SOW_New_Bus_Facility_Final_Revised_16_Oct2026.pdf
PDF 315 KB Posted
- Solicitation number
- RFP 126DX001
- Issued by
- Denver County, Denver City, Colorado
About this file
This is a Scope of Work (SOW) document prepared by the Regional Transportation District (RTD) in Colorado for consulting services related to alternatives analysis and environmental planning for a new bus operations and maintenance facility. The document outlines the consulting services required to support the development of this facility, including environmental planning work necessary for project advancement. The SOW establishes the framework for conducting comprehensive analysis and planning activities that will inform site selection, design considerations, and regulatory compliance for the proposed bus facility project. The contract includes a 10% Small Business Enterprise (SBE) goal as specified in the related contract opportunity.
The SOW details the scope of work, methodology, and deliverables expected from the selected consultant firm. The document serves as the technical requirements document that responding firms must address in their proposals. Environmental planning and alternatives analysis activities outlined in the SOW will support RTD's development objectives and regulatory requirements for the new facility. Firms responding to this opportunity must demonstrate their capability to execute the specified planning and environmental analysis tasks while meeting RTD's schedule and technical requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
We make lives better through connections.
Regional Transportation District 1660 Blake Street, Denver CO 80202 rtd-denver.com
Statement of Work
Alternatives Analysis and Environmental Planning for New Bus Facility
Version: V1.2
August 20, 2026 rtd-denver.com 1
Table of Contents
Project Overview
Schedule
Scope of Work
Summary of Project Tasks
Task 1: Project Management First Thirty (30) Days after NTP First Forty-five (45) Days after NTP First Sixty (60) Days after NTP Bi-Weekly or Monthly Recurring Activities Upon Completion of Project Deliverables
Task 2: Alternatives Analysis
Task 3: NEPA
Task 4: Stakeholder and Public Engagement
Task 5: Preliminary Engineering
Task 6: Funding Strategy
Task 7: FFTP Reassessment
Appendix rtd-denver.com 2
Project Overview The Regional Transportation District (RTD) is seeking consulting services to conduct environmental planning work necessary to support the development of a new bus operations and maintenance facility. A new facility has been identified in the agency’s long-range plans, including Reimagine RTD, completed in 2022, which analyzed RTD’s existing bus operations facilities and determined that RTD’s existing facilities were not adequate to meet the growing needs of the Denver region. The need for the facility was summarized in a July 29, 2025 board report (see “Bus Maintenance Facility Alternatives Analysis and National Environmental Policy Act Study” background report to the RTD Board of Directors). RTD’s Facilities and Fleet Transition Plan (FFTP), completed in 2024, also supported the need for a new bus maintenance facility and identified three RTD-owned properties as potential locations for this facility.
The consultant selected to perform this work will complete an Alternatives Analysis (AA) to identify a preferred site, complete Environmental Documentation required under the National Environmental Policy Act (NEPA) for development of the preferred site, complete a Title VI facility siting equity analysis for the proposed project, complete Preliminary Engineering (PE) to include concept site design and facility plans, conduct Stakeholder/Public Engagement, develop a Funding Strategy, and assess the impact of this facility against the implementation plan for the FFTP.
Schedule RTD anticipates this project will take approximately two years to complete from Notice to Proceed (NTP). The draft schedule below illustrates the sequence and overlap of tasks. RTD expects that consultants responding to this RFP will provide a refined and more detailed schedule that ensures completion of the project within the proposed two-year contract period.
Major Components of the Scope of Work
Duration (Months) 0-3 4-6 7-9 10-12 13-15 16-18 19-21 22-24
Notice to Proceed (NTP) * Project Management Alternatives Analysis/Title VI Equity Analysis
NEPA
Stakeholder/Public Involvement Preliminary Engineering Funding Strategy FFTP Reassessment Final Report/Project Closeout * rtd-denver.com 3
Scope of Work The Scope of Work (SOW) for this project includes all requirements to identify a location for a bus operations and maintenance facility with a capacity to serve at least 150 buses. It will include an Alternatives Analysis (AA) prior to initiating an environmental study consistent with the National Environmental Policy Act (NEPA), a preliminary design program for the facility site and buildings, and recommendations for an implementation strategy for the new facility. A key goal for this facility is to support RTD’s objective for its fleet and facilities to achieve carbon neutral operations by 2050, as identified in the FFTP.
