SOW-I10C Backup Generator.1.pdf
PDF 283 KB Posted
- Attached to
- Generator
- Solicitation number
- 1331L526NTIAGener
About this file
This is a Statement of Work (SOW) for the installation of a Generac 50 kW outdoor backup generator system at the Institute for Telecommunication Sciences (ITS) Table Mountain Advanced Communications Test Site in Longmont, Colorado. The project objective is to procure and install a Generac SG050NA 50 kW stationary outdoor backup generator powered by a 4.5L inline 4-cylinder engine with LP vapor fuel system, including a transfer switch and all necessary electrical, mechanical, and safety components. The installation must comply with NFPA 99 and 110 standards and provide backup power for critical laboratory loads during utility failures.
The scope of work encompasses site preparation and evaluation including load studies and code compliance verification; concrete pad preparation with vibration isolators and aluminum bottom cover plates; generator installation and fuel line connections with leak testing; electrical connections to a 120/208 VAC 3-phase 60 Hz system including a 125 Amp thermal-magnetic breaker and Power Zone Pro digital control panel; installation of a TX Series 200 Amp 3-pole transfer switch with utility voltage sensing; battery and heating system setup including a 110 AH Group 31 battery, 10 Amp charger, and 1500-watt block heater; exhaust and silencer system installation; alarm and remote monitoring setup; and comprehensive testing and commissioning. Deliverables include system installation reports, as-built drawings, wiring schematics, three copies of owner's manuals, and testing/commissioning documentation. The contractor must also test for asbestos and hazardous materials and prepare cleanup plans. Project phases span 8 weeks total, with the period of performance not to exceed 365 days from award. The system includes a standard 2-year limited warranty on the generator and 2-year basic warranty on the transfer switch. Place of performance is Table Mountain, 8600 N. 39th Street, Longmont, CO 80503, with work occurring in buildings B9, T6, and various locations on the site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ_TM Generator.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Installation of Generac 50 kW Outdoor Backup Generator with Transfer Switch and
Accessories
1. BACKGROUND
The Institute for Telecommunication Sciences (ITS) provides research and development support for the National Telecommunications and Information Administration (NTIA) by performing basic research in radio science that provides the technical foundation for NTIA’s policy development and spectrum management activities, as well as solving telecommunications challenges for other Federal agencies, state and local Governments, private corporations and associations, and international organizations. Additionally, ITS addresses emerging telecommunications, information technology, and security challenges and contributes to the creation of telecommunications standards that support the full and fair competitiveness of the U.S.
communications and information technology business sectors.
2. OBJECTIVE
ITS requires the purchase and installation of brand or equal Generac SG050NA 50 kW Stationary Outdoor Backup Generator powered by a 4.5L inline 4-cylinder engine with LP vapor fuel system. The installation includes all necessary electrical, mechanical, and safety components required for full compliance with applicable codes and best practices. The system is designed to provide backup power for critical loads in the event of utility failure, meeting NFPA 99 and 110 standards and maintaining operational continuity. A backup generator be installed with a transfer switch at building I10C Table Mountain Advanced Communications Test Site. This building serves as a laboratory supporting a variety of telecommunications research projects.
Generac, Industrial Generator, 50kW/Gaseous / 4.5L Base Model # SG050 _ Variant #SG050NA 50 KW Gaseous Genset Features & Benefits Spark-Ignited Engine Powerzone Controller Generator Enclosure Industrial Alternator Model SG050NA Fuel Type: Gaseous Engine Type: 4-cyl in-line Engine Size (Liters):4-5 Engine Output (KW): 50 Running Watts (W): 50000
3. Scope of Work
3.1 Site Preparation and Evaluation
• Conduct a detailed site survey to evaluate the generator’s proposed location.
• Perform a load study on building.
• Verify compliance with local codes and regulations, including required setbacks and noise ordinances.
• Confirm adequate ventilation and exhaust clearance to prevent overheating and ensure safe exhaust dispersion.
• Verify structural adequacy of the concrete pad, ensuring compliance with seismic requirements per IBC Seismic Certified standards.
• Purchase Generac SG050NA 50kW backup generator.
3.2 Concrete Pad and Mounting
• Prepare and level the ground for concrete pad installation.
• Pour reinforced concrete pad to specified dimensions with appropriate depth and load-bearing capacity to support generator weight and vibration.
• Install Pad Vibration Isolators and secure generator to the pad using vibration-resistant anchor bolts.
• Install Base frame Bottom Cover Plates (Aluminum) to prevent rodent ingress and ensure airflow control.
3.3 Generator Installation and Wiring
• Position and secure the Generac 50 kW Outdoor Backup Generator on the concrete pad.
• Connect all fuel lines to the LP vapor fuel system using flex fuel hose with appropriate pressure ratings.
• Ensure all fuel connections are sealed, tested for leaks, and comply with NFPA 110 fuel system requirements.
3.4 Electrical Connections
• Connect generator output to the 120/208 VAC, 3-phase, 60 Hz electrical system.
