This is a Statement of Work (SOW) for the removal and replacement of three airfield lighting transformers at U.S. Coast Guard Base Cape Cod, Buzzards Bay, Massachusetts, with one optional transformer replacement. The contractor must remove and dispose of existing transformers and install new units in compliance with manufacturer specifications, the National Electrical Code (NFPA 70), FAA regulations, and all applicable federal, state, and local regulations. The three base transformers include: Transformer 413 (McGraw Edison, 37 KVA single phase) adjacent to building 614 and runway 23; Transformer 523 (McGraw Edison, 37 KVA single phase) adjacent to building 614 and runway 14; and Transformer 232177 (ABB, 1500/1680 KVA three phase) adjacent to building 3181 parking lot, which requires investigation for oil leaks with a feasibility analysis for repair or replacement. An optional fourth transformer (Southeastern Transformer Co., 15 KVA single phase, Transformer 575) adjacent to building 195 may be included.
Required work includes securing power to existing transformers, removal and off-site disposal at contractor expense, installation with necessary modifications per manufacturer instructions, operational testing, and power restoration to airfield equipment. The contract performance period is 45 calendar days from the Notice to Proceed. The contractor must submit a schedule of work, complete daily logs, provide qualified on-site supervision, obtain security clearances for all personnel (NCIC background checks required minimum 7 calendar days prior to access), comply with fire safety standards and OSHA regulations, obtain hot work permits for welding or torch work, and provide a one-year warranty on all work. Site visits are strongly recommended. Normal working hours are 7:00 A.M. to 4:00 P.M., Monday through Friday, excluding federal holidays, with written approval required for other times. The contractor is responsible for all hazardous materials handling, proper disposal documentation including bills of lading and landfill receipts, VOC compliance per Massachusetts regulations, and restoration of disturbed areas to pre-work conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW Replace (4) Airfield Transformers .pdf | ||
| 20260206_080225.jpg | JPG image | |
| 20260206_080243.jpg | JPG image | |
| SOW Replace Airfield Transformers (3) with (1) option.doc | DOC document | |
| Transformer_Standard Form 1449 - Solicitation_Contract_Order for Commercial Products and Commercial Services.pdf | ||
| DBA WAGES BARNSTABLE COUNTY.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
REPLACE AIRFIELD TRANSFORMERS
BASE CAPE COD
JULY 23, 2025
SECTION 01010
GENERAL REQUIREMENTS
PART 1 – GENERAL
1.1 SCOPE: The Contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to remove and dispose of existing airfield lighting transformers and replace with new (Fig. 1-11) at the U.S. Coast Guard, Base Cape Cod, on Joint Base Cape Cod, Buzzards Bay, MA, 02542.
1.1.1 Existing transformers: Contractors shall verify transformer specifications.
1) Transformer 413 (Fig. 1-3), adjacent to building 614 and runway 23. MANUFACTURER - McGraw Edison, Power System Division, Canonsburg, PA, 15317, single phase, 60 hertz, KVA 37 ½, 65° RISE, serial number 74ZD743004, voltage rating 4160GRD.Y/2400x12470GRD.Y/7200x13800GRD.Y/7970 240/120, cat nc. AAVL 115079A-37-K1, class OA, % IMP. 1.9 - 1.8, WDG MAT L.V. AL HV CU, wt.lb. 855, H.V. CONNECTION: VOLTAGE 2400 – SWITCH POSITION 2.4, VOLTAGE 7200 – SWITCH POSITION 7.2, VOLTAGE 7970 – SWITCH POSITION 7.9
2) Transformer 523 (Fig. 4-6), adjacent to building 614 and runway 14, MANUFACTURER - McGraw Edison, Power System Division, Canonsburg, PA, 15317, single phase, 60 hertz, KVA 37 ½, 65° rise, serial number 73ZE858030, voltage rating 4160GRD.Y/2400x12470GRD.Y/7200x13800GRD.Y/7970 240/120, cat nc. AAVL 115079A-37-K1, class OA, % imp. 1.9 - 1.8, WDG MAT L.V. AL HV CU, wt.lb. 855, H.V. CONNECTION: VOLTAGE 2400 – SWITCH POSITION 2.4, VOLTAGE 7200 – SWITCH POSITION 7.2, VOLTAGE 7970 – SWITCH POSITION 7.9
3) Transformer 232177 (Fig. 7-9), adjacent to building 3181 parking. MANUFACTURER - ABB, Power System Division, Jefferson City, MD, 21755, Three phase distribution, 60 hertz, KVA 1500/1680, 55/65° RISE, style number F3HF147L66, serial number 11JC572250001, MFG Date Jun-11, voltage rating 22860GRDy13200, HV BIL KV 125, HV MTL AL, % Impedance 5.75, Low voltage 4160Y/2400, LV BIL KC 60, LV MTL AL, Mineral Oil 513 Gallons. NOTE: The Contractor shall investigate and determine the existence of oil leaks and provide analysis/feasibility for replacement or repair.