RTD has identified the specific tasks of work required in its proposed scope of work and schedule, but proposers may modify the task contents, sequence, and durations to align to their own strategy for completion and best practice experience, to achieve a better project outcome, to streamline the scope of work, or to incorporate critical tasks that the consultants believe are required but have not been identified in this request for proposals
(RFP).
Summary of Project Tasks
Task No. Task Name Description
1 Project Management Maintain overall management and control of the project from start to finish.
2 Alternatives Analysis (AA)/Title VI Equity Analysis
Confirm the Purpose and Need and analyze up to five sites, plus a no-build scenario, for suitability of a new bus operations facility. Conduct a thorough alternatives analysis, including a Title VI Equity Analysis to select a site based on the criteria defined in the Purpose and Need.
4 NEPA Complete the NEPA process, including necessary documentation and public involvement, to ensure environmental compliance.
5 Stakeholder/Public Engagement Conduct engagement with stakeholders and with the public necessary to advance the study.
6 Preliminary Engineering (PE) Concurrent with the NEPA process, create space programming and preliminary design plans for the selected site, sufficient to support the NEPA process and inform future design phases.
7 Funding Strategy Since funding for construction is not yet identified, develop a strategy for acquiring the funding necessary to advance the project through construction.
8 FFTP Reassessment Assess how a new bus operations facility will integrate into RTD’s Facilities and Fleet Transition Plan (FFTP).
Task 1: Project Management The Consultant will provide adequate project oversight that, at a minimum, includes or ensures the following elements:
• Producing a proposed format and outline for the final report deliverable rtd-denver.com 4
• Developing and maintaining a project budget
• Coordinating with RTD staff, other consultants, and stakeholders
• Preparing and submitting progress reports and invoices
• Organizing and facilitating meetings and workshops
• Delivering presentations and briefings
• Managing quality control and assurance
• Resolving issues and risks
Deliverables expected in each phase are identified in bold.
First Thirty (30) Days after NTP In the first thirty (30) days after Notice to Proceed (NTP), the consultant will:
• Prepare a detailed Project Budget by task and a level of effort, measured as a percentage of the project, for each major deliverable. The project budget and monthly invoices will identify hours by task and team member (identifying staff affiliation by firm for prime, non-DBE subconsultant, and DBE consultant). This project shall utilize a time and materials (direct cost) approach for invoicing, but it shall incorporate an earned value management (EVM) reporting approach to measure progress toward the completion of the overall project and each project deliverable for which any portion of the budget has been expended during the progress period. The budget and monthly invoices shall identify the allocation between prime, non-DBE subconsultants, and DBE consultants, expenditures to date on monthly invoices.
• Prepare a detailed Project Schedule for all project tasks and all components of project management. The project schedule should include dates for [1] invoices and progress reports, [2] recurring internal team and project management meetings, [3] submission of draft and final versions of major project deliverables, [4] submission of the draft and final report, and [4] any other major milestones relevant to delivery of the project.
• Provide a complete Organizational Chart for all members of the project team and a Contact List that includes, at a minimum, the project manager, principal, and task leads. The organizational chart may be included in the proposal but shall be modified as project team members are removed or added. The contact list shall be updated as team members are removed or added. Any major changes in the project manager or task leads shall be approved in advance by RTD and include a transition plan that describes how the consultant will maintain continuity in the work plan.
• Review RTD requirements and guidelines for public-facing documents, reports, and presentations, including accessibility and language requirements (e.g. Americans with Disabilities Act, Web Content Accessibility Guidelines 2.1 AA/A level standards and RTD’s Language Access Plan).
• Hold an initial and informal meeting with the RTD Project Manager to review the work activities expected in the first thirty (30) days of the project and discuss any other issues relevant to the project and its work plan.
• Hold a project kick-off meeting with key members of the consultant team and the RTD oversight committee.
First Forty-five (45) Days after NTP In the first forty-five (45) days after Notice to Proceed (NTP), the consultant will:
• Prepare a detailed tentative Engagement Schedule for all public and stakeholder outreach activities, interagency coordination meetings, and RTD internal stakeholder meetings. The schedule should identify all required attendees by general title or position and include a description of the purpose and expected outcomes for each meeting. RTD staff and the consultant will identify the rtd-denver.com 5 names of potential and recommended internal and external stakeholder contacts for each task or component of the work program.