• Install MLCB 125 Amp Thermal-Magnetic Breaker with 80% rating, including shunt trip and auxiliary contacts for enhanced fault protection.
• Integrate Power Zone Pro Digital Control Panel with dual-core digital microprocessor and ensure communication via RS485, Ethernet, and CANbus ports.
• Configure 2-wire start circuit for connection with the transfer switch.
3.5 Control Panel and Monitoring Setup
• Install and configure Power Zone Pro Digital Control Panel with:
o 4.3” Resistive Color Touchscreen (IP65 front) o Auto/Manual/Off Key Switch o Alarm Indication with Audible Alert o Emergency Stop Switch
• Enable web server connection through Power Zone Gateway for remote monitoring and diagnostics.
• Configure programmable I/O and built-in PLC to handle special application requirements.
3.6 Transfer Switch Installation
• Install TX Series 200 Amp, 3 Pole Transfer Switch with 2-wire start circuit.
• Configure Utility Voltage Sensing and Logic Controls with:
o Adjustable Drop-out and Pick-up o Minimum Standby Voltage and Frequency o Engine Warmup and Cooldown Timers o Transfer on Exercise Option
• Mount NEMA 3R Enclosure securely with pad-lockable controller cover for weather protection.
• Perform wiring and commissioning of Double Set of Form C Auxiliary Contacts and Enclosure Heater to maintain optimal operating conditions.
3.7 Battery and Heating System Setup
• Install 110 AH, 925 CCA Group 31 Battery with secure battery rack.
• Connect 10 Amp NFPA 110-compliant Battery Charger and 1500-watt Block Heater for optimal cold-weather performance.
• Add Battery Heating Pad to ensure reliable starting in sub-zero conditions.
3.8 Exhaust and Silencer System
• Install Critical Grade Silencer with appropriate exhaust piping, ensuring compliance with noise reduction standards.
• Route and secure exhaust piping to minimize back pressure and optimize airflow.
3.9 Alarm and Remote Monitoring Setup
• Install and configure:
o 8 Function Alarm Relay Panel for generator protection o 21 Light Remote Annunciator for surface mount o Remote Emergency Stop Switch (flush mount) in a strategic and easily accessible location
3.10 Final Inspection and Testing
• Conduct comprehensive load and operational tests to ensure system functionality and performance.
• Validate system compliance with UL6200, NFPA 99/110, and IEC801 standards.
• Verify fuel supply, electrical connections, control panel functionality, and fault protection alarms.
4. TASKS
• The contractor shall test for asbestos and prepare a plan for cleanup.
• The contractor shall test for hazardous material inside bunkers and prepare a plan for cleanup on Table Mountain.
• System Installation Report:
o Detailed report on site preparation, equipment placement, wiring, and system integration.
• As-Built Drawings and Schematics:
o Provide wiring diagrams and schematics highlighting all major components and connections.
• User Manuals and Documentation:
o Deliver 3 copies of Owner’s Manuals and training materials.
• Testing and Commissioning Report:
o Document system performance, fault testing, and verification of safety controls.
5. Compliance and Safety Standards
• NFPA 99 and 110 compliance for life safety systems
• UL 6200 and cETLus listing
• CSA C22.2 No. 178 compliance
• IBC Seismic Certification and Pad Compliance
• EPA Certified Emissions Control
6. Warranty and Support
• Generator Warranty: Standard 2-Year Limited Warranty
• Transfer Switch Warranty: Standard 2-Year Basic Warranty
• Provide technical support and on-site assistance during commissioning and initial operational period.
7. Project Timeline
• Phase 1: Site Survey and Preparation (2 weeks)
• Phase 2: Concrete Pad and Mounting (1 week)
• Phase 3: Generator Installation and Fuel System Connection (2 weeks)
• Phase 4: Electrical and Control Panel Integration (1 week)
• Phase 5: Transfer Switch and Ancillary Equipment Installation (1 week)
• Phase 6: Final Testing, Inspection, and Commissioning (1 week)
8. Acceptance Criteria
• Successful completion of load and functional tests
• Compliance with safety and performance standards
• Approval by relevant authorities and stakeholders
9. Project Closeout and Handover
• Final walkthrough with client and submission of As-Built documentation
• Training session for system operators on maintenance, troubleshooting, and monitoring
• Certification of compliance and project completion
10. Diagrams and Schematics
• Electrical Wiring Diagram
• Site Layout Plan
• Generator and Transfer Switch Connection Schematic
11. Budget and Cost Estimate (To be provided separately based on site conditions and procurement pricing)
12. PLACE OF PERFORMANCE:
Prior coordination is required to gain access to the site. The West gate to Table Mountain is located at 8600 N. 39th Street, Longmont, CO 80503.
• See map below for location.
• Latitude 40°07’50.89 N, Longitude 105°15’46.84 W
• The work will take place in buildings B9, T6 and at various locations on Table
Mountain.
13. PERIOD OF PREFORMANCE:
The period of performance shall start at the time of the award and not exceed 365 days after award.