This Statement of Work (SOW) details the upgrade of Gas Turbine Engine (GTE) Test Cell Data Acquisition Systems at Hill Air Force Base, Utah. The project requires a comprehensive rehost of four test cells, involving the replacement of existing data acquisition units, computers, monitors, and associated hardware/software. Key technical requirements include upgrading to the latest ProTECS software version, adding capabilities such as LVDT position reading, improved EGT survey utility, enhanced load bank monitoring, and expanded signal processing for vibration and voltage measurements.
The contractor will be responsible for equipment removal, installation, training, and documentation, with specific deliverables including an Information Assurance plan, engineering data, commercial parts documentation, and a warranty certificate. The project involves two training sessions (8 hours for operators, 20 hours for engineers) and requires adherence to strict safety protocols. The contract includes provisions for a 2-year software functionality warranty, monthly status reporting, design reviews, and comprehensive data rights for the government. The upgrade aims to improve test cell performance, reliability, and maintainability while ensuring compatibility with existing test program sets.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 13820 - Combined Synopsis Solicitation Corrected.pdf | ||
| Solicitation - FA822825Q0011.pdf | ||
| GTE Test Cell Rehost CDRLs Portfolio.pdf | ||
| 13820 - Combined Synopsis Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GTE Test Cell Rehost
Hill AFB, UT
10 September 2025
Statement of Work (SOW) for
GTE Test Cell Rehost Upgrade
Prepared by:
COMMODITIES SUPPORT MAINTENANCE GROUP
309TH CMXG
HILL AFB UT 84056
TABLE OF CONTENTS
1. SCOPE
1.1. Scope
2. APPLICABLE DOCUMENTS
2.1. Government Documents
2.2. Other Government Documents, Drawings, and Publications
2.2.1. The Government will provide the current set of drawings to the contractor
2.3. General Industry Publications
2.4. Order of Precedence
3. REQUIREMENTS
3.1. Upgrade Data Acquisition System
3.2. Corrections and Additions
3.3. Program Management
3.3.1. Program Manager
3.3.2. Monthly Status Report
3.3.3. Conferences and Program Reviews
3.4. Removal of Existing Equipment and Installation of New Equipment
3.4.1. Equipment Removal
3.4.2. Equipment Installation
3.4.3. Equipment Provided by Contractor
3.4.4. Equipment Provided by Government
3.4.5. Facility Modifications
3.4.6. Tools and Equipment
3.4.7. Shipping
3.4.8. Removal and Installation Impacts
3.5. Training
3.6. Information Assurance (IA)
4. DOCUMENTATION
4.1. Operation and Maintenance Manual for Test Stands
4.2. Engineering Data
4.3. Commercial Parts
4.4. Calibration Quality Standard and Traceability
4.5. Acceptance Test Plan and Report
4.6. Physical Configuration Audit
4.7. Computer Program Identification Number (CPIN)
5. DATA DELIVERABLES
6. AVAILABLE FACILITY SERVICES
7. ACCESS TO FACILITIES AND PROPERTY
8. SAFETY
9. DATA RIGHTS
10. WARRANTY
10.1. Warranty period
10.2. Replacement of defective parts or software
10.3. Warranty certificate
Appendix A
Appendix B
1. SCOPE
1.1. Scope. This Statement of Work (SOW) defines the tasks associated with Rehosting the Gas Turbine Engine (GTE) test cells with new data acquisitions systems. This tasking includes all associated hardware and software, including computer systems that serve as HMI (Human Machine Interface) and data storage and handling systems.
2. APPLICABLE DOCUMENTS
2.1. Government Documents.
2.2. Other Government Documents, Drawings, and Publications.
2.2.1. The Government will provide the current set of drawings to the contractor.
Table 2 Drawings
DRAWING NUMBER CAGE
CODE NOMENCLATURE
8047 Current drawing package
2.3. General Industry Publications. All work shall conform to the following:
2.3.1. NFPA 70: National Electric Code (NEC), latest edition
2.3.2. 29 CFR 1910 Occupational and Health Administration (OSHA) General Industry Regulations
2.4. Order of Precedence. In the event of a conflict between the text of this document and the references cited herein, the text of this document takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained.
