About this file

This document is a Statement of Work (SOW) for the procurement and installation of a battery backup system and inverters for the NAS Defense Programs (NDP) MAST facility at Punta Tuna in Maunabo, Puerto Rico. The SOW details the requirements for the contractor to assess the site, provide and install the battery backup system, perform testing and training, and provide warranty information.

The related federal contract opportunity is a competitive solicitation for a firm-fixed-price contract to provide and install the battery backup system. The solicitation has been set aside for Small Disadvantaged Businesses, and the FAA intends to award the contract to the lowest priced, eligible offeror. Proposals are due by July 18, 2024, and a site visit is scheduled for July 10, 2024. The period of performance for the contract is 60 days from the notice to proceed.

View the file

Other files

File Type Posted
Offeror Organizational Experience Form.pdf PDF
6973GH-24-Q-00214.pdf PDF
Contractors Release Form DOT F 4220.4.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SERVICES STATEMENT OF WORK

For

Procurement and Installation of Battery Backup System and Inverters for the

NDP MAST Program

1. Background and Overview

This service statement of work entails the design and the installation of Battery Backup System to support the facility on Punta Tuna in Maunabo P.R. to meet the mission requirements of the NAS Defense Programs (NDP) and Department of Homeland Security (DHS) Customs and Border Protection (CBP). The Battery Backup System is intended to provide support to the mentioned facility in case of a power outage, to provide a minimum of 24-hour continuous backup to ensure the MAST System remains operational.

2. Purpose

The NDP aims to implement a backup system in case of a power outage to ensure uninterrupted operational capability of the facility for 24 continuous hours as a minimum.

3. Scope of work

Contractor will complete the following:

Conduct a thorough assessment of the site to determine power and capacity requirements, installation placement, and safety considerations.

Provide and install power battery backup system and design as approved by NDP Project Manager during solicitation review. Include specifications for batteries, inverters, chargers, and other necessary components to provide constant backup of uninterrupted power for a period of 24hr minimum based on 2kW/h load consumption.

The output power of the system must be 120/240V.

System must have the capacity to integrate solar system and engine power generator.

The installation should be inside the existing Equipment Conex. In case the specifications of the cabinet exceed the limited space, the battery cabinets should be installed at the east wall outside of the Conex.

Each battery cabinet should be secure for antitheft with a cage or secure bar with easy access to perform battery maintenance or replacement.

All the electrical piping must be rigid and galvanized with proper bushing and conduit fittings on each connection.

Complete proper connection to the existing electrical infrastructure for proper operation of the battery backup system.

Perform comprehensive testing of the installed system to ensure functionality, efficiency, and reliability. This testing will include but not limited to:

Operational test to confirm that the system provides constant backup of uninterrupted power for a period of 24hr minimum based on 2kW/h load consumption.

Certification of the installation in compliance with the proper regulations.

Provide training to relevant personnel on the operation, maintenance, and troubleshooting of the battery backup system.

Provide documentation, including user manuals, technical specifications, and as-built drawings, for future reference and maintenance purposes.

o Two Hard Copies in Binder o One soft copy

Provide the warranty of the installation and the equipment for a period of 10 years after project completion.

• Written proof of warranty must include:

• Exact nature of the item and its components that the contractor warrants.

• Extent of the contractor’s warranty, including all the contractor’s obligations to the FAA for breach of warranty.

• Specific remedies available to the FAA.

• Scope and duration of the warranty.

4. Location of Work

All work related to this statement of work will be performed on Crown Castle Tower site at Punta Tuna, Maunabo PR at the following address:

RD 760, Bo. Emajagua

Maunabo,P.R.

Coordinates:

Latitude:17.995537°N Longitude: 65.888155°W

5. Period of Performance

The period of performance for execution of the requirements identified in this Statement of Work shall be completed within 60 days from receiving notice to proceed.

6. Deliverables Schedule & Meetings

Contractor will coordinate with the Contracting Officer Representative (COR) and local on-site staff training times and equipment installation times. Availability times are expected to be from 9am-5pm local time unless other times are agreed upon by on-site staff and the contractor.

Access the site will be provide as per the agreed schedule.

Any “Act of God” such as adverse weather conditions or unforeseen circumstances must be considered during the development of the project schedule.

Contractor will provide training curriculum, schedule, and agenda for approval at least 15 days prior the date of the activity.

7. Applicable Standards

All Electrical Work and Materials must comply with National Electrical Code (NEC), industry standards and manufacture guidelines.

8. Acceptance Criteria

Upon installation of equipment and services provided in this statement of work, contractor will:

1. Certify that the Battery Backup System is fully operational and in compliance with our requirements.

2. Certify that the maintainers have obtained the required information and training to install, operate and maintain the System.

3. Operational test to confirm the load and capacity to confirm that the system holds the load for 24 hrs.

9. Pictures Attached

Conex outside 1 Conex outside 2 Conex outside 3 Conex inside 1 Conex inside 2 Floor Plan Interior Elevations

Conex outside 1

Conex outside 2

Conex outside 3

Conex inside 1

Conex inside 2

Floor Plan

Interior Elevations