This Statement of Work details guy tensioning requirements for Federal Aviation Administration (FAA) and U.S. Forest Service (USFS) guy towers, specifically at the Huger Repeater site in Francis Marion and Sumter National Forest (33°7'9.64"N, 79°46'49.02"W). The work encompasses implementing guy system tensioning, performing minor guy system repairs, and installing new grounding on guys and guy anchors of identified USFS tower assets.

The contractor must provide all tools, equipment, materials and expertise to complete specific tasks including: tensioning guyed wires to TIA-222 Rev. H specifications, performing corrosion abatement, installing safety wires at anchor points, replacing a broken guy wire marker ball, replacing a turnbuckle on leg A, clearing vegetation around guy anchors, and installing an above-grade ground system meeting NFPA 780 and TIA-222 standards. The project requires completion within 30 days of notice to proceed, with a preliminary schedule due 10 days after award and final schedule two weeks before work starts. Deliverables include a remediation plan, test data for tensioning, photographic documentation of below-grade work, and a complete documentation package within 30 days of site completion.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Guy Tensioning

For

Federal Aviation Administration and U.S. Forest Service Guy Towers

PREPARATION DATE: 1/16/2024

AJW-L533

1. Introduction and Overview

This Statement of Work will be issued in support of the United States Forest Service (USFS) mission to sustain the health, diversity, and productivity of the nation’s forests and grasslands to meet the needs of present and future generations. The initiative will focus on addressing systemic maintenance and critical infrastructure issues afflicting the USFS tower inventory and their ability to support mission critical activities. The contracting entity will serve independently to provide technical, and logistics services to support the Federal Aviation Administration (FAA) in the efforts detailed within this scope of work.

2. Scope of Work

The scope of work will encompass the implementation of guy system tensioning, minor guy system repair required for tensioning and new grounding installed on the guys and guy anchors of all identified USFS tower assets. Tensioning, minor repairs, and grounding shall be performed to meet applicable standards on each identified structure. Selected contractor(s) shall provide all necessary tools, equipment, material, and technical expertise to complete this effort:

a. System Types: Guyed lattice-based communication towers, guyed lattice-based fire watch/lookout towers, guyed lattice-based research towers.

b. Minor Repair: Correction of guy system and tower deficiencies are identified below in site specific requirements.

c. Grounding: A waterfall ground lead shall be installed on each guy wire near ground level. Each anchor shaft or fan plate shall also be bonded. The grounding leads shall be #2 tinned copper (stranded or solid). A new ground rod shall be installed in front of the anchor per applicable standards.

d. Facility Type:

Sole-Use: Stand-alone tower with communications building or box that is not attached to any other facility even if on the same land unit.

e. Site Specific Requirements:

Site - Huger Repeater

i. Tension each guyed wire to initial tension as specified in TIA-222 Rev. H.

ii. Perform corrosion abatement and control to each guyed wire anchor system.

iii. Install safety wire at each guy anchor termination point.

iv. Replace broken guy wire marker ball on leg C.

v. The guy wire turnbuckle on leg A, wire 1, has fewer than eight (8) threads showing on the inside. Replace turnbuckle and adjust the guy wire length to ensure proper tensioning.

vi. Clear soil and vegetation around the immediate area of the guy anchor, guy lanes and establish erosion control.

i. Install above grade ground system on tower and shelter to meet NFPA 780 and TIA-222 current addition.

Details and acceptations to above grade grounding installation.

1. Standard Conductor sizes: #2/0 AWG 133,100 Cir. Mils

2. Air terminal shall be installed no less than 6’ above the tallest antenna with an isolated lead rundown the tower and tied into the grounding system according NFPA 780. A rolling sphere design to support air terminal placement shall be provided and approved prior to installation.

3. Number of Down Conductors. At least two (2) down conductors shall be provided on any kind of structure, including steeples. NFPA 780 5.4 does not apply.

4. The target for the total ground resistance of this system is twenty-five

(25) ohms or less.

5. Ground rods shall not be less than 5/8 in. (12.7 mm) in diameter and 10 ft (2.4 m) long.

6. Ground connections shall be exothermic welds when possible or a non-reversible ground lug connection otherwise. Notable exceptions for exothermic welding, all above grade connections, tower legs, locations in dry or arid conditions with approval.

7. Ground rods that cannot be driven straight down, due to contact with rock formations, may be driven at an oblique angle of not greater than 45 degrees from the vertical or may be buried horizontally and perpendicular to the building, in a trench at least 762 mm (30 in.) deep.

8. The interconnection of the lightning protection system grounding electrodes and other grounded media shall be in the form of a ground loop conductor.

9. Each leg of a self-supporting tower shall be bonded to the tower ground ring using grounding conductors of 35 mm2 csa (#2 AWG) or coarser, bare, solid, tinned, copper conductor. Connection method shall be manufacturer or engineer approved.

10. The tower ground bus bar shall be connected to the tower grounding electrode system with a 35 mm csa (#2 AWG) or coarser, bare, solid, tinned, copper conductor.

11. Provide As-Built drawings of ground system.

vii. Secure waveguide/cable to tower at (3) ft. intervals where not currently attached with appropriate hangers.

viii. Perform corrosion abatement and control on all visually identifiable spots of corrosion throughout the tower and guyed system.

ix. Hardware shall be replaced if above CSF-2. (Reference in sec. 4)

12. Iron, steel, or aluminum surfaces to be coated shall be clean, i.e. devoid of grease, oil, mill scale, oxidation, loosely adherent rust, paint, etc. to SSPC (Steel Structure Painting Council).