• Prepare project-specific Templates for both internal and public-facing documents, reports, presentations, memoranda, monthly progress reports and invoices, and formal deliverables and reports.
• Develop a Preliminary Outline of the Final Report and its Appendices. RTD envisions that each major task or component of the project will have a deliverable that serves as a standalone appendix in the final report and details the methodology, process, data, results and findings, and recommendations from each major component or task in the report. The body of the final report will be a summary of the study process with a focus on the recommended site, site plan, and design for the proposed facility.
First Sixty (60) Days after NTP In the first sixty (60) days after Notice to Proceed (NTP), the consultant will:
• Prepare a proposed format and outline for the Final Report deliverable
Bi-Weekly or Monthly Recurring Activities The consultant will:
• Establish bi-weekly meetings with the RTD project management team to discuss progress, challenges, and solutions. RTD and the consultant may mutually determine when specific meetings are cancelled or when the frequency or timing is changed based on project needs.
• Prepare monthly invoices and progress reports. Invoices shall present hours, loaded rate, and total expense by staff and subconsultants and direct costs for each invoice period and cumulatively for the project. Each deliverable shall incorporate the percent complete and percent of budget expended per the EVM framework.
• The consultant Project Manager shall schedule a one-on-one meeting with the RTD Project Manager promptly and without delay when any challenge or discrepancy emerges with the scope, schedule, or budget. Challenges or discrepancies may include, but are not limited to, anticipated challenges in meeting the contract scope, any existing or anticipated cost overrun or variance reflected in EVM, any change in key project positions, or any additional effort not included in the scope of work that may be required in response to external or internal stakeholder expectations.
• RTD expects that the consultant may periodically be requested to develop presentations for the RTD Project Manager to deliver to RTD management and RTD Board of Directors. Presentations will adhere to RTD’s approved PowerPoint template, style guide and document accessibility standards. These should be included in the public and stakeholder engagement component on a quarterly basis, and the consultant’s Project Manager should expect to deliver at least two (2) presentations to the RTD Board of Directors during the term of the contract.
Upon Completion of Project Deliverables Upon substantial completion of each task or major component of the project, the consultant will:
• Prepare and submit draft deliverables to RTD for review and comment at least thirty (30) days prior to the task completion date shown in the project schedule. All deliverables that serve as components of the final report will be written in clear and concise language, avoiding unnecessary language and redundancy to the extent practicable.
rtd-denver.com 6
• As technical documents, the deliverables for tasks or major components of the work (appendices to the final report) should be appropriately written for a technical audience, including regulatory agencies that have a role in project or funding approvals.
• The body of the final report should be written for a public and stakeholder audience, avoiding technical language, jargon, and excessive use of industry abbreviations and acronyms to the extent possible.
• RTD expects that the consultant will employ a technical writer or editor to ensure delivery of well-written, high-quality documents for all deliverables from the first draft to the final versions. If the consultant submits a deliverable for RTD review that RTD deems to be of substandard or poor quality, RTD may reject the deliverable and require the consultant to submit a quality improvement plan for approval by the RTD Project Manager. The quality improvement plan will identify the consultant’s guidelines and quality control processes for improving the quality of its work.
• RTD will review all deliverables within fourteen (14) days. RTD may require additional time to review complex or lengthy documents, and the RTD and consultant Project Managers should anticipate additional review time in the initial schedule development. If the RTD Project Manager determines that the deliverable submitted by the consultant is of substandard quality, the RTD Project Manager may return the document to the consultant Project Manager within four (4) days for further internal review and editing. The RTD and consultant Project Managers should meet in person or by phone promptly to discuss the deficiencies in the deliverable and identify corrective actions prior to resubmittal by the consultant. RTD shall complete its review of deliverables within fourteen (14) days and return a document with markups and comments along with a document change log. The consultant will track responses and changes in the change log and complete the final deliverable by the task end date, which will serve as the deadline for the final deliverable. The final deliverable, with change log responses, may be accepted and approved by the RTD Project Manager or, at the discretion of the RTD Project Manager, to one or more RTD staff. Final deliverables for all tasks and major components shall be delivered as a final document ready for inclusion as an appendix to the final report.