4) Option Bid: Transformer 575 (Fig. 10-12), adjacent to building 195 and runway 5, Manufacturer Southeastern Transformer Co, Dunn, NC, single phase, 60 hertz, KVA 15, % imp. 3.6, serial number 1019102, volts 12470GRDY/7200-240/120
1.1.2 REQUIRED WORK: This list should not be considered complete. It represents the general items needed to complete the contract requirements.
1. The Contractor shall secure power to the existing transformers.
2. The Contractor shall remove and dispose of the existing transformers at Contractor’s expense off the Joint Base Cape Cod.
3. The Contractor shall install and make all necessary modifications needed to provide complete working systems per manufacturer’s instructions.
4. The installation shall be in accordance with all local, State, and Federal regulations
5. The installation shall comply with NFPA 70 National Electrical Code and FAA regulations.
6. The Contractor shall place new transformers into service restore power to airfield equipment.
7. The Contractor shall perform operational tests upon completion.
1.2 SITE VISITS: Bidders are strongly recommended to inspect the site where work is to be performed to satisfy them regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award. Arrangements for such visits shall be made by contacting the COR, Albert J. Pulsifer, at albert.j.pulsifer@uscg.mil, any questions regarding this specification or the work shall be addressed in writing and directed to the Contracting Officer.
1.3 LOCATION: Work will be performed at U.S. Coast Guard Base Cape Cod, Buzzards Bay, MA, 02542.
1.4 HOURS OF WORK: Normal working hours for the contract are 7:00 A.M. to 4:00 P.M., Monday through Friday (excluding Federal Holidays). If the Contractor desires to /work other than normal duty hours, on weekends or on federal holidays, he/she must request written permission from the Contracting Officer at least 36 hours in advance of such work and approval must be received prior to the requested work time. The Contractor shall coordinate the work schedule and all work with the COR. The Contractor shall not make any attempt to access any work areas without prior arrangements with the COR.
1.5 PRECONSTRUCTION CONFERENCE: Upon award of the contract and prior to starting the project, the Contractor shall attend a pre-construction conference with the Contracting Officer to ensure a complete understanding of the project. The Contractor shall pay for all expenses incurred by him in this regard. All questions shall be resolved and confirmed in writing if required.
1.6 SECURITY REQUIREMENTS: All Contractor personnel scheduled to work on JBCC shall be subject to a National Crime Information Center (NCIC) background check to gain access through the Base security gates. To process the NCIC background check, all Contractors shall provide the following information: name, citizenship, driver’s real license state and number, (or passport) and date of birth. The NCIC form shall be filled out by the Contractor, listing all personnel that require access to JBCC; form shall be submitted to the COR for processing at least 7 calendar days prior to the date of access.
1.6.1 Contractor’s vehicles shall have a valid and current proof of insurance and vehicle registration. The drivers and passengers shall have valid real licenses. All Contractor vehicles must enter the Base through the main gate on the Bourne side of the Base property.
1.7 REMOVAL OF CONTRACTOR EMPLOYEES: All employees of the Contractor in the performance of this contract, or any representative of the Contractor entering the worksite, shall abide by all applicable regulations and shall submit to security checks as may be deemed necessary. The Government reserves the right to direct the Contractor to remove from the performance under this contract, any employee, for misconduct or security reasons. This shall not relieve or constitute an excuse from the contract performance. Upon dismissal the employee shall render all identification for entry to the worksite.
1.8 SCHEDULE OF WORK: After receiving the notice to proceed, the Contractor shall submit a Schedule of Work on the Government furnished form or other form approved by the Contracting Officer. The Contractor shall not commence work under this contract without receiving a copy of the signed, approved schedule.
1.9 LABOR & DAILY LOGS: All personnel shall be skilled and have sufficient knowledge and experience necessary to perform work assigned to them. The Contractor shall complete the Base Cape Cod daily log form at the end of each working day and deliver weekly to the COR. The Government will attest to its accuracy by initialing the form and providing a copy back to the Contractor.
1.10 SAFETY: The Contractor shall take all necessary precautions to meet proper safety standards and regulations of the State and Federal Codes. OSHA regulations apply to all work performed on site. In addition, the Contractor shall conform to any restrictions as may be outlined by the Base Safety Officer and Fire Department during the contract. Prior to doing any welding or burning with a torch the Contractor shall obtain a “hot work” permit from the USCG FED Safety Office.
1.10.1 FIRE SAFETY: All requirements per Joint Base Cape Cod Fire Prevention Standard 911-1 shall be followed. A copy of the instructions will be provided.
1.11 ON SITE SUPERVISION: The Contractor shall always provide qualified supervision when work is being conducted by Contractor employees or Sub-Contractor employees. Prior to commencing work, the Contractor shall submit a letter to the Contracting Officer designating an employee from his/her company as the foreman or supervisor. The supervisor shall be on site any time work is being performed. The supervisor shall be able to read, write, speak English, and have the authority to approve and accept delivery orders and minor (under $2000.00) modifications to delivery orders.
