This is a Statement of Work for fire alarm control panel repair and replacement at the Domenici Fitness Center, Building 588, Holloman Air Force Base, New Mexico, dated 11 May 2026 (Work Request 18349091).
The contractor must replace a failed Edwards EST 2 fire alarm control panel with a compatible Edwards IO Series fire alarm control panel and associated electronics to restore the fire alarm system to its original operational status or better. The new panel must interface with the existing Monaco Enterprises BT2-4 transmitter to communicate with Fire Station 1, D-21 system. Additionally, the contractor shall provide, install, and integrate five replacement devices: two pull stations (Second floor office Room 211 and Pool east end Room 167), one smoke detector (First floor office Room 132), one duct detector (Mechanical Room 212), and one booster power supply (Janitor Room 205). The contractor is responsible for furnishing all labor, equipment, materials, tools, and transportation; maintaining a clean work area with complete cleanup at contract end; and coordinating work schedules with building facility managers and the Holloman AFB Alarm Shop, with a required ten-day notice for any power outages. Equipment, installation, and programming must include manufacturer and contractor standard warranties. The contractor must be authorized to install Edwards proprietary software systems and must adhere to UFC 3-600-01, UFC 3-601-02, NFPA 70, and NFPA 72 standards. Any uninstalled or replaced equipment becomes property of 49 CES and must be provided to the 49 CES/CEOFA Alarm Shop.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FIRE ALARM CONTROL PANEL REPAIR
DOMENICI FITNESS CENTER, BUILDING 588
HOLLOMAN AFB, NEW MEXICO
WORK REQUEST 18349091
11 May 2026
General Requirements:
1. The Contractor shall furnish all labor, equipment, materials, tools, and transportation necessary to accomplish the work.
2. Any damaged areas shall be restored to match the existing construction.
3. The work area shall be kept reasonably clean at all timesalways kept reasonably clean. The Contractor shall perform a complete cleanup of the work area at the end of the contract.
4. The Contractor shall coordinate their work schedule with the building facility managers and the Holloman AFB Alarm Shop to allow access to work areas in the building and to minimize any work disruptions. A ten (10) day notice of any power outage is required.
Specific Requirements
1. The existing Edwards (formerly Edwards Systems Technology) EST 2 fire alarm control panel has failed, is not repairable, and a replacement EST 2 panel is unavailable. To repair the building’s fire alarm system and use the existing detectors and notification devices, the EST 2 panel is to be replaced by a compatible Edwards IO Series fire alarm control panel and any other electronics required for bringing the fire alarm system to a status comparable to or better than the original fire alarm system design. The contractor shall provide, install, and program, the new Edwards IO Series panel and associated equipment so that the facility has a working fire alarm system. It must interface with the existing Monaco Enterprises BT2-4 transmitter so as to communicate with the Fire Station 1, D-21 system.
2. Five devices in the existing fire alarm reporting system have been identified as having failed. This contract is to include providing, installing, and integrating replacement devices. The devices are:
a. Pull station (Second floor office, Room 211)
b. Pull station (Pool east end, Room 167)
c. Smoke detector (First floor office, Room 132)
d. Duct detector (Mechanical Rm, Room 212)
e. Booster power supply (Janitor, Room 205)
3. If additional fire alarm system devices are discovered to have failed or are missing, the project manager and 49 CES/CEOEF Alarm Shop shall be notified. The contractor shall provide a quote for providing and installing the devices.
4. The Edwards fire alarm system products use proprietary software, requiring an authorized company to install and program the new fire alarm panel, interfacing it with the existing and new devices.
5. Provided equipment, installation, and programming for the hardware and software must include the manufacturers and contractor’s standard warranty. Any currently installed equipment which is ultimately uninstalled or replaced will remain the property of 49 CES and must be provided to the 49 CES/CEOFA Alarm Shop.
6. The Contractor shall adhere to the most current editions of the UFC 3-600-01 Fire
Protection Engineering for Facilities, UFC 3-601-02 Fire Protection Systems
Inspection, Testing, and Maintenance, NFPA 70 National Electric Code, NFPA 72
National Fire Alarm and Signaling Code, for this repair project.
END OF STATEMENT OF WORK