3. REQUIREMENTS
3.1. Upgrade Data Acquisition System. The Contractor shall upgrade the Data Acquisition system to the latest version of software and hardware platform that they deem to be the best fit for performance, Reliability, Accessibility and Maintainability (RAM). The system will maintain all of the features and capabilities of the existing system and include new features and capabilities outlined in this SOW.
3.1.1. A new computer for each test cell shall be included and running the latest supportable versions of ProTECS and Windows.
3.1.2. The Contractor shall supply all the needed computer monitors.
3.1.3. The engine bay monitor shall be replaced with a ruggedized (20” minimum) monitor appropriate for the fuel and oil environment.
3.1.4. The contractor shall supply one spare DAQ controller if applicable.
3.1.5. The contractor shall supply one spare computer.
3.1.6. Each test cell shall be capable of running all current Test Program Sets (TPS) on ProTECS software.
3.2. Corrections and Additions. The system shall include the following corrections and additional features.
3.2.1. The contractor shall provide a channel that can accurately read a Linear Voltage Differential Transducer (LVDT). The contactor shall add this capability to the system so an Inlet Guide Vane position reading can be obtained. The accuracy must meet the requirement of ± 1.5 °.
3.2.2. The Exhaust Gas Temperature (EGT) Survey utility used in the F22 TPS (Cell
3) has deficiencies. The purpose of this utility is to remove an exhaust EGT channel reading from the average if the value looks unreasonable, for example an open T/C. It is allowable to have two sensor readings out of the EGT average at a time. It appears that if more than two probes read higher than the set limit it disables all channels. To reset the utility, the program must be exited and restarted to get EGT readings again.
The contractor shall modify this utility so it will continue to read all EGT Channels even if more than two EGT readings are out of range but alert the operator that a requirement has not been met. This non-compliance shall be captured by the TPS and shown in the test report as a failed requirement.
3.2.3. There are power requirements for generator load on the 85 series engines.
Currently there is no monitoring to ensure the expected power is being applied. Since the load bank has no monitoring, the load on a phase could fail and there would be no indication. The contractor shall upgrade the system to read voltage and current on all phases, so the true kilowatt load can be calculated. An alarm condition shall notify the operator if the load value is out of range. This condition shall be captured by the TPS and reported as a failure.
3.2.4. Calibration Utility
3.2.4.1. In cases where a sensor is calibrated off the stand and correction offsets are entered by way of a table there is no capture of that event that shows the calibration dates. Examples of this are flow meters and vibration sensors. The contractor shall add a feature that allows calibration dates of sensors to be entered into the system, so technicians get a notice when the due date is approaching.
3.2.4.2. The system shall notify an operator when a calibration due date is approaching and not allow a test to run if any calibrated channels are past their due date. This feature should be determined by log in privileges. An operator should not be allowed to run but an engineer should be allowed to run.
3.2.5. Currently speed control on the 85 series engines is done by bypassing fuel, this method has not always resulted in good speed control. The Contractor shall add capability to better control speed by controlling the air pressure to the fuel control.
This would consist of a voltage or current controlled air pressure regulator that would control air pressure directly to the fuel control.
3.2.6. C17 load bank control is currently done by way of a serial interface utility provided by the OEM (Original Equipment Manufacturer). It is problematic because it sometimes loses communication and doesn’t seem to be very robust. The contractor shall consider integrating this feature into ProTECS. This would consist of Digital outputs to control the various loads of the load bank. However, there are other features of the load bank that would have to be considered, such as voltage and current monitoring. Voltage and current monitoring are currently done through the Loadtec (OEM) utility, if a manual interface is chosen those parameters would have to be monitored another way. The contractor shall investigate the suitability of a direct acting control and monitoring of the load bank. The contractor shall inform the government of the best solution. The contractor shall then implement the recommended solution.
3.2.7. Contractor shall add Direct Current (DC) amperage measurement capability for monitoring what the current the Unit Under Test (UUT) engine is drawing.
3.2.8. The contractor shall add the capability for an operator to type a message and have it displayed on the test cell monitor to communicate with someone in the test cell.
3.2.9. Display current configuration data:
3.2.9.1. The computer program identification number (CPIN) must be visible for operators and technicians. The ability to display the CPIN was added to our current version of ProTECS after the original installation. It is displayed on the About tab. The CPIN number field is populated from a config file. The contractor shall ensure the upgrade retains the ability to display the CPIN and populate it from a config file. The current implementation is acceptable.