13. Grease and Oils - Solvent clean to SSPC-SP1.

14. Rust scale or easy to remove paint - Power tool and hand tool clean to

SSPC-SP3.

15. The coating shall be applied at sufficient wet film thickness to achieve a minimum dry film build of 2.5 - 3.5 mils, using manufacturer's recoat time directions.

ii. Replace broken antenna mount on leg A at 227’ with industry standard equipment.

iii. Install rail type climbing system in accordance with OSHA 1926.1053(a)(22)

iv. Perform tower mapping on structure.

2.1. Location of Work

Region Forest Forest Name

Site Name Site Latitude

Site Longitude

08 12 Francis Marion and Sumter Huger Repeater

33°7'9.64"N 79°46'49.02"W

2.2. Schedule

The Contractor is required to submit a preliminary schedule 10 days after award for the project executed under this SOW for Government approval and submit a final schedule two (2) weeks prior to start of work. This project shall be completed within 30 days of receiving notice to proceed.

Contract Award Post Award Conference Deployment Readiness Review Mobilization Field Work Start Testing Field Work Finish Clean-up, Site Restoration

2.3. Site Access

The Contractor shall provide a schedule for staging of equipment and materials, and installation. Site access will be made available to the Contractor by FAA and the USFS. The assigned USFS radio technician can advise the contractor what types of vehicles may be necessary for traversing the area.

3. Government Equipment Security

a. Physical Security: The contractor shall be responsible for safeguarding all government property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.

b. Key Control: The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons.

4. Applicable Standards

a. OSHA (1910 and 1926)

i. Contractor shall follow all applicable standards, health, and safety practices.

b. ANSI-TIA 222 Rev. H

i. 7.6.1 Initial Tension. The initial tension in guys, for design purposes, at an ambient temperature of 60o F [16o C] shall be within upper and lower limits of 15 and 7 percent, respectively, of the manufacturer’s rated breaking strength of the strand. Values of initial tension beyond these limits may be used provided consideration is given to the sensitivity of the structure to variations in initial tension. The design ambient temperature may be adjusted based on site-specific data.

ii. 13.3.2 Guy Tensions. The maximum deviation from the design initial tension shall be ± 10% for guys up to and including 1 in. [25 mm] diameter and ± 5% for guys greater than 1 in. [25 mm] diameter, of the specified design initial tension at an anchorage, corrected

Statement of Work Power Installation for the ambient temperature.

iii. 7.4.6.1 Turnbuckies. Turnbuckles used to connect guy assemblies, shall be forged from

AISI grade 1030, 1035 or 1045 steel or equivalent, and suitably heat-treated (quenched and tempered, normalized or annealed).

iv. 10.4 Electrical Resistance & 10.5 Grounding Materials 10.5 Grounding Materials

c. NFPA 780

5. Metal Condition Guidance: Tower structural members, conduit, ladders, stairways, fastenerand all other components made from metal must be checked for deterioration and degradation in addition to standard member condition and in lieu of corrosion and proper protective coatings for metal members. The field guidance below is to be used to determine the appropriate compliance level with industry guidance from ANSI/TIA 222-G on material condition though the member may not physically denote large signs of distress, deterioration, and degradation.

i. 1st degree/CSF-1 distress, deterioration and degradation are minor as described below:

i. Corrosion – None

ii. Cracking – None

iii. Connection – Connection is in place and functioning as intended.

iv. Distortion - None

v. Settlement - None

vi. Erosion/Scour – None

ii. 2nd degree/CSF-2 distress, deterioration and degradation are moderate as described below:

i. Corrosion - Freckled Rust. Corrosion of the metal has initiated.

ii. Cracking – Crack has self-arrested or has been arrested with effective arrest holes, doubling plates or similar.

iii. Connections – Loose fasteners or pack rust without distortion is present but the connection is in place and functioning as intended.

iv. Distortion – Distortion not requiring mitigation or mitigated distortion.

v. Settlement – Exists within tolerable limits or arrested with no observed structural distress.

vi. Erosion/Scour – Exists within tolerable limits or has been arrested with effective countermeasures.

iii. 3rd degree/CSF-3 distress, deterioration and degradation are severe as described below:

i. Corrosion - Section loss is evident, or pack rust is present

ii. Cracking – Identified crack that is not arrested

iii. Connections – Missing bolts, rivets or fasteners; broken welds; or pack rust with distortion

iv. Distortion – Distortion that requires mitigation that has not been addressed

v. Settlement – Exceeds tolerable limits.

vi. Erosion/Scour – Exceeds tolerable limits but is less than the critical limits

6. Deliverables and Schedule of Delivery

a. Remediation plan shall be submitted with final schedule two (2) weeks prior to start of work.

b. Documents shall include a report of completed on sites activities, test data for tensioning before and after tensioning.

c. Schedule of pre-work and on-site activities is to be provided by the Contractor and accepted by

Statement of Work Power Installation the primary project POC.

d. Pictures shall be taken of all below grade work before, during and after excavation.

e. Post site completion all field reporting, images, and data packages are to be delivered to the

Primary Project POC within 30 days.

f. Pictures shall be taken of all below grade work before, during and after excavation.

g. Any final delivery of project documents shall be submitted in PDF format.

h. All required project documents have been provided to USFS and FAA and have been formally accepted.

i. All specified requirements have completed and accepted.