1.12 PROTECTION OF PROPERTY: The Contractor shall comply with the requirements of Paragraph 52.236-9 and 52.236-10 of the Federal Acquisition Regulation and the following: All existing grounds, fences, utilities, equipment, building components and adjacent property, including vehicles, shall be protected from any damage resulting from contract operations. Contractors will be responsible for any damage to Government property. Damaged property (done by the Contractor) shall be repaired by the Contractor, at Contractor’s expense, to meet previous existing conditions.
1.13 HAZARDOUS MATERIAL: The Contractor shall be solely responsible for all Contractor generated or owned hazardous materials. While performing work Specific herein, if potentially hazardous materials are utilized a SD will be submitted to the COR prior to its use. If the hazardous materials are encountered, the Contractor shall notify the COR immediately. The Contractor’s responsibility for handling hazardous material is incidental to work performed, i.e., the Contractor shall handle, remove, and properly dispose of only those hazardous materials necessary to complete the contract work.
1.13.1 Any commercial adhesives, sealants, adhesive primers, sealant primers, and associated surface preparation and cleanup solvents in containers greater than a net volume of 16 fluid ounces, or a net weight of one pound shall not exceed volatile organic compounds (VOC) limits as established in the Massachusetts Department of Environmental Protection promulgated Adhesives and Sealants regulations, 310 CMR 7.18(30)."
1.14 DISPOSAL OF REMOVED MATERIALS: Dumpsters placed on site require a permit. Permits are obtained from the USCG FED Safety Office. All material removed by the Contractor that is not indicated to be salvaged by the Government shall become the property of the Contractor. This material shall be disposed of legally off Joint Base Cape Cod property. The Contractor shall not cause, suffer, or permit the handling, transportation, or storage of any material in a manner which results, or may result in emissions that cause or contribute to a condition of air pollution, any debris which could create air-borne dust must be shipped in a closed container or wet down and securely tarped over. The Contractor is responsible to comply with all applicable federal, state, and local environmental and disposal regulations. The Contractor shall submit to the COR the following:
1.14.1 Bill of lading for all disposed materials.
1.14.2 Copy of landfill receipts.
1.14.3 Recyclers operating permit.
1.15 SUBMITTAL DESCRIPTION: Samples, catalog cuts, shop drawings, and other information shall be submitted by the Contractor as required by the list of submittals on the Submittal Register Form(s) which is included in this specification. No other forms shall be used or will be accepted by the COR
1.15.1 The Contractor shall submit a list of all hazardous materials with Safety Data Sheets (SDS) to the COR for approval prior to work commencement on this project. Storage of hazardous materials will not be permitted on Joint Base Cape Cod property.
1.15.2 All materials used by the Contractor shall comply with VOC Emission limits for use in the Commonwealth of Massachusetts (310 CMR 7.00). Cleaning and maintenance of the Contractor's and Sub-Contractor's equipment shall not be conducted on Joint Base Cape Cod property.
1.15.3 The Contractor shall ensure that adequate protective measures are taken to minimize personnel exposure to harmful substances. If protective measures are required, the Contractor shall include them in a Safety Plan, and they shall be reviewed by the Contracting Officer prior to the start of any contract work involving use of the harmful substance.
1.16 RESTORATION AND CLEAN-UP: All areas disturbed by construction shall be restored to match the condition and material that existed prior to the start of work. The Contractor shall always keep the work areas clean of trash and debris. The Contractor shall not allow trash or debris to blow from the work area.
1.17 GOVERNMENT INSPECTION: The Contractor shall keep the COR informed of contract operations and plans so that they may arrange to be present at the various times that work is being performed.
1.18 PERFORMANCE PERIOD: All work under this contract including site cleanup, punch list, acceptance by the COR and required submittals shall be completed within (45) calendar days of issuance of the Notice to Proceed (NTP) by the Contracting Officer unless stated otherwise.
1.19 WARRANTY: The provisions of the entire warranty clause from paragraph 52.246-21 (April 84) and Federal Acquisition Regulation are incorporated into this contract. The clause is written, in part, as follows:
“In addition to any other warranties set out elsewhere in this contract, the Contractor shall warrant that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material, or design furnished or workmanship performed by the Contractor or any of his Sub-Contractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the work.”
END OF GENERAL SECTION
Figure 1. Transformer 413, Serial #74ZD743004.
Figure 2. Transformer 413, Serial #74ZD743004 interior.
Figure 3. Transformer 413, Serial #74ZD743004 data tag.
Figure 4. Transformer 523, Serial #73ZE858030.
Figure 5. Transformer 523, Serial #73ZE858030 interior.
Figure 6. Transformer 523, Serial #73ZE858030 data tag.
Figure 7. Tranformer 168613, Serial # 232177
Figure 8. Tranformer 168613, Serial # 232177 interior
Figure 9. Tranformer 168613, Serial # 232177 Data Tag
Figure 10. Option Transformer 575, Serial #1019102.
Figure 11. Option Transformer 575, Serial #1019102 interior.
Figure 12. Option Transformer 575, Serial #1019102 data tag.