3.2.9.2. The Technical Order (TO) number for each UUT must be displayed to the operator. This could be accomplished by the same method as the CPIN or through the TPS message screens which is also acceptable. The contractor shall discuss the possible implementations with the government and implement the selected option.
3.2.10. The current version of the GTCP165 engine TPS monitors 4 EGT probes.
The contractor shall add capability for the system to read an additional 4 EGT channels for a total of 8. The scope of this task is software only, hardware implementation is not required.
3.2.11. Current signal conditioning cards for measuring vibration are general purpose voltage cards, it is likely that special purpose vibration processing hardware could improve the performance of vibration signal processing. There are advantages to having all hardware on the Data Acquisition (DAQ) so upgrading computers is easier.
The contractor shall investigate the best solution for vibration monitoring with an effort to host this function on the DAQ. The findings of this investigative effort shall be presented to the government, so an implementation method can be selected. The contractor shall implement the selected method. Additionally, the contractor shall retain all capabilities for vibration processing of the current systems.
3.2.12. The contractor shall review all signals read by the DAQ to ensure the hardware aligns well with sensor ranges, so calibration tolerances are easily met with suitable resolutions.
3.2.13. The GTCP165 engine employs a three-phase generator. It is a requirement to measure the voltage to ensure that all three phases are producing the same voltage within 10vac. It has been a challenge to make these measurements accurately through the system because of the interference of each phase on the other. These measurements are currently being accomplished with a hand help DMM. The Contractor shall incorporate a method to measure this phase-to-phase voltage accurately within the DAQ system.
3.2.14. The contractor shall provide a copy of the LabVIEW development suite of the same version used for the development of the software. (CDRL A001) This suite shall be licensed by a perpetual license and be transferable to the government. This software suite shall be installed on a computer that is identical to the ones used in the test cell. This computer will have the capability to be used as a development machine as well as a spare test cell computer. As such it should have all the software loaded to function in this capacity including ProTECS and any other needed software including any needed drivers.
3.3. Program Management
3.3.1. Program Manager. The contractor shall identify to the Government and maintain a single point of contact (Program Manager) for all matters under this contract. The contractor shall also ensure that all program management personnel assigned to the program shall be available, as required, to meet program objectives.
3.3.2. Monthly Status Report. The contractor shall submit a monthly status report, due by the 5th of every month, which shall cover actions to date as well as a projection of planned work for the remaining effort. Reports shall document tasks, issues, actions, and deliverables. Problem areas shall be identified with proposed solutions and outcomes. (CDRL A002)
3.3.3. Conferences and Program Reviews
3.3.3.1. Kick Off Meeting. The kickoff meeting shall take place within 7 business days of the contract award. This can take place via telecom.
3.3.3.2. Post Award Conference. The Government will convene a post-award conference with the contractor within 30 days after contract award. The Government will coordinate the actual date and time of the conference with the contractor. It is up to the discretion of the contractor if they want to make an onsite visit or participate by way of a telecom. The purpose of this conference will be to review the requirements of this SOW, CDRLs (to include DIDs), milestones and provide the opportunity to ask questions. This conference also allows the contractor to present possible design options.
3.3.3.3. Preliminary Design Review. The Contractor shall conduct a Preliminary Design Review (PDR) within 120 days after contract award. The design review may be held at Hill AFB or may be a telecom, this will be left to the contractor’s discretion. The purpose of the PDR is to allow government personnel to review the preliminary mechanical and electrical test equipment diagrams, preliminary software methodology (e.g. proposed architecture) and provide early feedback to the contractor. The contractor shall provide preliminary copies of the system diagrams, a proposed list of major components, and a description of the proposed software methodology. This information shall be e-mailed (or mailed on CD ROM) to the Government representative one week in advance of the conference. File transfer by way of DoD SAFE is an option as well. (CDRL A003)
3.3.3.4. Critical Design Review. The Contractor shall conduct a Critical Design Review (CDR). This review may be held at Hill AFB or a telecom at the contractor’s discretion. The purpose of the CDR is to perform a thorough review of the proposed system as well as technical manuals and drawing package to ensure that the contractor has understood the governments requirements. Actual work on the system should not take place until after the
CDR. (CDRL A004)
3.3.3.5. Technical Data Exchanges. Technical data exchanges may occur whenever needed by either party. These exchanges may be accomplished by way of DoD SAFE, email or CD/DVD depending on what is needed for file size and suitability.
