This is a Facilities and Fleet Transition Plan (FFTP) document prepared for the Regional Transportation District (RTD) of Colorado, specifically the Facility Siting Analysis component completed in December 2024. The document outlines RTD's strategic initiative to transition its facilities and fleet to low- and zero-emission technologies by 2050. The analysis identifies potential locations for a new District-owned, fixed-route bus operations and maintenance facility through a two-phase screening process of RTD-owned and publicly-owned parcels across the RTD service area encompassing Adams, Arapahoe, Broomfield, Boulder, Denver, Douglas, and Jefferson counties. The project involves evaluation of parcels based on multiple criteria including location, zoning compatibility, deadhead distance impacts, utility availability, and environmental considerations. RTD's near-term strategy (2025-2035) includes replacing diesel buses with diesel-hybrid electric buses (dHEBs), increasing battery-electric bus (BEB) fleet capacity, evaluating fuel cell electric buses (FCEBs) as a pilot program, and planning for property acquisition or development for future bus facilities.
The Facility Siting Analysis identifies three final candidate locations among RTD-owned parcels: Parcel 2 (70th Ave/Broadway Parking Lot, 16.3 acres), Parcel 4 (Quail Yard, 18.2 acres in Lakewood), and Parcels 6 & 7 (Wadsworth & Hampden Park-n-Ride and adjacent vacant parcel, combined 21.6 acres). Three additional RTD-owned parcels were eliminated due to existing operational uses, insufficient size, or planned facility relocations. The analysis also identified 46 publicly-owned vacant parcels across the service area as alternative candidates should RTD-owned sites prove infeasible. Subsequent phases require further analysis including cost estimation, environmental review (including assessment of floodplains, wetlands, hazardous materials, and traffic impacts), utility infrastructure compatibility for BEB and FCEB operations, adjacent use compatibility assessment, and comprehensive community outreach. The related contract opportunity (GovTribe ID: 6af71130e3e642e58002e5b8) seeks consulting services for alternatives analysis and environmental planning to support development of the new facility, with a 10 percent small business enterprise (SBE) goal.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FACILITIES AND FLEET TRANSITION PLAN 1
Facilities Plan – Facility Siting Analysis Faci l i t ies and Fleet Transit ion Plan
December 2024 | FINAL
FACILITIES AND FLEET TRANSITION PLAN i
Contents
1. Executive Summary
1.1 Project Overview
1.2 Analysis Purpose
1.3 Facility Siting Analysis Summary
1.4 Next Steps
2. Introduction
2.1 Project Overview
2.2 Project Background
2.2.1 Phase 1 – Fuels/Technologies Screening
2.2.2 Phase 2 – Facilities and Fleet Transition Plan
2.3 Report Background, Purpose, and Structure
2.3.1 Background
2.3.2 Purpose and Structure
3. Analysis Approach
3.1 Overview
3.2 Screening Criteria
3.3 RTD-Owned Parcel Analysis
3.4 Other Publicly-Owned Parcel Analysis
4. RTD-Owned Parcel Analysis
4.1 Initial Shortlist Parcels Eliminated from Final List
4.1.1 Parcel 1: Existing Transdev Access-A-Ride Facility, 7500 E 41st Ave, Denver
4.1.2 Parcel 3: Existing RTD North Metro Commuter Rail MOW Facility
4.1.3 Parcel 5: Former Ward Rd & I-70 Park-n-Ride
4.2 Final RTD-Owned Parcel Shortlist
4.2.1 Parcel 2: 70th Ave/Broadway Parking Lot
4.2.2 Parcel 4: Vacant (Quail Yard, Quail St south of W Colfax Ave)
4.2.3 Parcel 6 & 7: Existing Wadsworth & Hampden Park-n-Ride and Adjacent Vacant Parcel
FACILITIES AND FLEET TRANSITION PLAN i i
5. Other Publicly-Owned Parcel Analysis
6. Conclusion
6.1 Facility Siting Summary
6.2 Next Steps
FACILITIES AND FLEET TRANSITION PLAN i i i
List of Figures Figure 1: FFTP Project Workflow
Figure 2: Phase 2 Workflow
Figure 3: Analysis Approach Flowchart
Figure 4: Publicly Owned Vacant County Parcels
Figure 5: Parcel 1 (Existing Transdev Access-A-Ride Facility, 7500 E 41st Ave, Denver)
Figure 6: Parcel 3 (Existing RTD North Metro Commuter Rail MOW Facility)
Figure 7: Parcel 5 (Former Ward Rd & I-70 Park-n-Ride)
Figure 8: Parcel 2 (70th Ave/Broadway Parking Lot)
Figure 9: Parcel 4 (Quail Yard, Quail St South of W Colfax Ave)
Figure 10: Parcels 6 and 7
Figure 11: Other Publicly-Owned Parcel Screening Shortlist
FACILITIES AND FLEET TRANSITION PLAN iv
List of Tables Table 1: Parcel Evaluation Criteria
Table 2: Total Weekly Vehicle Block Counts (by Route Ends within Driveshed)
Table 3: Initial Phase 2 Shortlist of RTD-Owned Parcels with Route Ends Analysis Results
Table 4: Parcel 1 Details (Existing Transdev Access-A-Ride Facility, 7500 E 41st Ave, Denver)
Table 5: Parcel 3 Details (Existing RTD North Metro Commuter Rail MOW Facility)
Table 6: Parcel 5 Details (Former Ward Rd & I-70 Park-n-Ride)
Table 7: Parcel 2 Details (70th Ave/Broadway Parking Lot)
Table 8: Parcel 4 Details (Quail Yard, Quail St South of W Colfax Ave)
Table 9: Parcel 6 Details (Existing Wadsworth & Hampden Park-n-Ride)
Table 10: Parcel 7 Details (Adjacent Vacant Parcel)
Table 11: Shortlist of Other Public-Owned Parcels
FACILITIES AND FLEET TRANSITION PLAN v
Acronyms BEB Battery-Electric Bus
Blueprint Facilities Transition Blueprint
BRT Bus Rapid Transit
CDOT Colorado Department of Transportation
CRMF Commuter Rail Maintenance Facility
CRV Commuter Rail Vehicles dHEB Diesel-Hybrid Electric Bus
DRCOG Denver Regional Council of Governments
EIS Environmental Impact Statement
FCEB Fuel Cell Electric Bus
FEMA Federal Emergency Management Agency
FFTP RTD Low and No Emission Facilities and Fleet Transition Plan
FLU Future Land Use
FTA Federal Transit Administration
GIS Geographic Information Systems
MOW Maintenance of Way
OEM Original Equipment Manufacturer
PNR Park-n-Ride
RFI Request for Information
RTD Regional Transportation District
SOP System Optimization Plan
ZE Zero Emission
ZEB Zero Emission Bus
ZEV Zero Emission Vehicle
EXECUTIVE SUMMARY
1. EXECUTIVE SUMMARY
1.1 PROJECT OVERVIEW
The Regional Transportation District (RTD) is currently planning the transition of its facilities and fleet to low- and/or no-emission (also referred to as zero emission [ZE]) fuels/technologies. This effort is pursuant to the RTD Board’s authorization to evaluate pathways to achieving net ZE for RTD’s facilities and fleet by 2050. RTD’s transition to alternative fuels/technologies will improve air quality in the RTD service area, make the RTD system more environmentally sustainable, and improve the overall experience for RTD’s riders and the region.