• All deliverables that serve as public-facing components of the final report will be compliant with Section 508 of 29 U.S.C § 794d, the Rehabilitation Act of 1973, as amended. RTD expects that the consultant will employ a suitably qualified member of the team to ensure Section 508 compliance and adherence to Web Content Accessibility Guidelines (WCAG) 2.1 AA/A level standards of all final deliverables that form part of the final report document.
Project Documentation All presentations and reports presented to RTD staff, Board of Directors or to the public are required to be compliant with Title II of the ADA, specifically Web Content Accessibility Guidelines. Additionally, documents presented at public meetings may be required to be translated into Spanish or other safe harbor languages or may be to be provided in alternative formats (large print, braille, etc.) required on an as-needed basis and are the responsibility of the consultant team. The need for translation services will be determined based on several factors, including, but not limited to, the demographics of the location of the meeting and whether translation services were requested by the public prior to the meeting. The need for alternative formats will be determined through public requests to the consultant team, prior to the meeting.
RTD Inputs:
• RTD requirements and guidelines for public-facing documents, reports, and presentations.
• RTD Public Participation Plan (PPP), 2025-2028 https://cdn.rtd-denver.com/image/upload/v1750258321/Public_Participation_Plan_az3ib9.pdf https://cdn.rtd-denver.com/image/upload/v1750258321/Public_Participation_Plan_az3ib9.pdf https://cdn.rtd-denver.com/image/upload/v1750258321/Public_Participation_Plan_az3ib9.pdf rtd-denver.com 7
• RTD Language Access Plan (LAP), 2025-2028: https://cdn.rtd-denver.com/image/upload/v1752163166/2025-2028_Language_Access_Plan_jonb2a.pdf.
• RTD Disability Community Engagement Plan (Appendix B)
• RTD requirement for Section 508 compliance and Web Content Accessibility Guidelines (WCAG) 2.1
AA/A level standard: https://www.w3.org/TR/WCAG21/.
Deliverables:
• Project Budget (NTP + 30 days)
• Project Schedule: Project Management Activities (NTP + 30 days)
• Project Organizational Chart and Contact List (NTP + 30 days)
• Project Schedule: Public and Stakeholder Activities (NTP + 45 days)
• Project Templates (NTP + 45 days)
• Draft Final Report and Appendix Outline (Project Deliverable Outline) (NTP + 45 days)
Task 2: Alternatives Analysis RTD has already conducted preliminary work to identify potential sites for a new bus facility and has identified RTD-owned properties and properties owned by other public entities as potential options (see Facility Siting Report in Appendix A). Additional sites may be included based on input from the project team and stakeholders.
The selected consultant will need to conduct an alternatives analysis on up to five sites, including the sites in the list below, plus a no-build alternative. Additional information on the RTD-owned sites can be found in the FFTP Facility Siting Analysis.
Sites to be assessed:
• Former 70th/Broadway Park-n-Ride (RTD-owned)
• Quail Yards (RTD-owned)
• Wadsworth/Hampden Park-n-Ride (RTD-owned)
• Up to two additional sites based on input from the project team and stakeholders, including sites identified in the publicly owned property list from the FFTP Facility Siting Analysis.
Each site should be evaluated based on the draft evaluation criteria identified in the Purpose and Need, and any additional criteria determined to be necessary. The Consultant is expected to conduct site visits to gather information sufficient to complete this analysis and develop a scoring matrix to compare and rank alternatives.
RTD has developed a draft Purpose and Need for the development of a bus operations facility to support the environmental planning work that will be conducted as part of this project. It will be refined with input from the Federal Transit Administration (FTA), lead agency, and stakeholders, as part of the scope of this project. This study is the next step towards advancing a new bus facility to design and construction.
One major goal for the proposed bus maintenance facility is to support RTD’s projected 2050 future fleet as envisioned in the 2024 RTD FFTP. The FFTP has been developed to determine pathways to achieving net zero emissions for RTD’s facilities and fleet by 2050. The transition to alternative fuels/technologies will improve air quality in the RTD service area; make the RTD system more environmentally sustainable; and improve the overall experience for RTD’s riders and the region.
Draft Purpose and Need RTD has developed the draft purpose and need statement shown below, and RTD expects the consultant to further refine it through the alternatives analysis and NEPA process.
