SOW_PTOWN - Replace bathroom and galley pipes.docx
DOCX document 10 MB Posted
- Solicitation number
- 37020250000018
About this file
This Statement of Work outlines requirements for replacing bathroom and galley sewer pipes at USCG Station Provincetown's Multi-mission Building (MMB) located at 125 Commercial St, Provincetown, MA. The contractor must remove and replace failed cast iron sewer pipes in both the bathroom and galley areas with heavy-duty PVC pipes, repair associated water damage to studs/drywall, replace concrete and tile flooring in the galley area, and reconnect the galley garbage disposal. The existing damage has left two duty rooms without bathroom facilities and rendered the galley disposal inoperable.
The work must be completed within 30 calendar days of contract issuance, with normal working hours from 7:00 AM to 4:30 PM Monday through Friday. The contractor must provide their own sanitation facilities and supervision, with a designated on-site foreman required whenever work is being performed. The contract includes a one-year warranty period from final acceptance. Key points of contact are MKC Paul Lehman (QAI) and CWO Steve Mensen (Facilities Engineer). Site visits are strongly encouraged for bidders to assess conditions before submitting proposals.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DBA WAGES BARNSTABLE COUNTY.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
USCG STATION PROVINCETOWN
Replace bathroom and galley pipes
STATEMENT OF WORK
FOR
USCG Station Provincetown Replace bathroom and galley pipes
GENERAL REQUIREMENTS
PART 1 – GENERAL
1.1 SCOPE: The Contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to replace a bathroom and a galley sewer pipe in the Multi-mission Building (MMB).
1.1.1 Work shall include providing all transportation, materials, and labor. The awarded contractor shall complete the following.
· Removal of current failed/cracked cast iron sewer pipe in bathroom.
· Replace cracked pipe with heavy duty, to code, PVC pipe and connections.
· Confirm repair will not leak.
· Cut out and replace any studs/wood/drywall where there has been rot/water damage to this area.
· First, snake the current failed/clogged cast iron sewer pipe underneath galley from the clean-out, outside of the MMB.
· If current failed/clogged cast iron sewer pipe can’t be snaked, remove this failed/clogged pipe and replace with heavy duty, to code, PVC pipe and connections.
· Confirm repair will not leak.
· Replace concrete and tile floor in galley, as there is no basement under the galley area.
· Re-connect galley garbage disposal to be used by station.
· Use the Clean Out, outside of the MMB to make sure all sewage pipes flow to the city’s main line.
· Clean areas of debris and dispose materials.
1.2 EXISTING CONDITIONS: The existing section of damaged bathroom piping leaves two duty rooms without bathroom use including shower, sinks and all drains. See pictures of existing cracked pipe. The existing section of failed piping in the galley prohibits the use of the galley garbage disposal. See pictures of where the failed/clogged pipe is approximately located.
1.3 SITE VISITS: Bidders are strongly encouraged to inspect the site where work is to be performed to satisfy them regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award. Arrangements for such visits shall be made by contacting Facilities Engineer- CWO Steve Mensen (FE). Any questions regarding this specification or the work shall be addressed in writing and directed to the Contracting Officer.
1.4 LOCATION: 125 Commercial St, Provincetown, MA 02657
1.5 HOURS OF WORK: Normal working hours for the contract are 7:00 A.M. to 4:30 P.M., Monday through Friday. If the Contractor desires to work other than normal duty hours, on weekends or federal holidays, he/she must request written permission from the FE at least 24 hours in advance of such work and approval must be received prior to the requested work time.
1.6 COORDINATION OF CONTRACT WORK WITH GOVERNMENT WORK: The Government will continue to operate within its buildings and areas during the execution of the contract. The Government will keep interference with the Contractor’s operation to a minimum. The Contractor shall conduct his/her operations so as not to interfere with the Governments operation of the facility.
1.7 SANITATION FACILITIES: To be provided by the contractor.
1.8 ON SITE SUPERVISION: Prior to commencing work, the Contractor shall submit a letter to the FE, designating an employee from his/her company as the foreman or supervisor. The supervisor shall be on site any time work is being performed.
1.9 PROTECTION OF PROPERTY: The Contractor shall comply with the requirements of Paragraph 52.236-9 and 52.236-10 of the Federal Acquisition Regulation and the following: All existing grounds, fences, utilities, equipment, building components and adjacent property, including vehicles, shall be protected from any damage resulting from contract operations. Contractors will be responsible for any damage to Government property. The contractor, at contractor’s expense, to meet previous existing conditions, shall repair damaged property (done by the contractor).
1.9.1 The Contractor shall take all necessary precautions to meet proper safety standards and regulations of the State and Federal Codes. OSHA regulations apply to all work performed on site. In addition, they shall conform to any restrictions as may be outlined by the Sector Safety Officer during the course of the contract. Contractor shall comply with all federal and state environmental regulations including local Coast Guard policies.
1.10 DISPOSAL OF REMOVED MATERIALS: All material removed by the Contractor that is not indicated to be salvaged by the Government shall become the property of the Contractor. This material shall be disposed of legally off Coast Guard property. The Contractor shall not cause, suffer, or permit the handling, transportation, or storage of any material in a manner that result, or may result in emissions that cause or contribute to a condition of air pollution, any debris that could create air-borne dust must be shipped in a closed container or wet down and securely tarped over. The contractor is responsible to comply with all applicable federal, state and local environmental and disposal regulations.
1.11 RESTORATION AND CLEAN UP: All areas disturbed by construction shall be restored to match the condition and material that existed prior to the start of work. The contractor shall keep the work areas clean of trash and debris at all times. The contractor shall not allow trash or debris to hinder Station work.
1.12 UTILTIES: Electrical 110/120 V outlets are available, contractor responsible for providing extension cords.
1.13 GOVERNMENT INSPECTION: The Contractor shall receive approval before install of shingles, siding, and flashing and shall keep the QAI informed of contract operations and plans so that they may arrange to be present at the various times that work is being performed. Inspector must be present for operation testing and pressure testing.
1.14 DRAWINGS: See pictures below.
1.15 PERFORMANCE PERIOD: All work under this contract including site cleanup, punch list, acceptance by the QAI and required submittals shall be completed within 30 calendar days of issuance of the contract by the Contracting Officer unless stated otherwise.
1.16 WARRANTY: The provisions of the entire warranty clause from paragraph 52.246-21 (April 84) and Federal Acquisition Regulation are incorporated into this contract. The clause is written, in part, as follows:
“In addition to any other warranties set out elsewhere in this contract, the Contractor shall warrant that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material, or design furnished or workmanship performed by the Contractor or any of his subcontractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the work.”
POC’s
Onsite QAI: MKC Paul Lehman, 407-579-4750
Sector SENE Facilities Engineer: CWO Steve Mensen 440-787-5429
Pictures of cracked/failed pipe in bathroom.
Sewage/mold drywall, to be replaced in bathroom.
Sewage/mold/rot/water damage around toilet area, to be replaced in bathroom.
Sewage/mold/rot/water damage inside wall, to be replaced in bathroom.
Pictures of where the failed/clogged pipe is approximately located.
Pictures of where the failed/clogged pipe is approximately located.
image1.png image2.png image3.png image4.png image5.png image6.png image7.png image8.png image9.png image10.png image11.png image12.png image13.png image14.png image15.png image16.png