To achieve the 2050 goal, RTD is developing the Facilities and Fleet Transition Plan (FFTP), a framework and technical vision for RTD to meet its transition goals. The FFTP consists of two corresponding plans.
The first, the Facilities Transition Blueprint (Blueprint), is a comprehensive document that details the strategy and actions that RTD should take to meet the 2050 goal. The second, the ZE Fleet Transition Plan (Federal Transit Administration [FTA] Plan), is an FTA-compliant plan that enables RTD to pursue certain federal bus and infrastructure funding opportunities.1
The FFTP is being developed in two distinct phases (Figure 1). The first phase, the Fuels/Technologies Screening, concluded in August 2024 and consisted of an initial screening of five alternative fuels/technologies2 to determine their respective impacts on RTD’s service and fleet, facilities, workforce and training, budget and finances, and emissions. The analysis, along with input from RTD staff, resulted in the selection of preferred fuels/technologies to advance into Phase 2. In Phase 2 (current phase), the project team will develop technical plans for the preferred fuels/technologies. These plans (Facilities Plan, Workforce and Training Plan, Fleet Procurement Plan, Lifecycle Costs and Funding Plan) will culminate in the aforementioned comprehensive Facilities Transition Blueprint and FTA Plan, positioning RTD to begin the process of meeting its 2050 goal.
1 https://www.transit.dot.gov/funding/grants/zero-emission-fleet-transition-plan 2 Renewable diesel, diesel-hybrid, battery-electric, compressed natural gas (CNG), and hydrogen
FACILITIES AND FLEET TRANSITION PLAN 2
Figure 1: FFTP Project Workflow
Source: WSP
Based on Phase 1 findings, RTD has determined that the transition strategy be two-phased, segmented by near-term (2025–2035) objectives and long-term (2036–2050) objectives. This approach provides RTD with the flexibility to take immediate cost-effective emission-reduction strategies in the near term, while also allowing RTD to take advantage of improved pricing, availability, and technological capabilities as alternative fuels/technologies continue to mature in the long term.
Recommendations for the near- and long-term strategies include:
Near-Term Strategy (2025–2035):
• Update the FFTP annually to capture any changes that may impact RTD’s transition timeline, including market and/or policy changes, financial adjustments, and technological improvements.
• Replace existing diesel buses with diesel-hybrids (dHEBs) and integrate the use of renewable diesel, if feasible, when available.
• Increase the battery-electric bus (BEB) fleet to the extent possible based on technological advancements, as well as infrastructure and service requirements.
• Consider and evaluate the feasibility of operating fuel cell electric buses (FCEB) as a pilot program.
• Plan for the potential acquisition or development of properties for future bus facilities.
FACILITIES AND FLEET TRANSITION PLAN 3
• Implement facility improvements that facilitate emission reduction, such as energy efficiency and state of good repair improvements.
• Incorporate language into new fixed route contracts to accommodate technological changes to the fixed route revenue fleet.
Long-Term Strategy (2036–2050):
• Continue to update the FFTP annually to reflect any fuel/technology and market updates.
• Replace dHEBs with BEBs and/or FCEBs if the respective fuels/technologies have matured to an appropriate degree.
• If both technologies fail to mature at the expected rate, consider increasing the dHEB fleet.
1.2 ANALYSIS PURPOSE
As RTD plans for the transition to alternative fuels/technologies, there are opportunities to evaluate and optimize other aspects of its service and operations to better prepare for the future. Given that RTD does not own four of the seven bus operating facilities, meeting the 2050 net-zero emission goal depends on the other contracted entities’ ability and willingness to adhere to and adopt RTD’s vision.
Since this poses a potential risk to meeting the goal, it is essential that RTD evaluate the possibility of building new bus facilities that they would own and operate.
The purpose of this Phase 2 analysis is to further refine and evaluate parcels using additional criteria.
The result is a “shortlist” of properties that RTD can further investigate in the near future. These properties are selected with consideration of RTD-vetted criteria, including operating efficiency (deadhead distance), environmental justice and Title VI impacts, utility availability, and road access. It should be noted that the properties identified in this analysis are based on the existing land use and zoning and not properties that could be redeveloped by going through a variance process.
1.3 FACILITY SITING ANALYSIS SUMMARY
The Facility Siting Analysis was driven by RTD’s desire to begin the process of identifying a suitable location for a District-owned, fixed-route bus operation and maintenance facility, or division. This analysis builds on the Phase 1 Facility Siting Analysis, with further discussion of the RTD-owned parcels and identification of a three-site shortlist for advancing in the environmental review process. Additionally, this report presents the methodology and results for an initial, District-wide screening of other vacant, publicly-owned parcels not owned by RTD. This includes a screening for size, appropriate shape (e.g., not a slender, right-of-way parcel), and zoning permissibility. Identification and selection of a final site for a new facility will be contingent upon further analysis of the short-listed parcels, including cost estimation, environmental review, and site utility infrastructure and needs.
FACILITIES AND FLEET TRANSITION PLAN 4
1.4 NEXT STEPS
As RTD prepares to move into the next phase of the site selection and environmental review process for a fixed-route bus facility, further analysis will need to be undertaken to ensure the preferred candidate locations among the RTD-owned parcels fully meet all critical criteria and align with needs and objectives. This includes ensuring the site is appropriately proximal to the routes that will be assigned to the future facility (in terms of minimizing deadhead), the site’s actual buildable acreage aligns with the requirements of the desired facility size, and that utility and other infrastructure at the site is compatible with the future BEB and/or FCEB fleet needs. Additionally, it will also be essential to further assess adjacent uses to the preferred location(s) and ensure compatibility. Community outreach and engagement is recommended during site selection to mitigate pushback or concerns from neighboring residents or businesses and establish community buy-in for the project.