Purpose https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcdn.rtd-denver.com%2Fimage%2Fupload%2Fv1752163166%2F2025-2028_Language_Access_Plan_jonb2a.pdf&data=05%7C02%7CChris.Quinn%40RTD-Denver.com%7C16d6b8336d6d4d7560bd08de1642c488%7C051820892b8a4c82864baa265b61fa57%7C0%7C0%7C638972673188473523%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=XyhnB8W3PIj5ARwq1VApzJmy0nD8rF1J7uxDsGFi%2FoU%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fcdn.rtd-denver.com%2Fimage%2Fupload%2Fv1752163166%2F2025-2028_Language_Access_Plan_jonb2a.pdf&data=05%7C02%7CChris.Quinn%40RTD-Denver.com%7C16d6b8336d6d4d7560bd08de1642c488%7C051820892b8a4c82864baa265b61fa57%7C0%7C0%7C638972673188473523%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=XyhnB8W3PIj5ARwq1VApzJmy0nD8rF1J7uxDsGFi%2FoU%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.w3.org%2FTR%2FWCAG21%2F&data=05%7C02%7CChris.Quinn%40RTD-Denver.com%7Cbe3c67e75bba46773ac108de4e1a441a%7C051820892b8a4c82864baa265b61fa57%7C0%7C0%7C639034072212067243%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=iv7c3I9bqK53f8%2FBf%2ByAJdkIPSDC9hWfRSrFj6eomT0%3D&reserved=0 rtd-denver.com 8
The purpose of the proposed bus maintenance facility is to support RTD’s projected 2050 future fleet as envisioned in the 2024 RTD FFTP. The FFTP has been developed to determine pathways to achieving net zero emissions for RTD’s facilities and fleet by 2050. The transition to alternative fuels/technologies will improve air quality in the RTD service area; make the RTD system more environmentally sustainable; and improve the overall experience for RTD’s riders and the region.
Need
• Need to transition to a zero emission fleet by 2050 to improve air quality and meet greenhouse gas (GHG) reduction goals prescribed by State of Colorado legislation, established in RTD Board policy, and consistent with the GHG Pollution Roadmap 2.0.
Evaluation Criteria: Will the site accommodate a facility with zero emission technology(s)?
• Need to provide facilities and infrastructure for maintenance of a zero emission fleet (minimum of 150 buses) Evaluation Criteria: Is the site size sufficient to accommodate a zero emission fleet with 150+ buses?
• Need to ensure that site selected would accommodate a facility that provides flexibility to serve vehicles with newer technologies, such as battery electric (BEB) or hydrogen buses Evaluation Criteria: Will the site support a facility that can maintain BEB, hydrogen buses, or potentially both?
• Need to promote sustainable practices for RTD’s fleet and facilities
Evaluation Criteria: Will the site support zero emission technologies and permit sustainable storage of fuel; collection and storage of maintenance materials such as solvents; accommodate charging equipment; be of size and configuration to be constructed to meet building and fire code requirements and other sustainability and safety needs for the facility?
• Need to site the facility, and provide mitigations as needed, to address potential environmental impacts to environmental resources as addressed thorough evaluation consistent with the National Environmental Policy Act (NEPA) Evaluation Criteria: Are there environmental impacts and if so, what are the relative magnitude of the impacts, and can they be mitigated?
• Need to site the facility in a manner that meets facility siting requirements according to Title VI of the
Civil Rights Act Evaluation Criteria: Can Title VI evaluation and outreach requirements be met and what is the impact on any surrounding underserved communities?
• Need to provide a site of sufficient size to support fleet and infrastructure
Evaluation Criteria: Will the site size support fleet and infrastructure needs?
• Need to centrally locate facility to minimize deadhead distance Evaluation Criteria: Is the site located where there would be, ideally, a minimum of 3,000 weekly route ends within a 10-mile radius of the facility
• Need to meet local jurisdictional requirements and plans
Evaluation Criteria: Is the current zoning for the site consistent with the proposed land use and, if not, is the proposed land use consistent with the comprehensive plan and surrounding community?
rtd-denver.com 9
Title VI A bus operations facility falls under the provisions in Chapter III-13 of FTA Circular 4702.1B: Title VI Requirements and Guidelines for Federal Transit Administration Recipients, which requires RTD to conduct a Title VI facility siting equity analysis prior to the selection of the preferred site. This analysis ensures the location is selected without regard to race, color, or national origin and RTD upholds its nondiscrimination requirements as set forth by federal civil rights regulations.
