This Statement of Work (SOW) details the installation of a Deister Access System entrance gate at Grand Teton National Park (GRTE) by a contractor. The project requires comprehensive project management, quality control, and technical oversight, including a dedicated project manager, quality control team, and a lead low voltage technician. The contractor must provide all necessary personnel and tools for installation, with all travel expenses, operational costs (water, power, fuel), permits, fees, and licenses included in the bid cost.
Key project specifications include performing work during regular business hours (Monday-Friday, 7 AM - 5 PM), adhering to National, State, and local codes, and using existing or pre-planned raceways. No materials are to be ordered or work performed without a customer purchase order or notice to proceed. The solicitation is issued by the Department of the Interior National Park Service Intermountain Region, with the solicitation number 140P1425Q0092, focusing on a turnkey installation of the customer-provided access system at the park's entrance gate.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P1425Q0092.pdf | ||
| B03_Wage_Determinations_2015-5409_rev_07082025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GRTE Granite Gate Installation - Statement of Work Contractor shall meet all the following requirements:
Installation of customer provided Deister Access System for entrance gate. The contractor shall provide\provision as part of installation:
1. Dedicated Project Management: A dedicated project manager will spearhead project execution and permitting processes.
2. Dedicated Quality Control: Ensuring construction quality throughout the project's duration will be the responsibility of a dedicated quality control team.
3. Lead Low Voltage Technician/Supervisor: A full-time lead low voltage technician/supervisor, accompanied by certified technicians as required, will oversee the technical aspects.
4. Provide all necessary personnel and tools required to install the Diester Access System provided by the National Park Service.
5. Travel Expenses: All travel-related expenses for project personnel are encompassed in the cost of the bid.
6. Operational Costs: Comprehensive coverage of water, power, and fuel requirements for project execution is included in the bid cost.
7. Permits, Fees, and Licenses: All essential permits, fees, and licenses are covered under this proposal as part of the bid cost.
NOTES AND EXCLUSIONS
· No materials are to be ordered or work to be performed without a customer PO or notice to proceed.
· All installs through existing or preplanned raceway are presumed to be of the size type and designed per capacity rating as well as free and clear of obstructions or breaks.
· All work to be performed during regular business hours (M-F 7AM – 5PM).
· All work will be performed in accordance with National, State, and local codes.