Development of a new facility on land already owned by RTD is preferrable to acquiring new land through purchase from another governmental entity or through a swap with them. However, it is important to consider parcels outside the current RTD portfolio should the need arise. As RTD continues to analyze the three short-listed RTD-owned parcels for future environmental review, these sites should be compared to the top candidates from the publicly-owned parcels shortlist to determine if any on the latter list carry benefits that outweigh their added cost in acquisition or any jurisdictional challenges and warrant further review.
INTRODUCTION
FACILITIES AND FLEET TRANSITION PLAN 5
2. INTRODUCTION
2.1 PROJECT OVERVIEW
The Regional Transportation District (RTD) is currently planning the transition of its facilities and fleet to low- and/or no-emission (also referred to as zero emission [ZE]) fuels/technologies. This effort is pursuant to the RTD Board’s authorization to evaluate pathways to achieving net ZE for RTD’s facilities and fleet by 2050. RTD’s transition to alternative fuels/technologies will improve air quality in the RTD service area, make the RTD system more environmentally sustainable, and improve the overall experience for RTD’s riders and the region.
To achieve the 2050 goal, RTD is developing the Facilities and Fleet Transition Plan (FFTP), a framework and technical vision for RTD to meet its transition goals. The FFTP consists of two corresponding plans.
The first, the Facilities Transition Blueprint (Blueprint), is a comprehensive document that details the strategy and actions that RTD should take to meet the 2050 goal. The second, the ZE Fleet Transition Plan (Federal Transit Administration [FTA] Plan), is an FTA-compliant plan that enables RTD to pursue certain federal bus and infrastructure funding opportunities.3
2.2 PROJECT BACKGROUND
The FFTP is being developed in two distinct phases. The first phase, the Fuels/Technologies Screening, concluded in August 2024 and consisted of an initial screening of five alternative fuels/technologies4 to determine their respective impacts on RTD’s service and fleet, facilities, workforce and training, budget and finances, and emissions. The analysis, along with input from RTD staff, resulted in the selection of preferred fuels/technologies to advance into Phase 2. In Phase 2 (current phase), the project team will develop technical plans for the preferred fuels/technologies. These plans (Facilities Plan, Workforce and Training Plan, Fleet Procurement Plan, Lifecycle Costs and Funding Plan) will culminate in the aforementioned comprehensive Facilities Transition Blueprint and FTA Plan, positioning RTD to begin the process of meeting its 2050 goal. The following subsections provide background on each phase of the FFTP project.
2.2.1 Phase 1 – Fuels/Technologies Screening
During Phase 1 (September 2023–August 2024), the project team conducted analyses and developed screening reports to provide RTD with an understanding of each alternative fuel/technology’s impact on
3 https://www.transit.dot.gov/funding/grants/zero-emission-fleet-transition-plan 4 Renewable diesel, diesel-hybrid, battery-electric, CNG, and hydrogen
FACILITIES AND FLEET TRANSITION PLAN 6
various elements of RTD’s operation and the effectiveness of meeting the 2050 goal. Before developing each screening report, RTD staff and the project team collaborated during virtual workshops to align on the data inputs and approach and to form a common understanding of the general findings of each analysis.
At the conclusion of Phase 1, an in-person Fuel/Technology Screening Workshop was held to summarize the Phase 1 findings and to provide staff with a forum in which to ask questions and offer comments to inform the recommendation of the preferred or combination of preferred fuels/technologies. While each alternative fuel/technology has its advantages and disadvantages, based on findings from the screening reports and input from RTD staff, the agency’s transition strategy will be two-phased, segmented by near-term (2025–2035) objectives and long-term (2036–2050) objectives. This approach provides RTD with the flexibility to take immediate cost-effective emission-reduction strategies in the near term, while also allowing RTD to take advantage of improved pricing, availability, and technological capabilities as alternative fuels/technologies continue to mature in the long term.
Recommendations for the near- and long-term strategies include:
Near-Term Strategy (2025–2035):
• Update the FFTP annually to capture any changes that may impact RTD’s transition timeline, including market and/or policy changes, financial adjustments, and technological improvements.
• Replace existing diesel buses with diesel-hybrids (dHEBs) and integrate the use of renewable diesel, if feasible, when available.
• Increase the battery-electric bus (BEB) fleet to the extent possible based on technological advancements as well as infrastructure and service requirements.
• Consider and evaluate the feasibility of operating fuel cell electric buses (FCEB) as a pilot program.
• Plan for the potential acquisition or development of properties for future bus facilities.
• Implement facility improvements that facilitate emission reduction, such as energy efficiency and state of good repair improvements.
• Incorporate language into new fixed route contracts to accommodate technological changes to the fixed route revenue fleet.
Long-Term Strategy (2036–2050):
• Continue to update the FFTP annually to reflect any fuel/technology and market updates.
• Replace dHEBs with BEBs and/or FCEBs if the respective fuels/technologies have matured to an appropriate degree.
• If both technologies fail to mature at the expected rate, consider increasing the dHEB fleet.
These strategies will be the focus of plans in Phase 2. Phase 1 of the FFTP is summarized in the Fuels/Technologies Screening Report.
FACILITIES AND FLEET TRANSITION PLAN 7
2.2.2 Phase 2 – Facilities and Fleet Transition Plan
In Phase 2 (current phase), the project team will develop a Facilities Plan, Fleet Procurement Plan, Workforce and Training Plan, and Lifecycle Costs and Funding Plan (see Figure 2). These plans will provide the framework for achieving the near-term strategy. Ultimately, these plans will be summarized and collated to develop the Blueprint, which will be a living document that RTD continually updates as market factors, funding, technology, and direction evolve. The FTA Plan is largely a derivative of the Blueprint that focuses on the six FTA-required ZE Transition Plan elements. The FTA Plan will position RTD to begin applying for various federal grants to support facility and fleet low- and no-emission upgrades.
