SOW Installation of Oil Water Separator System.pdf
PDF 195 KB Posted
- Solicitation number
- Not on record
About this file
This Statement of Work (SOW) details the installation of an Oil Water Separator (OWS) system at Hush House No. 2, Mountain Home Air Force Base. The project requires a contractor to design, fabricate, install, and commission a 300 GPM OWS system that will handle wastewater from aircraft maintenance operations, ensuring compliance with EPA, DoD, and NPDES regulations. The system must achieve >99% hydrocarbon removal efficiency, with key specifications including corrosion-resistant tank construction, integrated sensors for oil accumulation detection, automatic sludge removal, and vapor control measures.
The SOW is structured in four phases: (1) Pre-Construction Planning & Submittals, involving design drawings and product specifications, (2) Site Preparation, including geotechnical surveys and excavation, (3) System Installation, covering tank, piping, and electrical components, and (4) Commissioning & Testing, which includes hydrostatic leak testing, flow capacity validation, and environmental compliance verification. The project has specific technical requirements conforming to UFC, EPA, NPDES, FAR, NFPA, and NEC standards. Contractor personnel must meet specific qualifications, including English fluency and base access requirements, with work to be completed Monday to Friday, 0700-1630 MST, excluding federal holidays.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page | 1 of 6
STATEMENT OF WORK CONSTRUCTION
PROJECT: Installation of Oil Water Separator System
LOCATION: Hush House No. 2, Mountain Home AFB
NEXGEN WT: 14118044
DATE: July 28, 2025
SCOPE OF WORK
General:
The contractor shall furnish all personnel, equipment, supervision, and materials necessary to design, fabricate, install, and commission a complete and functional Oil Water Separator (OWS) system that will be fully integrated into the existing facility infrastructure. This system must handle wastewater from aircraft maintenance operations, ensuring compliance with EPA, DoD, and NPDES regulations. Updating this facility to meet these standards will allow a more efficient and continuous way to test jets and their engines by reducing maintenance intervals between uses and reducing possible environmental hazards.
EXECUTION PLAN
Assess suitable area, excavate and install into existing facility infrastructure a 300 GPM OWS, that meets or exceeds any applicable regulations.
Phase 1:
Pre-Construction Planning & Submittals
1. Material and Design Submittals
a. Submit design drawings, product data, and specifications for but not limited to:
i. OWS system components
1. Capable of a flow rate of 300 GPM (Gallons per minute)
2. 99% Removal of free and dispersed hydrocarbons larger than 20 microns
3. Designed to allow gravitational and coalescing plate separation for optimal hydrocarbon phase separation.
4. Must meet or exceed 40 CFR Part 112 (Oil Pollution Prevention)
a. Must meet or exceed 40 CFR 122 (NPDES Permit
Regulations)
ii. Sensors and automation systems
Page | 2 of 6
1. Integrated sensors for real-time detection of oil accumulation beyond 15% tank volume threshold.
2. Smart alert for maintenance personnel when hydrocarbon level exceed environmental discharge limits.
3. Scheduled solids extractions and dewatering system to prevent sludge overloading.
4. Vapor-phase carbon adsorption units mitigate volatile organic compound (VOC) emissions.
5. Explosion-proof venting system for flammable vapor control.
iii. Coatings and structural materials
1. OWS tank will be made from corrosion-resistant steel, stainless steel (316L), or fiber reinforced polymer (FRP) tank construction to withstand exposure to JP-8, MIL-PRF-7808, MIL-PRF-83282, and MIL-PRF-23699 aviation-grade fuel and lubricants.
2. OWS interior will be epoxy-based, high-resistance coating for hydrocarbon and chemical exposure mitigation.
iv. Control system schematics
1. Will design, produce and implement working schematic of operating control system for OWS.
b. All products must meet FAR Buy American compliance.
c. All submittals are due within 20 calendar days of NTP.
2. Work Plan
a. Timeline with major milestones (mobilization, construction, commissioning)
b. Roles and responsibilities of project administration
i. During performance under contract, the contractor shall participate in administrative tasks inherent to the administration, surveillance, and oversight
c. Role and Resume of Contract Employees
i. All contract personnel must be able to read, write, speak, and understand
English fluently. Contract personnel shall present a neat appearance and be easily identified as a contract employee. The contractor shall obtain base identification, and vehicle passes for all employees who make frequent visits to or perform work on Mountain Home AFB in accordance with the current installation access/entry requirements. Contractor personnel are required to wear or prominently display installation identification while visiting or performing work on the installation. The contractor shall not employ persons for work on this contract, identified to the contractor by the CO as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population. Each employee will be easily identified by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges that contain
Page | 3 of 6 the company name and employee name(s). The contractor shall not employ any person who is an employee of the Government, if employing that person would create a conflict of interest. The contractor is cautioned that off-duty active military personnel hired under this contract may be subject to permanent change of station, change in duty hours, or deployment. Military Reservists and National Guard members may be subject to recall to active duty. The abrupt absence of these personnel could adversely affect the service provider’s ability to perform; however, their absence at any time shall not constitute an excuse for non-performance under this contract.
d. Safety protocols and training certificates (OSHA 30, HAZMAT, etc.)
