SOW_MT_Room_1125_Renovation.pdf
PDF 179 KB Posted
- Attached to
- RFP Main Treasury Renovation 1125
- Solicitation number
- 2032H326R00019
- Issued by
- District of Columbia
About this file
This Statement of Work (SOW) outlines a competitive firm fixed price contract for the renovation of Main Treasury Room 1125, located at 1500 Pennsylvania Avenue, NW, Washington, DC 20220, administered by the District of Columbia. The scope of work encompasses hazardous material abatement, office space refurbishment including painting and carpet replacement, security upgrades to doors, and mechanical and electrical renovations with HVAC improvements, all performed in accordance with approved design drawings and project specifications. The contractor must provide all labor, tools, equipment, management, and supplies necessary for project completion. The period of performance extends one year from the date of award. Contractors must submit two-week look-ahead schedules every Monday detailing planned work, scheduled deliveries, tentative project completion dates, and pending issues. Work is restricted to standard business hours between 7:00 am and 3:30 pm, Monday through Friday, excluding federal holidays and government facility closures.
This is a Total Small Business Set-Aside contract under NAICS code 236220 for Commercial and Institutional Building Construction. All workers must be U.S. citizens and subject to security protocols including property control inspections, alarm system coordination, and Treasury Property Pass requirements for material removal. Material deliveries require 25 hours advance notice with Access Forms submitted to the Treasury Facilities Service Desk, and all deliveries must first proceed to the Remote Delivery Site at JBAB Visitor Center for vehicle inspection and scanning before U.S. Secret Service escort to the Treasury Complex. The contractor bears all costs for correcting defective work within a reasonable timeframe and assumes responsibility for any system damage caused by contractor employees, including repair costs and related overtime expenses. Standard commercial warranties covering all materials and equipment must be collected and delivered to the government upon project completion.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Main Treasury 1125 Renovation
1. BACKGROUND
This is a competitive firm fixed priced stand-alone contract. This is a new acquisition for Main Treasury 1125 Renovation.
2. SCOPE OF WORK
The contractor shall provide all labor, tools, equipment, management, supplies and any other items deemed necessary to complete the following:
This contract is for the renovation of Main Treasury Room 1125 and includes, but is not limited to, hazardous material abatement; refurbishment of the office space, including painting and carpet replacement; security upgrades to doors; and mechanical and electrical renovations, including heating, ventilation, and air conditioning (HVAC) improvements, in accordance with the approved design and project requirements outlined in the following additional documents:
a) MT Room 1125 Renovation Drawings and Specifications
3. DELIVERABLES AND DELIVERY SCHEDULE
a) Standard Commercial Warranty:
The Contractor agrees that the supplies or services furnished under this contract shall be covered by the most favorable commercial warranties the contractor gives to any customer for such supplies or services and that the rights and remedies provided therein are in addition to and do not limit any rights and remedies provided to the Government by any other clause of this contract. The contractor shall collect all written warranties and equipment manuals and deliver them to the Government.
The contractor further warrants to the Government that all materials and equipment furnished under this contract will be new, unless otherwise specified, and that all work will be of good quality, free from improper workmanship and defective materials and in conformance with the drawings and specifications. The contractor agrees to correct all work performed under this contract which proves to be defective in material and workmanship within a reasonable time as determined by the Government and the contractor and at no additional cost to the Government.
b) Contractor to provide a two week look ahead every Monday from Award of Project-to-Project completion to include the following: 1) Two –Week Look Ahead, 2) Scheduled Deliveries for the next two weeks, and 3) Tentative project completion date and any issues pending.
c) Contractor to notify the COR via email of any Request for Information five working days before an answer is required.
4. GOVERNMENT-FURNISHED EQUIPMENT AND GOVERNMENT-FURNISHED INFORMATION
The contractor is authorized to use on a no-charge basis, in the performance of the contract, the Government-owned facilities as identified below:
1. Restrooms
2. Utility lines
3. Space for storage of materials and equipment as authorized by the Contracting Officer's Representative.
All hose extension, wiring, etc., required for connection for utility lines shall be furnished by the
Contractor.
5. PLACE OF PERFORMANCE
The place of performance for this action is as follows:
Main Treasury Building 1500 Pennsylvania Ave, NW Washington, DC 20220
6. PERIOD OF PERFORMANCE
The period of performance for this requirement is one year after the Date of Award.
7. INSPECTION AND ACCEPTANCE
Completed work to be reviewed and inspected by Contracting Officer’s Representative.
8. WORK HOURS
The contractor is not required to perform services on the following holidays: Federal holidays are set by law (USC Title 5 Section 6103). Under current definitions, four are set by date:
New Year's Day January 1
Independence Day July 4
Veterans Day November 11
Christmas Day December 25
The following Federal holidays are set by a day of the week and month:
Martin Luther King's Birthday Third Monday in January
Washington's Birthday Third Monday in February
Memorial Day Last Monday in May Juneteenth Third Monday in June
Labor Day First Monday in September
Columbus Day Second Monday in October
Thanksgiving Fourth Thursday in November
HOURS OF OPERATION:
The contractor is responsible for conducting business between the hours of 7:00 am to 3:30 pm, Monday through Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government direct facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must always maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce is essential.
The Contracting Officer may adjust these working hours at the request of the COR in the best interest of the Government.
9. SECURITY
All workers must be US Citizens.
Access and Property Control at Property Location:
(a) Property control: All property being removed from the Treasury Department is subject to inspection by security personnel. Property cannot be removed from the premises without a complete Treasury
Property Pass.
(b) Existing Building Alarm Systems: The Contractor shall notify the COR prior to disturbing any alarm wiring, device, system, etc. The Contractor shall coordinate planned disturbances at least two working days in advance of the scheduled work. Any alarm wiring, devices, or system that is broken or disturbed for any reason must be reported to the COR. If any system or component is damaged by Contractor employees, the Treasury Department, Administrative Operations Division Security, Safety and Parking
Officer will determine the procedures for repairing the work. The cost to repair the system and any related overtime costs for Treasury Department personnel shall be borne by the Contractor.
(c) Parking: There will be no parking available at the Annex Building. Treasury will only clear vehicles for delivery and pickups.
(d) Deliveries: All deliveries shall be scheduled no less than 25 hours in advance. An Access form must be filled out and emailed to FacilitiesServiceDesk@treasury.gov unless otherwise noted on the form.
(e) Ingress/Egress during off-hours is restricted; once in…you are locked in, once out…you are locked out.
(f) For non-routine circumstances, with 25 hours advance notice, request special ingress/egress arrangements as needed from COR.
Material Delivery Process
a) Access Form to be submitted to Treasury COR with 25 hours advance notice. The electronic
Access form is to be e-mailed to FacilitiesServiceDesk@treasury.gov. and COR.
b) All deliveries must go to the Remote Delivery Site (RDS) for vehicle inspection and scanning.
JBAB Visitor Center
256 McGuire Ave.
Washington, DC 20032
Hours of Operation:
Monday-Friday (6AM-2:30PM) by appointment only through COR before coming to Treasury.
mailto:FacilitiesServiceDesk@treasury.gov mailto:FacilitiesServiceDesk@treasury.gov
The truck will then be escorted by USSS to the Treasury Complex, where it may be canine swept and/or EOD inspected.
c) Materials may or may not require further inspection at the building entrance. It is a judgment call from the UD Officer at the Post.
d) All deliveries that shall be made to the Treasury are to be made during normal working hours, unless special arrangements have been approved by the COR.
e) Deliveries shall be unloaded in a timely responsive manner, so as not to cause congestion in the
Moat or alley.