Figure 2: Phase 2 Workflow
Source: WSP
2.3 REPORT BACKGROUND, PURPOSE, AND STRUCTURE
2.3.1 Background
As part of the FFTP project and associated facility planning work, RTD has identified a future need for a new fixed-route bus operating and maintenance facility. As an initial step toward site selection and design for a new facility, RTD and the project team initiated a Facility Siting Analysis to narrow the list of potential locations among property owned by RTD and by other public-sector entities. The Facility Siting cq15039 Highlight
FACILITIES AND FLEET TRANSITION PLAN 8
Analysis establishes a set of evaluation criteria, prioritized in three tiers, to provide a structured approach to the parcel screening and to standardize the methodology for future assessment of site suitability for a new fixed-route bus division. Additionally, the analysis identified a shortlist of 17 potential facility locations among RTD-owned property for further review and consideration. This shortlist was further refined to three candidate locations based on parcel size and proximity to current and planned SOP service. The project team also analyzed vacant parcels within the District that are owned by other public-sector entities outside of RTD and identified a shortlist of 46 parcels based on size and zoning compatibility with a bus facility.
2.3.2 Purpose and Structure
This Facility Siting Analysis report presents the results of a screening of the RTD-owned real estate portfolio for potential future bus facility locations. Additionally, this report presents the methodology and results of an initial District-wide screening of other vacant, publicly-owned parcels for size and compatible zoning.
This report is structured as follows:
1. Executive Summary
2. Introduction: Project overview, background, and plan background and purpose.
3. Analysis Approach: Overview of the parcel screening criteria and approach for the RTD-owned parcels and other publicly-owned parcels.
4. RTD-Owned Parcel Analysis: Results of the screening and analysis of the RTD-owned properties
5. Other Publicly-Owned Parcel Analysis: Results of the size and zoning screening of other vacant parcels owned by other public-sector entities.
6. Phase 2 Facility Siting Parcel Screening: Overview of RTD-owned parcel shortlist refinement and initial size and zoning screening for other publicly-owned, vacant parcels.
7. Conclusion: Overview of the report’s main takeaways and immediate next steps.
ANALYSIS APPROACH
FACILITIES AND FLEET TRANSITION PLAN 9
3. ANALYSIS APPROACH
3.1 OVERVIEW
The approach for determining appropriate facilities was guided by a high-level evaluation of sites based on criteria that would be incorporated into a list of potential sites for a future bus facility (see Figure 3).
The approach began with identifying RTD and publicly-owned land parcels that met a minimum criterion of being six acres in size, or adjacent parcels that could be assembled to reach six acres. Certain parcels were excluded based on current and planned uses. These sites were evaluated based on the Tier A, and some Tier B, criteria. The goal of the facility siting is to have a short-list of sites to consider for evaluation for a future bus operating and maintenance facility.
The site evaluation did lead to a short list of RTD owned sites for further evaluation along with a list of publicly-owned sites for further evaluation. The site evaluation has criteria that consider bus operations factors, site access, utilities, property ownership, and environmental impacts. The screening focused primarily on parcel ownership that considered only publicly-owned and RTD-owned parcels, zoning in and around the publicly-owned parcels, and proximity to route ends. The analysis also looks at high-level environmental factors for evaluating each of the sites. These factors provide a short-list of candidate sites for consideration (see Table 2). This includes property currently owned by RTD, in addition to vacant parcels owned by other public sector entities or government jurisdictions within the RTD service area.
Figure 3: Analysis Approach Flowchart
Source: Transportation Management & Design, Inc. (TMD), WSP
The screening of the other vacant publicly-owned parcels in the service area (not owned by RTD) provided helpful context for considering potential facility locations outside RTD’s current property portfolio that could be acquired in the future. The initial screening of parcels yielded a list of 1,763 parcels that are vacant, owned by a public sector or governmental entity, and at least six acres (the
Inputs
•Evaluation Criteria •GIS Parcel Data •Current and SOP service levels and route endpoints
Analysis
•RTD Input •Data Cleaning •Parcel Ownership (public sector)
•Parcel Size •Route End Density Proximity Analysis
Outputs
•Potential Facility Parcels Shortlist
FACILITIES AND FLEET TRANSITION PLAN 10
minimum amount of land needed to construct a small bus facility). This was reduced to fewer than 50 parcels after screening for compatible zoning and further review.
Having the short-list of candidate sites for consideration for a future bus operations facility, further evaluation of the feasibility of each site will be needed. The primary analysis would be an alternatives analysis to determine which of the facilities are the best candidates. The alternatives analysis will look at the operations as well as other datasets including environmental factors and the existence and compatibility of utilities for new technology buses. The goal of the alternatives analysis is to select a small number of sites from the short list of potential sites for construction of one or two bus operating and maintenance divisions.
Future analysis will require additional datasets and outreach. Datasets would be used to refine the analysis and would include schedule outputs from the SOP and detailed zoning and land use analysis for the areas around each of the sites. For sites that may be selected for the construction of a bus facility, an Environmental Assessment may be required with detailed evaluation of environmental impacts. The screening and comparative analyses would limit the number of sites where detailed evaluation will be conducted.
3.2 SCREENING CRITERIA
A set of evaluation criteria, prioritized in three tiers, was developed to provide a structured approach to the parcel screening and to standardize the methodology. These criteria are shown Table 1. Tier A or “Critical” tier criteria include location, bus deadhead impacts, and roadways/access and represent the most important criteria that will disqualify certain parcels before more nuanced criteria are applied. For example, a parcel that is too small to accommodate a bus facility, or does not have compatible zoning, or is too far from existing or planned bus service will be eliminated before considering development costs or environmental impacts. These criteria were presented to RTD staff at the March 16, 2024, FFTP Working Group meeting and revised based on group feedback. The Parcel Screening Analysis included several Tier A criteria, as well as several key Tier B and C criteria not requiring formal environmental review or analysis of adjacent utilities.
FACILITIES AND FLEET TRANSITION PLAN 11
Table 1: Parcel Evaluation Criteria
Tier A/Critical Tier B Tier C Location
• Parcel size
• Zoning/Future Land Use
(FLU) compatibility
• Site configuration
• Adjacent use compatibility
• Environmental justice/nearby demographics and equity
• Safety and security
Bus Operating Cost/Deadhead Impacts
• Proximity to high route-end densities
Roadways/Access
• Adjacent roadway quality
• Direct access to arterial
• Freeway access
• Hazardous materials delivery
Utilities
• Electric utility service area
• Electric substation proximity
• Gas, water, wastewater, telecom proximity and capacity
Parcel Acquisition
• Acquisition cost
• Current ownership
• Easements
• Development/relocation costs
Environmental Impacts
• Traffic
• Parklands
• Historic preservation/ cultural resources
• Noise
• Vibration
• Wetlands
• Floodplains
• Drainage and water quality
• Ecologically sensitive
• Migratory birds/prairie dogs
• Geotechnical (soil suitability)
• Hazardous material
(remediation and on-site storage)
• Climate hazard
Source: TMD, WSP, and RTD
3.3 RTD-OWNED PARCEL ANALYSIS
Following the initial screening of the RTD-owned parcels, the team identified a shortlist of 17 parcels for further screening and review. These parcels have been screened for RTD ownership, screened for a minimum 6.0-acre size threshold, and reviewed for proximity to current and SOP route ends. The results of the route end proximity analysis are shown in Table 2. The 17 RTD-owned parcels are ranked by the number of current route ends (in terms of those routes’ total scheduled weekly block counts) within a 10-mile drive. Further review and discussion of a final three-location shortlist can be found in Section 4.
