SOW - Metering Project_041620.pdf

PDF 131 KB Posted

Attached to
Mechanical Construction Multiple Award Indefinite Delivery Indefinite Quantity (IDIQ) Contract Federal contract opportunity
Solicitation number
1333ND20QNB190030
Issued by
Department of Commerce National Institute of Standards and Technology

About this file

This document contains a statement of work and related federal contract opportunity solicitation. The statement of work outlines a project for the National Institute of Standards and Technology to install potable water meters and connect them to existing building automation systems in various buildings on its campus within 90 calendar days of receiving notice to proceed. The scope involves installing meters, connecting them electrically to automation systems, and completing associated electrical work. The related solicitation seeks mechanical construction contractors for an indefinite delivery/indefinite quantity multiple award contract with a one year base period and four ordering periods and a total contract value not to exceed $8 million per contractor. Task orders will range from $2,500 to $1.5 million for services such as repair, replacement and modification of piping, air conditioning, control, fire suppression and laboratory safety systems.

View the file

Other files for this federal contract opportunity

Other files attached to Mechanical Construction Multiple Award Indefinite Delivery Indefinite Quantity (IDIQ) Contract, newest first.
File Type Posted
Amendment 1 to 1333ND20QNB190030.pdf PDF
FormSF1442.pdf PDF
NIST - OFPM Guidelines for Contractors.pdf PDF
NIST Bldg 222 - Provide Demand Potable Water Meters Final.pdf PDF
Bid Sheet - 5 Buildings.pdf PDF
NIST Bldg 301 - Provide Demand Potable Water Meters Final.pdf PDF
NIST Bldg 101 - Provide Demand Potable Water Meters Final.pdf PDF
NIST Bldg 226 - Provide Demand Potable Water Meters Final.pdf PDF
MD20200043 Wage Determination.pdf PDF
SPECS - NIST Potable Water.pdf PDF
NIST Bldg 215 - Provide Demand Potable Water Meters Final.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

NIST DEMAND POTABLE WATER METERS

Background

As part of Executive Order 13834, NIST is required to provide information on domestic water usage. Previous orders had required reporting of other utility usage which NIST satisfied by installing utility meters at the building‐level and trending usage using the existing site building automation system.

Objectives

Trending domestic water usage at the building level to allow collection and reporting of data.

Scope

Installation of building‐level domestic water meters and connection to the existing building automation system.

Tasks

The Work of the Project is defined by the contract drawings (listed below) and specifications and consists of the following:

A. Installation of domestic water meters in select buildings on the campus, connection to the building automation system, and associated electrical work

B. Drawing List:

1. Building 101‐ Drawings 101‐1239 through 101‐1242

2. Building 215‐ Drawings 215‐462 through 215‐465

3. Building 222‐ Drawings 222‐787 through 222‐790

4. Building 226‐ Drawings 226‐425 through 226‐428

5. Building 301‐ Drawings 301‐401 through 301‐405

Delivery

The Contractor shall deliver a potable water meeting system meeting the requirements included on the Contract Drawings and Specifications within 90 calendar days after Notice‐to‐Proceed (NTP) is issued.

Submittal requirements shall be as indicated in the Contract Specifications.

Government‐Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, or GFI)

No Government‐Furnished material is anticipated for this contract.

Travel

No specific travel requirements are anticipated.

Special Material Requirements

Asbestos Material: If material is encountered that looks suspicious but must be disturbed, do not touch the material. The contractor shall immediately notify the COR in writing. If the material encountered is asbestos and must be handled, the Government shall be responsible for the removal.

Place of Performance

Various buildings on campus

Period of Performance

90 calendar days from issuance of NTP