Per the guidance in the FTA Circular, this analysis must:
• Include outreach to meaningfully engage persons potentially impacted by the siting of the facility, including limited English proficient populations;
• Compare the potential impacts of all siting alternatives;
• Determine if cumulative adverse impacts might result due to the presence of other facilities with similar impacts in the area; and
• Occur during the planning stages and before the selection of the preferred site.
If the analysis identifies any disparate impacts or cumulative adverse effects, RTD must implement the least discriminatory alternative as well as document efforts to mitigate those impacts. The Consultant shall complete the Title VI facility siting equity analysis to include in the Alternatives Analysis Final Report.
RTD has explored rail maintenance facility locations and has completed a Title VI facility siting equity analysis in the past. Copies of the previous studies will be made available to the consultant. RTD’s Transit Equity Office will provide support in the development of the final report.
The culmination of this analysis will be a report documenting the equity analysis process, summarizing public engagement and input, evaluating all alternatives and providing a clear and equitable justification for the preferred site.
RTD Inputs:
• Prior rail maintenance facility Title VI facility siting equity analyses (for comparative reference only).
• RTD Language Access Plan (LAP), 2025.
• RTD requirement for Section 508 compliance and Web Content Accessibility Guidelines (WCAG) 2.1
AA/A level standards.
Deliverables:
• Alternatives Analysis Final Report (Appendix A of Final Report)
• Title VI Facility Siting Equity Analysis Report (Appendix B of Final Report)
Task 3: NEPA An Alternatives Analysis (AA) and National Environmental Policy Act (NEPA) clearance are required as it is anticipated that federal funding will be used to help fund design and construction of the new facility. Following completion of the AA, the NEPA class of action will be determined and the environmental evaluation will be made and documented as described below.
NEPA Class of Action After the AA is complete and a site has been selected, RTD will coordinate with FTA, which will determine the NEPA class of action. The Consultant will support RTD by reviewing readily available data sources for environmental resources within the determined project study area, including preparing relevant maps or figures in support of RTD’s coordination efforts with FTA.
rtd-denver.com 10
NEPA Documentation The Consultant will prepare the NEPA document for the proposed bus facility that complies with the FTA’s NEPA regulations and guidance.The scope assumes that the FTA will determine that the project qualifies as a documented categorical exclusion (DCE), the criteria for which are described in 23 CFR §771.118(d). The scope assumes a DCE, as that level of documentation would require a higher level of effort to complete compared to a categorical exclusion (CE) described in 23 CFR §771.118(c).
The DCE will document the existing conditions in the study area and evaluate the project’s potential impacts on the natural and human environment. The Consultant will use readily available, and the most recently published, databases and aerial imagery to screen the project’s study area for resources. Based on Google aerial imagery of the site and a review of federal and state databases, the following environmental resource areas may require fieldwork or additional coordination time to support the NEPA documentation.
The Consultant shall complete the FTA Region 8 CE Worksheet to document impacts to the environmental resources listed in the CE Worksheet. It is understood that not all of the resources will be found in study area.
Thus, for those not present, statement/documentation of absence will be the only requirement.
The Consultant should develop appropriate mitigation measures to address any identified concerns. Impacts and mitigations will be documented on the CE Worksheet or in additional reporting dependent upon the FTA determined class of action.
Documentation and Report Preparation This scope assumes that a documented CE will be the class of action required by FTA. As such, deliverables for this scope will include completion of the FTA CE Worksheet and supporting technical reports. Required reports will include, at a minimum, Land Use, Cultural Resources, Air Quality, Environmental Justice, and Traffic, with the potential for additional reports dependent upon site specific conditions. It is anticipated that one to two review cycles with RTD and a final review and revision cycle with FTA will be necessary to respond to questions and/or requests for additional information.
Potential Additional Scope: If the class of action is elevated to an Environmental Assessment (EA), this scope will be expanded to include an Environmental Assessment Report with potential associated tasks to include additional community outreach and documentation, and/or other efforts as required by FTA. The Consultant should include this task in their proposal with the understanding that this task will only be required if the class of action is elevated to an EA.
