This is a Statement of Work (SOW) for the United States Coast Guard (USCG) related to fire system inspection and maintenance for the CGC OSPREY vessel. The solicitation (52000QR250020216) is a small business set-aside seeking a contractor to perform CO2 system inspection, hydrostatic testing, and recertification of the vessel's CO2 flooding system and R-102 galley range guard fire system. The project requires trained personnel to complete the work in accordance with specific Coast Guard maintenance protocols, with performance to be completed by August 28, 2025, at the vessel's homeport in Port Townsend, Washington.

The procurement will be awarded on a firm-fixed price basis using simplified acquisition procedures, with quotes due by July 21, 2025, at 9:00 AM Eastern Standard Time. Interested vendors must be registered in SAM.gov and submit a quote including cost breakdown, unit cost, extended price, total price, payment terms, and company details. The contracting officer is Timothy S. Ford, and the technical point of contact is MKC Amanda Cole. The solicitation allows the government to award on an all-or-none basis and will select the most advantageous quote considering price and other factors.

View the file

Other files

File Type Posted
Smart Matrix SAP CM FFP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) CGC OSPREY Fire System Inspection

PR# 52000PR250020216

1. Background and Current Observed Issues CGC OSPREY is requires inspection/certification and hydrostatic testing of the installed CO2 system and inspection/certification of the Galley range guard R-102 fire system.

2. REFERENCES

CG MPC N33005.D

CG MPC N10047.0

3. REQUIREMENTS

Entity completing the work will have trained personnel. Contractor must inspect and repair the installed CO2 flooding system to ensure CO2 bottle is refilled and hydrostatically tested and recertify system IAW CG MPC N33005.D. Contractor must inspect/certify the installed R102 galley range guard system.

4. PERIOD OF PERFORMANCE

The period of the performance is requested to be completed by 28 August 2025.

5. PLACE OF PERFORMANCE

The primary place of performance shall be at CGC OPSREY homeport located at below address:

CGC OSPREY

102 Benedict street Port Townsend WA 98368

Cutter Point of Contact:

MKC Amanda Cole, Engineer Petty Officer Cell: 360-301-3714 Email: Amanda.m.cole@uscg.mil

Contracting Officer Technical Representative (COR):

CWO Jim Beechey Office: (757) 628-4632 Email: James.E.Beechey@uscg.mil