOCX document
RFI-Answer to Questions-Final-28 Jul 2023.pdf PDF
Site visit log-11Jul2023.pdf PDF
ATTACHMENT A - PHASE 1 FACTOR 2 - EXPERIENCE.xlsx XLSX spreadsheet
DBA Wage Determination_San Mateo_CA20230018_23June2023.pdf PDF
Map of VAMC -San Francisco Campus.pdf PDF
ATTACHMENT B - PHASE 1 FACTOR 3 - PAST PERFORMANCE QUESTIONNAIRE.docx DOCX document
36C26123R0043.docx DOCX document
Specificaton_01 32 16 16_Network Analysis Schedules_21Apr2023.pdf PDF
SPECIFICATIONS PROJECT 662-23-122_28Jun2023.pdf PDF
ATTACHMENT C - PHASE 2 FACTOR 4 - Offeror Key Personnel.docx DOCX document
Price Breakdown Worksheet.pdf PDF
Combined Drawings Bldg 200.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

San Francisco VA Medical Center

4150 Clement St

San Francisco, CA 94121

Date: April 19, 2023

Project: 662-23-121, Replace Interior Doors – Building 200

Scope of Work

The San Francisco VA Medical Center requires the services of a qualified general contractor to execute the requirements of project 662-23-121, Replace Interior Doors – Building 200. This requirement is limited to the direct replacement of existing interior doors and related hardware. Areas of work are in Building

200 occurring on Ground, 1st, 2nd, and 3rd floor. Replacement doors are to be fit to existing frames. This requires individual measurements to coordinate hinge and strike placements. Replacement materials include door slabs, mortise locksets, hinges, closures, and crash hardware. Materials do not include lock cores which are to be relocated by the VA (removed from existing and reinstalled into new). Kickplates and glazing, where salvageable, are approved for reuse.

Specific specifications sections are provided however the VA standard master specifications are the standards from which any other sections would emanate.

Develop any other specification sections that may be required to lend sufficient detail to the requirement.

Provide floor plans to identify individual doors, numerically or otherwise to correspond to phasing plan and schedule

Generate and submit phasing plan and schedule

Submit products for review and approval from the VA. Products referenced are VA standard use items and substitutions, while possible, may not necessarily be approved. Hardware, Mortise –

Shlage Type S, and Egress – Von Durpin 9927 Rated Panic

Products and Quantities

Corridor Doors – 240 passage doors to corridor spaces have been identified, 63-G, 106-1st, 56-2nd, and

25-3rd floor. Roughly 75% of these doors are 36” however there are several 42” and 48” doors.

Replacement doors are all to be 45-minute rated to accommodate 1-hour barriers. Surface materials are to be an institutional grade resilient laminate with a Birch grain and color finish.

A total of 10 sets of corridor partition doors – 2-36” for a total opening width of 6’, exist that require a 45-minute rating. These have the same technical requirements as above.

Fire-Rated Doors – A total of six 6’ double egress and one 3’ single egress doors require replacement.

These are similar to the above in technical specifications however require a 90-minute rating.

Schedule for Design Build

ACTION CALENDAR

DAYS

AFTER …

Kick-Off Mtg/Preliminary Site Review 10 Notice to Proceed

35% Design Submittal & Mtg 30 Kick Off Meeting

35% VA Comments 7 35% Design Submittal & Mtg

65% Design Submittal & Mtg 21 35% VA Comments *Start mobilization & Phasing Plan

65% VA Comments 7 65% Design Submittal & Mtg

100% Design Submittal & Mtg 14 65% VA Comments

100% VA Comments 7 100% Design Submittal & Mtg

100% Final Documents Submittal 7 100% VA Comments

TOTAL CONSECTUTIVE DAYS 103

ACTION

CALENDAR

DAYS

AFTER …

Mobilization & Submit Phasing Plan 10 *65% Design Submittal & Mtg (Note Schedule Overlap)

Install Corridor Doors 160 Mobilization & Phasing Plan

Install Fire Rated Door 20 Install Corridor Doors

Final Inspection 10 Install Fire Rated Door

Contract End & Demobilization Date 10 Final Inspection

TOTAL CONTRACT DAYS 278

Constraints / Existing Site Conditions

Replacements are required to occur within a single day to include demolition of existing and reinstallation of new. The lone exception is where repair of frames are required which includes drying time. Close coordination is required with VA staff to minimize impact to operations as much of these doors exist in an operating clinical environment. It should be anticipated that roughly 50% of labor hours will be outside of normal business hours, or weekend hours and needs to be approved by contracting officer.

Period of Performance:

Period of Performance 278 Days

Bid Schedule

Base Bid

The offeror shall perform all work in this Scope of Work

File details come from the government source that posted it. Updated .