RTD Inputs:
• RTD Title VI Program Update (2025-2028) https://cdn.rtd-denver.com/image/upload/v1750273281/2025-2028_Title_VI_Program_-_Final_o8yd6e.pdf
Deliverables:
• Completed FTA CE Worksheet
• Land Use Technical Report
• Cultural Resources Technical Report
• Air Quality Technical Report
• Environmental Justice Technical Report
• Traffic Technical Report
• Other reports dependent on site specific conditions.
• Potential: Environmental Assessment Report rtd-denver.com 11
Task 4: Stakeholder and Public Engagement Public and stakeholder outreach are expected to occur throughout the study process with a focus on major milestones and decision-making points as well as feedback on alternatives and mitigations. The Consultant shall be responsible for all administrative tasks associated with community outreach including scheduling meetings, preparing meeting materials, developing facilitation guides, and meeting summaries.
There shall also be a focus on continuous communication with local jurisdictions and other relevant stakeholders throughout the project. The forms of communication with stakeholders, such as establishing advisory committees, establishing a project website, providing regular email updates, or other such techniques, shall be identified in the proposal by the Consultant and should include proven techniques that Consultant team has had success with on previous projects.
The Consultant shall propose a robust community and stakeholder engagement plan as part of the response to this RFP. Expectations for that plan include:
• The RTD General Manager and CEO and the Board will receive periodic updates on the status of the project and have input in the alternatives analysis on the selected alternative. RTD staff will take the lead on Board engagement. The Consultant will support RTD staff and help with the development of materials for the Board such as PowerPoint presentations and Board briefing documents.
• A technical working group (TWG), primarily made up of key RTD staff related to bus technology and facilities, will be established. The TWG will be managed by RTD project management staff and the consultant team will provide support to RTD staff including meeting notes, presentation materials, and other items as needed.
• Community and stakeholder engagement on the project should be responsive to Title VI and engagement of unrepresented populations. The Consultant is encouraged to propose methods for targeted engagement of underrepresented populations including: using community groups and non-profits with connections to the communities impacted by the project to facilitate meetings, administer surveys, and attend neighborhood meetings; translate materials and provide translation services at meetings in Spanish and other safe harbor languages that are applicable to the impacted community.
• Community and stakeholder engagement should also follow NEPA requirements for meaningful engagement with RTD customers and the general public and should go beyond conducting public meetings/hearings on the project. The Consultant is encouraged to propose innovative solutions and apply industry best practices. Engagement activities should be focused on project milestones/decision points.
It is anticipated that the TWG would provide input on the results of the evaluation and potential and that the findings of the NEPA process, impacts and mitigations, would be finalized by the TWG and later presented to the Public. The Consultant shall propose the number and types of meetings based on their understanding of this project and its level of complexity.
RTD Inputs:
• Document and PowerPoint templates
Deliverables:
• Community and Stakeholder Engagement Plan
• Support materials for Board and TWG meetings
• Other materials as identified in Community and Stakeholder Engagement Plan rtd-denver.com 12
Task 5: Preliminary Engineering The Consultant will work with RTD staff to develop conceptual design (15%), schematic design, and space programming for the proposed facility. Detailed building specifications will not be required.
Prior to initiating the conceptual design process, the consultant shall engage with RTD stakeholders (staff from Bus Operations, Capital Programs, Planning, and Safety and Environmental Compliance who, along with RTD’s Bus Facility Design Criteria, will inform the development of the facility program) to identify core components that may be included in facility design and issues that may need to be addressed during the design process. The initial product of this task will be a Draft Facility Definition and Scope memorandum defining options for the facility to verify which maintenance functions will be included and performed on-site versus those that must be performed off-site (e.g. at District Shops), the inclusion or exclusion of storage and maintenance of buses by fuel type (diesel, diesel-electric hybrid, battery electric, hydrogen fuel cell, etc.), the minimum total number of buses to be accommodated on-site, and any special provisions based on the expected fleet composition (e.g.
possible inclusion of a microgrid to support the conversion to battery-electric buses). Based on responses from RTD stakeholders, the Consultant shall refine the Draft Facility Definition and Scope to confirm RTD stakeholder’s expectations for the facility.