3. Disinfection and Commissioning Plan
a. Methodology for system flush-out
b. Hydrostatic and operational testing strategy
i. Hydrostatic Testing: Verify tank integrity with 72-hour static water load test.
ii. Flow Capacity Testing: Confirm compliance with designed flow rates.
iii. Oil Separation Efficiency Testing: Conduct controlled hydrocarbon injection test and measure separation performance against EPA Method
1664 (IF APPLICABLE)
Phase 2:
Site Preparation
1. Geotechnical Survey
a. Verify subgrade strength and drainage profile
b. Determine suitability for OWS weight and excavation impact
i. Conduct geotechnical soil analysis to determine subsurface stability and load-bearing capacity.
2. Excavation & Ground Stabilization
a. Ensure maximum water level is below required frost depth per UFC 3-240-04A
i. MHAFB frost depth is 32”
b. Ensuring a minimum of 48-inches of clearance below the frost line. Install compacted crushed stone base or reinforced slab based on Geotech results
Phase 3:
System Installation
1. Tank and Mechanical Components
a. Install corrosion-resistant tank system (316L SS or FRP)
b. Internal epoxy coatings per hydrocarbon exposure spec
Page | 4 of 6
c. Integrate internal separation and retention system
2. Hydraulic & Piping Network
a. Schedule 80 PVC/stainless piping with 0.5–1% gravity grade
i. Prevent degradation due to petroleum-based products and wastewater, to include hydraulic fluids, jet fuel (JP-8, JP-10, etc.), grease, oils, soaps, and detergents.
b. Install pre-filtration debris screen and auto shut-off valves
i. Screen mesh to be <100 microns in filtration, to capture foreign object debris (FOD), jet blast residues, and metallic particulates.
ii. Automatic inlet flow restrictors and emergency shutoff valves to regulate surge flow conditions during fuel spill events. Install double-wall piping in critical zones to mitigate potential leaks.
3. Electrical & Automation Controls
a. Class I, Div 2 electrical enclosures
i. Provide explosion-proof electrical enclosure in hazardous locations.
b. Remote monitoring and shutdown capability
i. Implement redundant fail-safe mechanism throughout the system, with the ability to pause, shut down and de-energize the entire system as needed.
c. Level sensors, VOC monitoring, and maintenance alerts.
i. Automatic Level & Hydrocarbon Detection Sensors:
1. Integrated sensors for real-time detection of oil accumulation beyond 15% tank volume threshold.
2. Smart alerts for maintenance personnel when hydrocarbon levels exceed environmental discharge limits.
ii. Automatic Sludge Removal System:
1. Scheduled solids extraction & dewatering system to prevent sludge overloading.
iii. Secondary Vapor Control Measures:
1. Vapor-phase carbon adsorption units to mitigate volatile organic compound (VOC) emissions.
2. Explosion-proof venting system for flammable vapor control.
Phase 4:
Commissioning & Testing
1. System Testing
a. 72-hour hydrostatic leak testing
i. Verify tank integrity with a static water load test.
b. Flow capacity validation (300 GPM)
i. Confirm designed flow capacity of 300 GPM
c. Oil separation test per Method 1664 (if applicable)
Page | 5 of 6
i. Conduct controlled hydrocarbon injection test and measure separation against stablished standards.
2. Environmental Compliance
a. Conduct NPDES compliance validation for effluent discharge quality.
b. Obtain final discharge permits and agency signoffs.
i. Secure necessary State-level discharge permits if applicable.
c. Submit compliance certificate to base CE and contracting office
3. Training & Documentation
a. On-site training for operator teams
i. Provide comprehensive operator training on system operation, emergency shutdown, and routine maintenance.
b. Submit “As-Built” drawings and O&M manuals
c. Provide 1-year no-limit commercial warranty
TECHNICAL CRITERIA
1. All work shall conform to the latest editions of the following standards:
a. UFC 3-240-04A (Oil Water Separator Design)
b. 40 CFR Part 112 and 122 (EPA Regulations)
c. NPDES Permit Requirements
d. Federal Acquisition Regulation (FAR) Buy American Compliance
e. NFPA and NEC standards for hazardous environment installation
f. Idaho State Environmental Codes
g. 01 57 19 Temporary Environmental Controls_MHAFB Env Spec 20220614
(Attachment 1)
GENERAL PROVISIONS
1. Work Authorization: All work must be directed in writing by the Contracting Officer.
Hours of Operation: Monday to Friday, 0700–1630 MST. Federal holidays excluded.
2. Emergency Contact Numbers:
a. Fire Department: 911
b. CES PM: Brad Newcomb – 208-828-2792
c. WFSM R&O SME: Donoso, Samuel SSGT – 208-828-4015
d. WFSM Shop: 208-828-6538
Page | 6 of 6
ACCEPTANCE CRITERIA
1. The OWS system will be deemed successfully installed and operational when it meets the following criteria:
a. Achieves >99% hydrocarbon removal efficiency under load conditions.
b. Passes all hydrostatic, flow rate, and EPA discharge compliance tests
c. It is fully integrated into the facility without leaks or disruptions
d. Meets all safety, operational, and documentation requirements