3.4. Removal of Existing Equipment and Installation of New Equipment
3.4.1. Equipment Removal. The Contractor shall disassemble, remove, and palletize the existing equipment listed in Table 3-1. The palletized components shall be placed in a designated location within building 240. The contractor shall remove all unused equipment when replacing the existing equipment.
Table 3-1
Equipment to be removed Data Acquisition units
Associated computers and monitors All applicable wire and cables
3.4.2. Equipment Installation. The Contractor shall install the equipment listed in the table below.
Table 3-2
Equipment to be installed 4 New Data Acquisition units
4 New Computers and monitors All applicable wire and cable
3.4.3. Equipment Provided by Contractor.
Table 3-4
Equipment Provided by Contractor 4 New Data Acquisition Systems
4 Computer Systems including monitors Associated cables and interfaces 1 Spare computer with monitors
3.4.4. Equipment Provided by Government.
Table 3-5
Equipment Provided by Government Printers
The government will provide the OS and office software
3.4.5. Facility Modifications. The Contractor shall not make any facility structural modifications without prior written approval from the Government’s technical representative.
3.4.6. Tools and Equipment. The Contractor shall be responsible to furnish all tools required to remove existing equipment and install new equipment.
3.4.7. Shipping. The Contractor shall be responsible for shipping all required equipment to Hill AFB.
3.4.8. Removal and Installation Impacts. The contractor shall minimize impact to current test stand capability during the removal and installation processes. The contractor shall submit a removal and installation plan that allows for only one test cell to be down at a time. (CDRL A005) The contractor shall coordinate installation efforts with the Government to retain capability on priority workloads during the upgrade project.
3.5. Training. The Contractor shall provide the trainings listed in Table 3-6.
Table 3-6
Training Type Number of Hours Number of People Operator training 8 4
Engineer training of software 20 2
3.6. Information Assurance (IA). The following paragraphs layout the IA Management Plan.
3.6.1. IA Management. The contractor shall maintain appropriate IA management and incorporate tools into system software that provide DoD-approved malware protection/prevention and tracking in accordance with 115 AFI 33- 115_YOKOTAABSUP dated 6 May 2015.
3.6.2. IA Program. The contractor shall maintain a robust information assurance program that is detailed in a written Contractor’s Information Assurance Plan. (CDRL A006) The contractor shall perform a virus scan prior to all shipments addressing most current virus scanning software. A signed and dated certification from the virus scanning official that this action has been taken shall be shipped with the asset.
3.6.3. IA Reporting/Tracking. The Contracting Officer (CO) shall be notified upon discovery of any virus or malware associated with the equipment being procured. Be aware that an IA reporting/tracking process is mandatory for subject procurement.
Ensure the following:
3.6.3.1. Malicious Logic. In accordance with 115 AFI 33-
115_YOKOTAABSUP dated 6 May 2015, the contractor and 309 CMXG/EN shall promptly report any incident meeting the requirements as defined in paragraph 5.4, Incidents Defined, to the USAF and cooperate with USAF investigations. Affected assets shall be immediately quarantined. The contractor shall notify the CO by telephone within 24 hours upon verification of a virus. The contractor shall not perform any remedial action of affected USAF equipment without direction from the CO.
3.6.3.2. Malicious Logic Protection. The contractor shall ensure incoming and outgoing non-volatile storage devices, via utilization of human and technological preventative measures such as good cyber hygiene and virus scanning, are free of malicious logic. (AFMAN 17-1301, 10 February 2017, pp 5.4)
3.6.3.3. Removable Media. The contractor shall ensure all removable media devices (hard drives, thumb drives, CDs, etc.) are free of malicious logic before and after use. (AFMAN 17-1301, pp 5.12)
3.7. Life Cycle Sustainment. The overall system design (e.g. components, hardware, software, etc.) shall be reliable, accessible, and maintainable and allow the Government to competitively select service providers for all future repairs without involving the original manufacturer of the system. Wherever possible, the contractor shall use components that are commercially available, commonly used in comparable industry equipment, interchangeable with other brands, and competitively priced. The system design shall not require the Government or a Government contractor to perform any reverse engineering to make system repairs.
