This is a Statement of Work (SOW) for repair services related to hydraulic hose replacement on a JLG 600AJ aerial lift for the U.S. Coast Guard Sector Key West. The contractor is responsible for providing all labor, supervision, materials, and equipment necessary to complete the replacement work at the specified location (100 Trumbo Road, Key West, FL 33040). The work is expected to commence no later than 5 business days after contract award, with an anticipated award date of September 18, 2026. This is a Small Business Set-Aside solicitation with a firm fixed price contract structure, utilizing simplified acquisition procedures under FAR Part 13. The NAICS code is 811310 (Commercial and Industrial Machinery and Equipment Repair and Maintenance), with a small business size standard of $12.5 million. Quotes must be submitted by 3 p.m. on September 4, 2026, to Jerry.Lopez@uscg.mil, with award expected within 10 business days of solicitation close. The applicable wage determination is 2015-4583, Revision 34, dated August 12, 2026.
The contract award will be made using a Lowest Price, Technically Acceptable (LPTA) evaluation criterion. A site visit is highly recommended to inspect the aerial lift unit prior to submitting a quote. The Department of Homeland Security, U.S. Coast Guard, is the contracting agency responsible for this requirement. No separate written solicitation will be issued beyond this combined synopsis/solicitation announcement (Solicitation Number 70Z02826Q0000082).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Fixed Price service Clauses Acquisition.GOV.pdf | ||
| 15-4583.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
FOR
U.S. Coast Guard Sector Key West 100 Trumbo Rd Key West, Florida 33040
GENERAL REQUIREMENTS
PART 1 – General:
United States Coast Guard Sector Key West is accepting proposals for qualified individuals or firms to replace the hydraulic hoses on one (1) JLG 600AJ aerial lift.
The existing hydraulic hoses have reached the end of their service life and require replacement to maintain safe and reliable operations of the equipment.
The POC’s are: Brett Foster, Phone: (305) 292-8756, email: Brett.A.Foster@uscg.mil OR Amanda Green, Phone: (305) 292-8708 email: Amanda.F.Green@uscg.mil
PART 2 – Location:
U.S. Coast Guard Sector Key West
BLDG 102
100 Trumbo Rd Key West, Florida 33040
PART 3 – Parts Required:
The contractor shall furnish all labor, materials, equipment, and incidentals necessary to complete the work, including but not limited to:
1. Approximately 400 feet of 3/8-inch hydraulic hose.
2. Hydraulic hose ends and adapters.
3. JLG-approved hose clamps and associated mounting hardware.
4. Shipping and delivery of all required materials.
5. Any additional fittings, seals, or miscellaneous hardware required to complete the installation.
PART 4 – Facility Operating Hours:
1. The facility shall remain in operation throughout the service. Contractor access to the service site shall be limited to the following: 8:00am to 4:00pm, Monday through Friday, excluding holidays. Access to the site shall not be permitted on the weekends without prior approval from the Contracting Officer in writing.
PART 5 – Security Requirements
1. Contractor shall provide a list of names for required personnel needing to access the base to the Coast Guard COR for access to the base.
2. Personnel will be required to first report to the NAS Boca Chica Security Office for an entry pass unless they already have base access.
3. All personnel shall present their ID and base entry pass to the security personnel at the entrance to the base for access.
PART 6 – Contractor Responsibilities:
1. Remove and replace all hydraulic hoses from the tower boom knuckle to the man basket on one (1) JLG 600AJ aerial lift.
2. Install approximately 400 feet of new hydraulic hose with all required hose ends and adapters.
3. Replace all JLG hose clamps and associated hardware as required.
4. Ensure all hoses are properly routed, secured, and protected from abrasion or interference.
5. Inspect hydraulic fittings for leaks and verify proper torque specifications.
6. Refill hydraulic fluid as required and restore the hydraulic system to proper operating condition.
7. Perform functional testing of the boom, basket, and hydraulic systems to verify proper operation.
8. Clean the work area and dispose of removed materials in accordance with applicable environmental regulations.
9. Provide all tools, equipment, transportation, and labor necessary to complete the work.
PART 7 – Final Acceptance:
1. Contractor shall provide all required documentation and installation records.
1. Contractors shall coordinate and participate in a final walkthrough inspection with the designated representative.
1. Any deficiencies identified during the final inspection shall be corrected prior to acceptance.
1. Final acceptance will be granted upon successful completion of operational testing and verification that all hydraulic systems are functioning properly and are free of leaks.
Submittal of invoice(s) information will be provided once award of contract has been made.