FACILITIES AND FLEET TRANSITION PLAN 12
Table 2: Total Weekly Vehicle Block Counts (by Route Ends within Driveshed)
Parcel No. Parcel Name
Parcel Size
(Acres)
Existing Service SOP Routes
1 mi 10 mi 1 mi 10 mi
1 Existing Transdev Access-a-Ride Facility (7500 E 41st Ave, Denver) 7.8 52 8,000 814 6,402
2 Former 70th Ave/Broadway PNR 16.3 0 7,128 0 5,912
3 Existing RTD North Metro Commuter Rail MOW Facility 7.3 0 6,286 0 4,678
4 Vacant (Quail Yard; Quail St. south of W Colfax Ave) 18.2 0 5,664 140 4,460
5 Former Ward Rd & I-70 Park-n- Ride 7.7 98 4,862 0 3,314
6 Existing Wadsworth & Hampden Park-n-Ride 9.2 38 2,522 104 3,658
7 Vacant (across W. Hampden Ave.
from Wadsworth Park-n-Ride) 12.4 38 2,386 104 3,468
8 Vacant (102nd Ave & Riverdale Rd Open Lands, Thornton) 8.7 0 2,358 0 1,848
9 Vacant (C-470/Lucent Blvd) 11.3 0 1,382 0 1,242
10 Vacant (Former US-36/Broomfield Park-n-Ride) 20.7 0 1,328 0 1,674
11 Vacant (Across Midway Blvd from US-36/Flatiron East Park-n-Ride) 9.1 0 1,254 24 1,040
12 Vacant (South of 80th Ave, between Simms St & Alkire St) 19.1 0 1,126 0 1,450
13 Existing C-470/Ken Caryl Park-n- Ride 6.6 0 856 0 862
14 Existing US-285/Twin Forks Park-n-Ride 9.9 0 194 0 100
15 Vacant (Northeast of E-470/I-76) 11.5 0 144 0 162
16 Existing Pine Junction Park-n-Ride 6.9 0 0 50 50
17 Existing US-285/Mountain View Park-n-Ride 14.7 0 0 0 50
Source: RTD Property Data and September 2023 Runboard Data
FACILITIES AND FLEET TRANSITION PLAN 13
3.4 OTHER PUBLICLY-OWNED PARCEL ANALYSIS
The parcel screening process for publicly-owned parcels was conducted using a similar methodology as the RTD screening process, with the addition of the detailed zoning analysis. As part of this screening of the publicly-owned parcels, the GIS parcels from Adams, Arapahoe, Broomfield, Boulder, Denver, Douglas, and Jefferson counties were identified and screened for public ownership. This step created the universe of public parcels across the RTD service area that can be considered as potential sites for a bus operating facility. An overview of the process for identifying and screening public parcels is below (See Section A of the Appendix for a more detailed explanation of the process).
Step 1: Obtain GIS parcel data for seven counties in RTD service area and identify vacant parcels with public ownership
Step 2: Screen parcels for six-acre size threshold and appropriate geometry (i.e., remove parcels too narrow to accommodate a facility footprint)
Step 3: Conduct zoning screening for parcels under jurisdiction of county-level zoning code (review the zoning codes present in parcels that passed Step 2 and remove those with incompatible zoning types)
Step 4: Conduct zoning screening for parcels superseded by city-level zoning code jurisdiction (review the zoning codes present in parcels that passed Step 2 but are under the zoning codes of various cities rather than the counties, and remove those with incompatible zoning types)
Step 5: Merge candidate parcels from Steps 4 and 5 and conduct spot-check to remove obvious non-contenders
Step 6: Conduct route-end proximity analysis (same methodology as RTD-owned parcels)
The total screened public-sector and governmental entity parcels from the initial vacancy, ownership, size, and shape screening totaled 1,763 parcels, which are shown in Figure 4. Following the zoning screening and spot-check, 46 candidate parcels remained. An overview of these candidate parcels can be found in Section 5.
FACILITIES AND FLEET TRANSITION PLAN 14
Figure 4: Publicly Owned Vacant County Parcels
Source: TMD
RTD-OWNED PARCEL ANALYSIS
FACILITIES AND FLEET TRANSITION PLAN 15
4. RTD-OWNED PARCEL ANALYSIS
As noted previously in Section 3, the project team identified a shortlist of 17 RTD-owned parcels for further screening and review. These parcels were screened for confirmed RTD ownership, a minimum 6.0-acre size threshold, and reviewed for proximity to current and SOP route ends. Following the initial analysis and in consultation with RTD staff, the project team refined the RTD-owned parcel shortlist to include just the top six locations (encompassing seven parcels) from the route ends proximity analysis.
Beyond scoring lower on the route end proximity analysis, the 10 parcels eliminated from the Phase 2 list also presented various challenges limiting their suitability as a future facility location. These include actual usable site footprints below the necessary acreage, future planned uses for the parcel, or excessive distance from the core of the RTD service area. The six remaining sites were further reviewed to identify three final candidates for consideration in the next phase of future facility planning following conclusion of the FFTP. The following sections present an overview of the six short-listed locations and the three final candidates.
The list of six shortlisted RTD-owned locations, encompassing seven parcels, is shown in Table 3. These include the existing Transdev Access-a-Ride Facility, the former 70th Avenue/Broadway Park-n-Ride, the RTD North Metro Commuter Rail MOW Facility site, Quail Yard, the former Ward Road & I-70 Park-n- Ride, and the existing Wadsworth & Hampden Park-n-Ride (with the adjacent vacant parcel across W.
Hampden Avenue). These six locations are centrally located within the RTD service area and urbanized core of the Denver Metro Area, as reflected by their highest scores in both the current service and SOP route end proximity analysis.