4. DOCUMENTATION
The Contractor shall provide the following documentation:
4.1. Operation and Maintenance Manual for Test Stands. Operation and Maintenance manuals shall be delivered for operation, maintenance, and any needed setup for the system. A 33K series TO is currently used for calibration of the stands. It is not anticipated that a commercial manual for calibration will be needed, but if there are enough changes that one is warranted, they shall provide this or consult with the government to update the existing TO to accomplish calibration.
4.2. Engineering Data. The contractor shall update all applicable items in the Technical Data Package (TDP) to reflect changes to the system. The TDP shall represent the approved, tested, and accepted configuration of the defined delivered item(s). TDP data includes, but is not limited to, Computer Aided Design (CAD) data, CAD models, model-based definition data sets, Gerber data, Master Bill of Materials (BOM) and parts list, schematics, wiring diagrams, assembly drawings, functional block diagrams and flowcharts, and equipment layout. The TDP shall provide the necessary design, engineering, manufacturing, testing and quality assurance requirements information necessary to enable the procurement and manufacture of an interchangeable item that duplicates the physical and performance characteristics of the original product without additional design engineering effort or recourse to the original design activity. For any third-party items procured for this effort, the contractor shall provide the OEM’s original nomenclature, key characteristics, and data sheets as part of the TDP. Vendor Item Control Drawings shall be used to specify the requirements for purchased items when such items have been approved for use in the design and are used without alteration, selection or source qualification (testing of an item prior to procurement action to ensure that it satisfies the specified requirements). (CDRL A007)
4.3. Commercial Parts. The Contractor shall provide commercial literature (i.e.
data sheets) for all major commercial off-the-shelf components (i.e. motors, flow meters, pressure transducers, power supplies, etc.). (CDRL A008)
4.4. Calibration Quality Standard and Traceability. The contractor shall ensure the developed system is capable of being calibrated and its calibration is verified in accordance with Air Force Metrology and Calibration (AFMETCAL) requirements. Calibration and measurement traceability shall be identified and documented in accordance with MIL-STD-1839D. MIL-HDBK-1839C shall be used for interpretive guidance to clarify requirements invoked by MIL-STD- 1839D. The contractor shall provide a means to perform calibration to meet these requirements. The contractor shall provide all proprietary/unique software and peculiar/special hardware required to perform calibration and calibration verification. The contractor shall inform the government of changes to the new system that will require calibration procedure changes.
4.5. Acceptance Test Plan and Report. The contractor shall provide an Acceptance Test Plan (ATP) that includes an Acceptance Test Report (ATR) provided in the contractor’s format in accordance with CDRL A004 and CDRL A005. This plan shall outline procedures for providing objective evidence that the new test equipment meets each requirement outlined in this purchase specification. This plan shall be provided to the Government representative 30 days in advance of the scheduled tests to allow opportunity for review and feedback. (CDRL A009)
4.6. Physical Configuration Audit. The contractor shall conduct a Physical Configuration Audit jointly with the Government chairing the audit. The Physical Configuration Audit shall verify the drawings reflect the “as built” configuration of all developed or modified portions of the hardware. A product baseline shall be established upon completion of and Government acceptance of the Physical Configuration Audit Plan. A complete preliminary copy of the drawing package (section 4.2) shall be delivered 15 business days prior to the Physical Configuration Audit (CDRL A0010)
4.7. Computer Program Identification Number (CPIN). The contractor shall request a CPIN number and implement it in the executive software such that the CPIN number and revision are visible to an operator or calibration technician. The contractor shall provide two copies of the install disk for the executive software. Each disc (CD or DVD) shall be labeled with the following information: CPIN number, Revision, Date, Classification, Units (e.g. 1 of 1, 1 of 2, etc.) and the Title. (CDRL A011)
5. DATA DELIVERABLES
The contractor shall provide a technical data package as stated in the table below.
