SOW MRY Bathroom as of 23MAR2022.pdf
PDF 222 KB Posted
- Attached to
- Renovation of First-Floor Bathroom Federal contract opportunity
- Solicitation number
- 02648
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MRY New Layout 08062021 visio w-stacked tile labeled 001.pdf | ||
| Market Survey.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FAALC Enhancement Program 2475 Henderson Way Monterey, CA 93940
STATEMENT OF WORK
MRY
Monterey, CA
PURPOSE: FAALC Enhancement Program (Beautification).
STATEMENT OF WORK:
The contractor will provide labor, travel, permits/application fees, mobilization costs and tools for technicians to travel to the Monterey, CA – MRY site for the purpose of renovating first floor bathroom facility; Contractor will ensure compliance with ADA standards. All work shall be completed by a licensed contractor in the state of California and completed in accordance with local, state, federal and industry standard requirements. Contractor work schedule will have to be approved by local FAA POC (point of contact). Contractor will provide samples of paint, tile, grout, and fixtures to SSC and AT for approval. Paint will be matched as closely as feasible to current paint color(s) of the bathroom door trim, walls, and ceiling. Reference attached photo and drawings.
COVID Consideration(s): Contractor will follow all facility, local, state, and federal COVID protocols; utilizing entrance and exit point established by local FAA representative. Contractor will be required to create safe work area utilizing barriers and/or materials for separation based upon COVID protocols during execution of enhancement described in this document.
Scope of Work:
(a) Demolition:
1. 4” x 4” ceramic floor tile
2. 6” x 6” ceramic floor splash guard tile
3. Toilet “B”
4. Urinal “C”
5. Sink “D”
6. Toilet stall divider wall “E”
7. Hanging wall storage cabinet
8. Mirror
9. Entrance foyer wall “J”
10. Paper towel dispenser
11. Vent fan
12. Center ceiling light fixture
13. Vanity light fixture
14. Shelf next to sink.
15. Toilet seat cover dispenser
(b) Remediation:
1. Remove foyer wall “J”
2. Widen entrance door to 36” and to swing “I & L” (inward & left)
3. Repair water damaged wall below sink and urinal
4. Remove toilet stall wall “E”
5. Repair wall board and paint in hallway leading to bathroom from door change out
6. Change out center floor drain cover
(c) Install Work:
1. Install new 36” entrance door with ADA compliant hardware to swing “I & L” (inward and left) with inside lock
2. Install new 12” x 24” ceramic floor tile with 1/8” grout lines
3. Install new floor drain cover
4. Install new 3” x 6” subway tile to a height of 48” from floor with 1/8” grout lines
5. Install new comfort height toilet (ADA compliant)
6. Install new handicap grab bars
7. Paint interior walls and ceiling
8. Install new exhaust fan
9. Install new LED ceiling mount light fixture
10. Install new vanity mirror
11. Install new LED wall mounted light fixture above new vanity mirror
12. Install new touchless urinal
13. Install new handicap accessible sink
14. Install new touchless water faucet
15. Install new 24” x 96” wall storage cabinet
16. Install new touchless soap dispenser
17. Install new touchless paper towel dispenser
18. Install new toilet seat cover dispenser
19. Install new bag and coat hanging hooks on wall
20. Install new UNISEX Bathroom Sign
21. Install new Handicap Accessible Sign
LOCATION:
ATC Facility Monterey, CA Airport
Monterey, CA 93940
PERIOD OF PERFORMANCE:
Completion within 30 days from issuance of Notice to Proceed. Any deviation of the period of performance timeline will require the prior approval of the CO (contracting officer).
SECURITY REQUIREMENTS:
Approved entrance from facility manager. FAA personnel will escort contractor, sub-contractor, delivery, and vendor personnel while on site; contractor will arrange with FAA POC for delivery schedule and daily work schedule.
SPECIAL REQUIREMENTS:
Contractor will provide portable latrine and sanitation/wash station. Contractor will ensure regular servicing of portable latrine is performed.
The contractor will provide waste removal container and removal from site in accordance with local sanitary rules and regulations.
Local SSC/Stakeholder will contact EOSH representative to determine requirements and/or submittals that must be reviewed and approved prior to implementation. Demolition work will be performed at this site creating dust and debris in the ATC (Air Traffic Control) facility.
SUBMITTALS:
1. Warranty documentation on all newly installed equipment, fixtures, and furnishings.
2. Owner’s manuals for newly installed equipment, fixtures, and furnishings.
3. Disposal receipt will be required.
4. Provide “as installed drawings”.
https://www.airnav.com/airport/KMGM
| Scope of Work: |
| 1. 4” x 4” ceramic floor tile |