Table 3: Initial Phase 2 Shortlist of RTD-Owned Parcels with Route Ends Analysis Results
Parcel No. Parcel Name
Parcel Size
(Acres)
Existing Service SOP Routes
1 mi 10 mi 1 mi 10 mi
1 Existing Transdev Access-a-Ride Facility (7500 E 41st Ave, Denver) 7.8 52 8,000 814 6,402
2 Former 70th Ave/Broadway PNR 16.3 0 7,128 0 5,912
3 Existing RTD North Metro Commuter Rail MOW Facility 7.3 0 6,286 0 4,678
4 Vacant (Quail Yard; Quail St. south of W Colfax Ave) 18.2 0 5,664 140 4,460
5 Former Ward Rd & I-70 Park-n- Ride 7.7 98 4,862 0 3,314
6 Existing Wadsworth & Hampden Park-n-Ride 9.2 38 2,522 104 3,658
FACILITIES AND FLEET TRANSITION PLAN 16
Parcel No. Parcel Name
Parcel Size
(Acres)
Existing Service SOP Routes
1 mi 10 mi 1 mi 10 mi
7 Vacant (across W. Hampden Ave.
from Wadsworth Park-n-Ride) 12.4 38 2,386 104 3,468
Source: RTD Property Data and September 2023 Runboard Data
4.1 INITIAL SHORTLIST PARCELS ELIMINATED FROM FINAL LIST
Following further review of the six shortlisted locations, the project team identified challenges and constraints with three of the six that precluded their inclusion in the final Phase 2 list. A discussion of these three parcels (numbers 1, 3, and 5) and their limitations is below. A prime consideration for these parcels is size. RTD staff have articulated a desire to develop a bus facility with a comparable size to the Platte or East Metro divisions. At a general estimate of 10 buses per acre of facility size, a 200-bus facility would require 20 acres. None of the six locations meet this threshold, with the exception of the consolidated acreage of the bifurcated parcels 6 and 7 site, but further review and discussion of exact facility needs is warranted to determine if the three remaining shortlisted RTD-owned parcels are sufficiently sized.
4.1.1 Parcel 1: Existing Transdev Access-A-Ride Facility, 7500 E 41st Ave, Denver Parcel 1 is located near Quebec Street just south of I-70. It is currently occupied by Transdev’s Access-a- Ride facility and is adjacent to an electrical substation, two motels, and several industrial parcels, including a trucking depot.
This parcel scored highest on the route end proximity analysis and is conveniently located near the Quebec Street and I-70 junction and is less than three miles from the East Colfax Avenue corridor.
However, the parcel’s existing use as an Access-A-Ride facility introduces significant challenges to its redevelopment as an RTD fixed-route operating and maintenance facility. Displacing the Access-a-Ride facility would require development of a new location for that operation, which dramatically increases cost and precludes the feasibility of this parcel for a future fixed-route facility.
Table 4: Parcel 1 Details (Existing Transdev Access-A-Ride Facility, 7500 E 41st Ave, Denver)
Parcel Size (Acres) City
Coordinates (Latitude, Longitude)
Current Use
7.8 Denver 39.77438112, -104.9006652 Transdev Access-a-Ride Facility
Source: RTD Property Data and Google Maps
FACILITIES AND FLEET TRANSITION PLAN 17
Figure 5: Parcel 1 (Existing Transdev Access-A-Ride Facility, 7500 E 41st Ave, Denver)
4.1.2 Parcel 3: Existing RTD North Metro Commuter Rail MOW Facility Parcel 3, on Steele Street north of E 78th Avenue and adjacent to the South Platte River, is planned for use as the North Metro Commuter Rail Maintenance of Way (MOW) Facility. Use of this site for a future bus facility would require accommodation of the MOW needs or relocation of that facility to another site.
This site was acquired for support of N line commuter rail operations.
The existing and planned uses for this site introduce feasibility challenges for also developing a bus facility. Assuming the planned commuter rail maintenance of way uses are fully realized, a bus operating and maintenance facility would almost certainly need to develop as an overbuild to an already size-constrained parcel. If the Commuter Rail MOW facility is built elsewhere, it introduces additional property acquisition costs and constraints for siting that facility adjacent to the rail right-of-way. As with Parcel 1, the cost implications and incumbent operational complexity eliminate this site from contention.
FACILITIES AND FLEET TRANSITION PLAN 18
Table 5: Parcel 3 Details (Existing RTD North Metro Commuter Rail MOW Facility)
Parcel Size (Acres) City Coordinates
(Latitude, Longitude) Current Use
7.3 Welby (Unincorp.
Adams County) 39.84466744, -104.9504256 RTD Rail Facility
Figure 6: Parcel 3 (Existing RTD North Metro Commuter Rail MOW Facility)
4.1.3 Parcel 5: Former Ward Rd & I-70 Park-n-Ride
Parcel 5 is occupied by the former Ward Road & I-70 Park-n-Ride, which was closed in 2021 with the opening of the Wheat Ridge/Ward Road Station Park-n-Ride. CDOT has since used the parcel for equipment storage and staging during the I-70 & Ward Road Improvements project.
FACILITIES AND FLEET TRANSITION PLAN 19
While this site’s location in the west metro area and proximity relative to existing and planned SOP service is compelling, its relatively small size introduces limitations for future bus facility use. RTD staff have articulated a desire to develop a bus facility with a comparable size to the Platte or East Metro divisions. At a general estimate of 10 buses per acre of facility size, this parcel could accommodate no larger than a 77-bus facility. Given that the actual usable footprint is probably smaller, this precludes this parcel’s development as a suitably sized bus facility. Additionally, following closure of the RTD Park-n- Ride, this parcel may revert to CDOT ownership, introducing additional complexity to any future use by
RTD.
Table 6: Parcel 5 Details (Former Ward Rd & I-70 Park-n-Ride)
Parcel Size (Acres) City Coordinates
(Latitude, Longitude) Current Use
7.7 Wheat Ridge 39.78049627, -105.1391884 Bus Park-n-Ride
Figure 7: Parcel 5 (Former Ward Rd & I-70 Park-n-Ride)
FACILITIES AND FLEET TRANSITION PLAN 20
Source: RTD Property Data and Google Maps
4.2 FINAL RTD-OWNED PARCEL SHORTLIST
The following section provides an overview of the three remaining RTD-owned parcels on the Phase 2 list. While these parcels remain in contention, their ultimate suitability for a fixed route facility has not been established and further evaluation is required. However, they are appropriately located, of adequate size, and do not have obvious constraints or planned uses that preclude their candidacy.