Table 5-1
Deliverable CDRL Reference
LabVIEW and SDS computer A001 3.2.14 Monthly Status Report
A002 3.3.2
PDR Docs A003 3.3.3.3 Critical design review A004 3.3.3.4
Removal and Installation plan A005 3.4.8 Information Assurance plan A006 3.6.2 Product Drawings/Models and Associated lists
A007 4.2
Commercial Manual and Supplemental Data
C008 4.3
Acceptance Test Plan C009 4.5 PCA Drawings C010 4.6 PCA Report C011 4.7 Personnel List C012 7 Safety Program C013 8
6. AVAILABLE FACILITY SERVICES. The following facility services will be made available to the Contractor. It shall be the responsibility of the Contractor to route new piping, cables, conduit, hangers, insulation, etc. from the existing facility connection points.
If insufficient facility services are available, it shall be the responsibility of the Contractor to install and modify the facility after written approval from, and coordination with, the Government’s technical representative.
7. ACCESS TO FACILITIES AND PROPERTY. The contractor shall ensure the pass and identification items required for contract performance on Hill AFB are obtained for employees and non-Government owned vehicles. Contractor employees requiring escorted access will coordinate with the government. The contractor shall provide a list to the process engineer (PE) not less than 7 business days prior to the date access to the base is required.(CDRL A012) The list will be computer generated or typed and organized alphabetically by the visitor’s last name. The list will include last name, first name, driver’s license number, and state listed on license of all guests that will need access.
8. SAFETY. While performing work under this contract on Government Installations, the Contractor shall comply with the specific health and safety requirements established by this contract. Comply with the health and safety rules of the Government installation that concern related activities not directly addressed in this contract. Take all reasonable steps and precautions to prevent accidents and preserve the health and safety of contractors and Government personnel performing or in any way coming in contact with the performance of this contract.
The contractor shall implement a safety program plan that ensures protection of Government personnel and property as defined in appendix B. (Attached) (CDRL A013)
In the event of an accident/mishap on a Government Installation, the Contractor shall take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence. A written or email copy of the Mishap Report shall be sent within 48 hours to the PE, who will forward it to Ogden Air Logistics Complex (OO-ALC) safety office. (CDRL A007)
The Contractor shall create an Incident/Mishap report in the event of any of the following:
• A condition or material fault that is a hazard to personnel, equipment, and missions.
• Conditions which prevent proper operation of the equipment.
• When equipment does not perform to published, operational or maintain standards.
• When a contract employee causes damage to equipment.
• When a contract employee is involved in an accident or injury.
9. DATA RIGHTS. The contractor shall provide at least Government Purpose Rights for all software used in the test stands as part of this contract as asserted in any Data Rights Assertion Table, or if none, as described in the Statement of Work or elsewhere in the contract. The delivery of data and software as described in the Technical Data Package (TDP) and deliverables (CDRLs) shall include, but are not limited to all software, source code, CAD files, CAD models, schematics, wiring diagrams, Gerber files, and equipment layout. The contractor shall comply with those contract clauses and definitions with respect to the government rights in technical data and software and CDRLs shall conform with DFARS 252.227-7013 and DFARS 252.227-7014, including any other applicable contact clause referenced or intended to be referenced in the contract.
10. WARRANTY.
10.1. Warranty period. The contractor shall provide a written warranty certificate for each individual test cell. The warranty period shall commence at the date of final acceptance for each test cell. The warranty shall consist of two parts.
10.1.1. A warranty for parts and systems is equal to the OEM warranty length and terms.
10.1.2. A warranty from the prime contractor should cover software functionality and troubleshooting support for a minimum length of 2 years.
10.2. Replacement of defective parts or software. During each respective warranty period, the contractor shall be responsible for the replacement of any defective parts, systems or software, the failure of which is due to faulty materials, workmanship, design or inadequate service life. Components normally consumed during this period, e.g. filters, shall be excluded from this requirement. The contractor is not expected to come on site to replace a part or make a repair that could easily be done by government personnel through off-site support.