The Facility Definition and Scope memorandum shall be a working document that evolves throughout the conceptual design task in support of a Draft Facility Programming Report that reflects RTD’s internal consensus on the expectations for this facility. In its first refinement, after the core components have been defined, the Consultant shall incorporate fleet and technology considerations that affect facility design and identify current best practices and case studies in facility design for the size and type of facility desired. The refined memorandum shall also address issues associated with evolving technology, as applicable (e.g. electrical capacity required at the facility, safety considerations in design, microgrid requirements).
The Consultant shall solicit RTD stakeholder feedback on the refined Facility Definition and Scope and develop initial high-level design alternatives in preparation for a design charette. The design charette with RTD stakeholders will assist the Consultant in developing, analyzing, and refining conceptual alternatives and to establish consensus for a facility design approach and concept.
The Consultant shall develop preliminary architectural and engineering drawings that provide a visual representation of the proposed facility, including floor plans, elevations, and building sections for review and comment by RTD stakeholders. Concept facility design shall consider sustainable design principles, energy efficiency, and the potential need for the facility to support an alternative technology in the future (battery-electric and/or hydrogen).
Preliminary facility and site engineering will be conducted concurrently with the NEPA process, and the final products of this task shall be a Facility Programming Report that consolidates RTD stakeholder consensus on the Facility Definition and Scope with the conceptual design schematics.
RTD Inputs:
• Bus Facility Design Criteria: https://cdn.rtd-denver.com/image/upload/v1694642682/RTD%20Web/Doing%20Business/Construction%20Engineerin g/Bus-Infrastructure-Design-Guidelines-and-Criteria-2016_cwyq9j.pdf
Deliverables
• Facility Programming Report (including “report-level” conceptual design)
• Facility Design Files (CADD) https://cdn.rtd-denver.com/image/upload/v1694642682/RTD%20Web/Doing%20Business/Construction%20Engineering/Bus-Infrastructure-Design-Guidelines-and-Criteria-2016_cwyq9j.pdf https://cdn.rtd-denver.com/image/upload/v1694642682/RTD%20Web/Doing%20Business/Construction%20Engineering/Bus-Infrastructure-Design-Guidelines-and-Criteria-2016_cwyq9j.pdf https://cdn.rtd-denver.com/image/upload/v1694642682/RTD%20Web/Doing%20Business/Construction%20Engineering/Bus-Infrastructure-Design-Guidelines-and-Criteria-2016_cwyq9j.pdf rtd-denver.com 13
Task 6: Funding Strategy RTD has not identified funding to advance this project beyond the planning phase, and RTD’s implementation timeline for this project will likely take several years. RTD has identified two important components required as this project progresses in future phases: (1) an estimated cost based on categories that both provide for periodic updates and allow for components or implementation phases to be broken out for purposes of specific grant applications and (2) a strategy to obtain federal, state, and/or private funding for this project.
Project Costs RTD proposes the following categories as potential cost elements; however, the Consultant shall refine the categories and cite a methodology and sources for periodic or annual building industry updates to the recommended cost categories.
• Foundations and structures
• Building envelope (shell)
• Interior Finishes
• HVAC
• Electrical/communications/security/lighting
• Plumbing
• Fixture, Furniture and Equipment (FFE)
• Specialized equipment (lifts, pits, etc.)
• Demolition, Civil sitework and drainage
• Utilities
• Design Costs
• Taxes, permits, fees, etc.
• Contingency
• Taxes
Funding Strategies The Consultant shall develop an inventory with brief descriptions of potential funding relevant to this project.
The inventory should not reflect a universe of options; rather, it should reflect funding sources that are at least reasonably plausible as a funding option. Funding options may consider both federal and state grants, as well as private-sector funding (e.g. long-term lease of a privately built facility on RTD property).
Task 7: FFTP Reassessment RTD completed its FFTP in 2024, a plan that outlines how RTD will transition its facilities to meet RTD’s 2050 zero emission goal. The Consultant should consider how the new facility will support RTD’s facility transition under a revised timeline beginning in 2032 with completion by 2050, including an assessment of the number and type of vehicles that will be assigned to the facility and the overall change to RTD’s carbon footprint as a result of facility operation.
rtd-denver.com 14
Appendix The following appendix materials are included for contractor review and are incorporated into this Statement of Work:
Appendix A: Facility Siting Analysis (component of the Facility and Fleet Transition Plan)
Appendix B: Disability Community Engagement Plan
File details come from the government source that posted it. Updated .