4.2.1 Parcel 2: 70th Ave/Broadway Parking Lot
Parcel 2 is partially occupied by a parking lot. It was formerly the 70th Ave & Broadway Park-n-Ride but has been closed since 2016. Approximately nine acres of the 16-acre site are vacant and undeveloped.
Further analysis is needed to determine if any of the 16-acre site is unusable, or its total size can be considered.
The parcel is located adjacent to the US-36 and I-25 junction, which facilitates its use as a facility that would operate service for portions of the northern parts of the region. Given the size constraints at the Boulder Division, which precludes that facility from accommodating articulated buses, this location would reduce the deadhead distance for operating larger vehicles in Boulder compared to the other two candidate locations described below.
Zoning: The parcel is subject to the Adams County Zone District regulations. The majority of the parcel is zoned Industrial-1 District (I-1), while approximately 22% of the parcel is zoned Commercial-4 District (C-4). Among light industrial uses, “bus repair,” “local and interurban passenger transit,” and “transportation services” are all permitted in I-1 zones. While all three of these uses are prohibited in C-4 zones, all government‐owned facilities except landfills or mining facilities are an allowed, conditional use in this zone. Additional analysis and coordination with Adams County will be necessary to ensure that a bus operating facility will be permissible on the entire parcel without a zoning variance or other change.
Table 7: Parcel 2 Details (70th Ave/Broadway Parking Lot)
Parcel Size (Acres) City
Coordinates (Latitude, Longitude) Current Use
16.3 Denver 39.8254365, -104.9886847 Parking Lot
FACILITIES AND FLEET TRANSITION PLAN 21
Figure 8: Parcel 2 (70th Ave/Broadway Parking Lot)
4.2.2 Parcel 4: Vacant (Quail Yard, Quail St south of W Colfax Ave) Parcel 4, a vacant parcel (known as Quail Yard), is located along Quail Street south of West Colfax Avenue, just west of Oak Station on the W Line. Its primary frontage is on Quail Street but includes right-of-way for a driveway connection to Simms Street. RTD initially acquired this parcel for use as a West Metro bus facility. The agency has constructed a test roadway and mock platform to be used for operator training for the center-running Colfax BRT at the site. Further discussion is needed to determine if the BRT training facility could be accommodated alongside the operating and maintenance division. It is likely that, if a bus facility is developed at this site, the BRT training facility would need to be relocated or constructed elsewhere.
Additionally, some of the property is within a flood hazard area which could restrict how the property is used. The northern portion of the parcel, between W. Colfax Avenue and W. Rail Road, is identified by
FACILITIES AND FLEET TRANSITION PLAN 22
FEMA as a Zone AE Special Flood Hazard Area, which means it would be inundated by a flood event having a 1-percent chance of being equaled or exceeded in any given year (100-year flood).5 Most of the western edge of the parcel is bounded by a small waterway known as Agricultural Ditch, which is a tributary of Dry Gulch. The latter and its other tributaries can become inundated during rainy periods and is the subject of a City of Lakewood and Mile High Flood District flood mitigation project. A future bus facility’s location within a flood zone would likely incur additional planning, engineering, construction, and insurance costs.
Zoning: This parcel is subject to the zoning regulations of the City of Lakewood Municipal Code. The entire parcel is zoned Light Industrial Research and Development (LI-RD). Under the Lakewood code, “Vehicle Dispatch Facility” and “[Public] Transportation Facility” are both permitted uses as of right.
Table 8: Parcel 4 Details (Quail Yard, Quail St South of W Colfax Ave)
Parcel Size (Acres) City Coordinates
(Latitude, Longitude) Current Use
18.2 Lakewood 39.73804321, -105.1248769 Vacant
5 See FEMA Letter of Map Revision (LOMR) 14-08-0653P for the City of Lakewood in Jefferson County, Colorado, issued June 6, 2014. https://map1.msc.fema.gov/data/08/L/14-08-0653P- 085075.pdf?LOC=c821b3986cc671f8b282eba7f7251be9
FACILITIES AND FLEET TRANSITION PLAN 23
Figure 9: Parcel 4 (Quail Yard, Quail St South of W Colfax Ave)
4.2.3 Parcel 6 & 7: Existing Wadsworth & Hampden Park-n-Ride and Adjacent Vacant Parcel
Parcel 6, on Wadsworth Boulevard at US-285, is the Wadsworth & Hampden Park-n-Ride. The park-n-ride has a capacity of 284 spaces and averaged 5 daily vehicles in the 2023, down from 15 in 2019.
Parcel 7 is directly across Hampden Avenue from the Park-n-Ride. The parcel is adjacent to the multifamily Skyecrest Apartments to the south and open/agricultural space to the west. An image of both Parcels 6 and 7 is shown in Figure 10.
Considered together, these two parcels encompass a total acreage of 21.6 acres, providing ample space for the larger facility desired by RTD. However, the site is bifurcated by W. Hampden Ave. This introduces some complexity in terms of site design and future operations if W. Hampden Ave is not realigned in some fashion to allow for contiguous use of the entire two-parcel location. Moving a portion
FACILITIES AND FLEET TRANSITION PLAN 24
of W. Hampden Ave below grade with an underpass or constructing a bridge over the roadway to connect the two facility parcels may be feasible but would add significant cost to the project.
Zoning: These two parcels are immediately outside Lakewood city limits in unincorporated Jefferson County and subject to the county Zoning Resolution. Both parcels are zoned Agricultural-Two District (A- 2). The Jefferson County Zoning Resolution does not include a public transportation facility among permitted or special uses in A-2 zones. Use of this location for a new RTD facility may require a zoning variance or rezoning. All four of Jefferson County’s industrial district types allow for “Terminals for transportation and public transit vehicles.”