10.3. Warranty certificate. The warranty certificate shall describe in detail the terms and timeline of the warranty, as well as outline the process of making warranty claims and contain at a minimum, the following information:
a. Part numbers/serial numbers of the new components of the test systems
b. Contract number
c. Warranty starts and end date
d. The contractor’s contact information
e. Explanation of warranty coverage
APPENDIX A. ACRONYMNS AND ABBREVIATIONS
AFB Air Force Base AFMAN Air Force Manual
AFMETCAL Air Force Metrology and Calibration ATP Acceptance Test Plan ATR Acceptance Test Report CDR Critical Design Review
CDRL Contract Data Requirements List COR Contracting Officer Representative
CMRS Calibration and Measurement Requirement Summary CPIN Computer Program Identification Number DID Data Item Description DoD Department of Defense EGT Exhaust Gas Temperature FAT Factory Acceptance Test FCA Functional Configuration Audit FTP File Transfer Protocol GFE Government Furnished Equipment GTE Gas Turbine Engine IA Information Assurance
IDR Intermediate Design Review IUID Item Unique Identification NSN National Stock Number
OSHA Occupational Safety and Health Administration PCA Physical Configuration Audit PCO Procuring Contracting Officer PDR Preliminary Design Review SOW Statement of Work TBD To Be Determined
TMCR Technical Manual Contract Requirements TOC Table of Contents
USAF United States Air Force TPS Test Program Set UUT Unit Under Test
APPENDIX B -- SAFETY
SAFETY, FIRE PROTECTION AND HEALTH
SPECIFICATION
INDUSTRIAL SAFETY REQUIREMENTS
OGDEN AIR LOGISTICS COMPLEX
UNITED STATES AIR FORCE
HILL AIR FORCE BASE, UTAH 84056
29 July 2025
Reviewed by:
Robert Pickett
OO-ALC/SE
801-586-4461
Control Number: JJ252907
SECTION I - GENERAL REQUIREMENTS
A. Safety Program Requirements
The contractor shall implement a safety program plan that ensures protection of
Government personnel and property. The program shall consist of, as a minimum:
1. Mishap reporting, as defined in paragraph B1 below.
2. A Safety Plan that addresses, as a minimum, the subjects listed in Section II –Specific Requirements, and shall be used during the performance of the work described in the contract. The Safety Plan shall be approved by OO-ALC/SE (Safety Office) prior to commencement of any work described in this contract.
3. Routine and recurring surveillance to ensure the safety requirements of this contract are enforced.
4. Competent personnel to provide surveillance of the Safety Plan.
5. Identification of segregated work site locations for operations that cannot be co-mingled with general industrial operations and the process for ACO approval of operations and changes at these specific sites.
6. All contractor personnel shall be trained and qualified to perform their duties safely.
7. The contractor shall include a clause in all subcontracts requiring the subcontractors to comply with the safety provisions of this contract, as applicable.
B. Mishap Notification
1. The contractor shall notify the OO-ALC/SE Workflow (OO- ALC.SE.Workflow@us.af.mil) or the Hill AFB Command Post (801-777-3007) after normal duty hours, and the designated Government Representative (GR), i.e., the ACO, PCO, or DCMA QAR (Quality Assurance Representative) within one (1) hour of all mishaps or incidents at or exceeding $2,000 (material + labor) in damage to DOD property entrusted by this contract, even if the government is wholly or partially reimbursed. This notification requirement shall also include physiological mishaps/incidents. A written or email copy of ALL the mishap/incident notification shall be sent within three calendar days to the GR, who will forward it to OO-ALC/SE. For information not available at the time of initial notification, the contractor shall provide the remaining information no later than 20 calendar days after the mishap, unless extended by the ACO.
Mishap notifications shall contain, as a minimum, the following information:
mailto:ALC.SE.Workflow@us.af.mil
(a) Contract, Contract Number, Name and Title of Person(s) Reporting
(b) Date, Time, and exact location of accident/incident
(c) Brief Narrative of accident/incident (Events leading to accident/incident)
(d) Cause of accident/incident, if known
(e) Estimated cost of accident/incident (material and labor to repair/replace)
(f) Nomenclature of equipment and personnel involved in accident/incident
(g) Corrective actions (taken or proposed)
(h) Other pertinent information
2. The contractor shall cooperate with all government mishap investigations.
Additionally, if requested by government personnel or designated government representative (GR), i.e., the ACO, PCO, or DCMA QAR (Quality Assurance Representative), the contractor shall immediately secure the mishap scene/damaged property and impound pertinent maintenance and training records, until released by safety investigators.
3. The contractor shall provide copies of contractor data related to mishaps, such as contractor analyses, test reports, summaries of investigations, etc. as necessary to support the government investigation.
4. The contractor shall support and comply with the safety investigation and reporting requirements of DAFI 91-204, Chapters 1 – 5.