Table 9: Parcel 6 Details (Existing Wadsworth & Hampden Park-n-Ride)
Source: RTD Property Data and Google Maps
Table 10: Parcel 7 Details (Adjacent Vacant Parcel)
Parcel Size (Acres) City
Coordinates (Latitude, Longitude)
Current Use
12.4 Unincorporated
Jefferson County near Lakewood
39.65118769, -105.0850946 Vacant
Source: RTD Property Data and Google Maps
Parcel Size (Acres) City
Coordinates (Latitude, Longitude)
Current Use
9.2 Unincorporated Jefferson
County near Lakewood 39.65108613, -105.0828219 Bus Park-n-
Ride
Parcel 7 Parcel 6
FACILITIES AND FLEET TRANSITION PLAN 25
Figure 10: Parcels 6 and 7
OTHER PUBLICLY-OWNED PARCEL ANALYSIS
FACILITIES AND FLEET TRANSITION PLAN 26
5. OTHER PUBLICLY-OWNED
PARCEL ANALYSIS
As discussed in Section 3.4, the screening of other parcels within the RTD service area for public ownership, vacancy, size, shape and zoning type that would allow for a transit facility yielded a shortlist of 46 parcels. These are shown in Table 11 and Figure 11.
6 These parcels range in size from six to 248 acres, with 28 of the 46 under 16 acres. The 46 parcels are owned by 21 different entities, with the most common owners being the City of Aurora, the City and County of Denver, CDOT, and the City of Boulder. Should the three shortlisted RTD-owned parcels prove infeasible for facility development, or if RTD wishes to consider options beyond their current real estate portfolio, further analysis of these parcels is warranted.
Should RTD pursue further investigation of these parcels, next steps would include further size screening to confirm suitability for the desired facility size, review of adjacent use compatibility, and a high-level environmental review to check for wetland/floodplain constraints or any other physical site characteristics that could impact feasibility.
Table 11: Shortlist of Other Public-Owned Parcels
Parcel No. County Parcel Owner Size
(Acres) Existing Service SOP Routes 1 mi 10 mi 1 mi 10 mi
1 Denver CDOT 7.7 133 4,381 0 4,595 2 Denver City & County of Denver 8.3 0 4,270 0 4,506 3 Denver CDOT 6.9 0 4,264 0 4,409 4 Adams City of Aurora 13.9 0 4,248 0 4,240 5 Denver City & County of Denver 7.1 0 4,238 0 4,261 6 Adams City & County of Denver 24.5 0 4,225 0 4,560
7 Adams Adams County Board of County Commissioners 9.4 0 3,939 0 4,786
8 Denver City & County of Denver 12.8 0 3,896 0 4,256 9 Denver CDOT 7.1 0 3,725 0 4,179
6 An interactive version of this map with the 46 shortlisted parcels can be found here. Parcels numbers correspond with Table 11.
https://www.arcgis.com/apps/mapviewer/index.html?webmap=17cf6a72c36d4866b1a2dca8d634d143.
https://www.arcgis.com/apps/mapviewer/index.html?webmap=17cf6a72c36d4866b1a2dca8d634d143
FACILITIES AND FLEET TRANSITION PLAN 27
Parcel No. County Parcel Owner Size
(Acres) Existing Service SOP Routes 1 mi 10 mi 1 mi 10 mi
10 Adams Brittany Place Metropolitan District 14.8 0 3,569 0 3,840
11 Jefferso n
Arvada Urban Renewal Authority 7.0 19 3,355 0 3,476
12 Jefferso n City of Wheat Ridge 10.0 0 2,681 100 2,637
13 Adams City of Aurora 49.6 0 1,833 0 2,107 14 Adams City of Aurora 77.1 0 1,805 0 2,112 15 Adams City of Aurora 33.7 0 1,726 0 2,107 16 Denver City & County of Denver 177.7 0 1,687 0 1,776 17 Adams City of Aurora 20.7 0 1,680 0 1,943 18 Adams City of Aurora 13.7 0 1,617 0 1,943 19 Adams City of Aurora 9.9 0 1,617 0 1,943 20 Adams City of Aurora 12.4 0 1,617 0 1,910 21 Denver City & County of Denver 247.5 0 1,560 0 1,607 22 Denver State of Colorado 8.4 0 1,560 0 1,607 23 Denver City & County of Denver 58.8 0 1,395 0 1,494
24 Denver Aviation Station North Metropolitan District 9.4 0 1,241 0 1,618
25 Adams Park 70 Metropolitan District 13.4 0 1,215 0 1,106
26 Boulder City of Boulder 155.0 0 1,179 0 1,035 27 Boulder City of Boulder 79.0 0 1,157 0 1,224 28 Boulder City of Boulder 38.1 0 1,157 40 1,224 29 Boulder City of Boulder 21.9 0 1,157 26 1,079 30 Boulder U.S. Government 40.5 0 1,088 0 1,079 31 Boulder County of Boulder et al. 67.7 0 1,060 0 1,055 32 Adams CDOT 19.8 0 996 0 796 33 Adams City of Westminster 15.4 0 761 0 1,144
34 Broomfie ld UCHealth 14.0 0 735 197 1,162
FACILITIES AND FLEET TRANSITION PLAN 28
Parcel No. County Parcel Owner Size
(Acres) Existing Service SOP Routes 1 mi 10 mi 1 mi 10 mi
35 Boulder City of Lafayette et al. 56.0 0 706 0 749 36 Adams City of Westminster 31.1 0 698 0 1,065 37 Boulder County of Boulder 10.0 0 558 0 774
38 Jefferso n
Jefferson Center Metropolitan District No.
15.0 0 334 0 715
39 Jefferso n
Jefferson Center Metropolitan District No.
10.4 0 320 0 715
40 Jefferso n
Jefferson Parkway Public Highway Authority 6.1 0 216 0 663
41 Boulder City of Longmont 10.3 6 209 38 286 42 Boulder City of Longmont 8.5 0 209 0 286
43 Boulder St. Vrain Valley School District No. Re-1J 9.6 0 209 0 311
44 Boulder County of Boulder et al. 156.6 0 188 0 236 45 Boulder UCHealth 8.1 0 188 0 291
46 Adams Brighton Housing Authority 7.1 0 86 0 81
Source: RTD Property Data and September 2023 Runboard Data
FACILITIES AND FLEET TRANSITION PLAN 29
Figure 11: Other Publicly-Owned Parcel Screening Shortlist
CONCLUSION
FACILITIES AND FLEET TRANSITION PLAN 30
6. CONCLUSION
6.1 FACILITY SITING SUMMARY
The Facility Siting Analysis was driven by RTD’s desire to begin the process of identifying a suitable location for a District-owned, fixed-route bus operation and maintenance facility, or division. This analysis builds on initial screening analysis, with further review of the RTD-owned parcels and identification of a three-site shortlist for advancing in the environmental review process. Additionally, this analysis presents the methodology and results for an initial, District-wide screening of other vacant, publicly-owned parcels not owned by RTD.