C. General Safety Requirements:
If the safety plan is modified, the contractor shall submit the proposed modification, in writing, to the Contract Administration Office safety representative.
The contractor is solely responsible for compliance with all federal, state, and local laws, the Occupational, Safety and Health Act (OSHA) (Public Law 91-596) and the resulting standards, OSHA Standards 29 CFR 1910 and 1926, as applicable, Air Force Occupational Safety and Health Standards (AFOSH STD), to include DAFMAN 91-203, Air Force Occupational Safety, Fire, and Health Standards, DAFI 91-204, Safety Investigations and Reports, Contract Safety, and the protection of their employees.
Additionally, the contractor is responsible for the safety and health of all subcontractor employees.
The contractor shall ensure assigned personnel are adequately trained and qualified for the task being performed. Brief all personnel on the hazards involved with operations and applicable precautions to be taken. Should unidentified hazards arise, cease operations until actions are taken to eliminate or mitigate hazards to safe levels.
Compliance with OSHA and other applicable laws and regulations for the protection of contractor employees is exclusively the obligation of the contractor. Note:
AFOSH STDs are annotated because many of the Air Force Standards exceed the OSHA standard criteria. If a conflict is noted, the most stringent requirement takes precedence.
The government shall assume no liability or responsibility for the contractor's compliance or non-compliance with such requirements. The contractor shall furnish to each of his/her employees a place of employment which is free from recognized hazards. The contractor shall brief his/her employees on the safety requirements of this contract and on hazards associated with prescribed tasks. The contractor is responsible for compliance with OSHA Public Law and the resultant standards identified within. In addition, the contractor is required to flow down the safety requirements/specification to all subcontractors. This applies to Federal Acquisition Regulation (FAR) 12 commercial acquisitions as well. This contract shall in no way require persons to work in surroundings or under working conditions which are unsafe or dangerous to their health.
The contractor must coordinate and perform work so as not to impact the safety of government employees or cause damage to government property. This requires providing personnel with protective equipment and associated safety equipment as may be necessary. The contractor must also protect personnel from hazards generated by the work. If the contractor employs BILINGUAL speaking employees, they must post bilingual signs and have written procedures for specific tasks in applicable languages.
SECTION II – SPECIFIC REQUIREMENTS
The contractor’s prepared Safety Plan shall:
• Provide contact information for on-site personnel
• Include a work hazard analysis of the worksite and operations to be performed to include baseline hazard identification and required control measures
• Identify employee safety and health training requirements and the documentation process
The contractor shall ensure that each element identified below is adequately addressed in detail in the safety and health plan:
PEDESTRIAN CROSSWALKS: All contractor personnel are required to use the closest crosswalk or traffic-controlled intersection when crossing the road. Pedestrians must look both ways to ensure the coast is clear before stepping out into the crosswalk.
Pedestrians DO NOT have the right of way unless they are already in the crosswalk.
Contractor vehicle operators have the same responsibilities as pedestrians to share the road and mutually observe and yield to pedestrians.
MOTOR VEHICLES: Contractor shall comply with the standards in: DoD Directive 5525.4, Enforcement of State Traffic Laws on DoD Installations", Nov 2, 1981, Para 3-4;
DODI 6055.4, DoD Traffic Safety Program, 20 Jul 99; AFI 91-207, USAF Traffic Safety Program, 22 May 07; Each applies to all persons at any time on an Air Force Installation and includes all leased, owned, or privatized property including housing areas. In addition: AFI 13-213, Airfield Management, 29 Jan 08, Paragraphs 1.3.6 and 4.4.2.1 applies to all contractors, sub-contractors, vendors, commercial delivery companies, and all other private business vehicles who operate anywhere on Hill Air Force Base, including the airfield (to include the industrial areas and any buildings or hangars located upon the airfield) in support of their mission.
HOUSEKEEPING: Housekeeping shall be conducted according to the requirements in OSHA Standard 29 CFR 1910.141. CLEAN AS YOU GO will be enforced.
| 1. SCOPE |
| 2.2. Other Government Documents, Drawings, and Publications. |
| 2.2.1. The Government will provide the current set of drawings to the contractor. |
| 3. REQUIREMENTS |
| 4. DOCUMENTATION |
| 5. DATA DELIVERABLES |