SOW - Garage doors.docx

DOCX document 653 KB Posted

Attached to
Replace Garage Doors
Solicitation number
70Z03926QCGA00032
Issued by

About this file

This is a Statement of Work (SOW) for the replacement of two garage doors at the Grounds Storage Building, Coast Guard Academy, New London, Connecticut. The contractor must furnish all labor, materials, equipment, tools, supervision, and transportation to remove the existing doors and install two new white flush-panel glazed garage doors measuring 10' 0" x 8' 1" with identical size and configuration to the originals. The scope includes removal and offsite disposal of existing doors, tracks, hardware, fasteners, and components; installation of new tracks, rollers, hinges, brackets, cables, torsion springs (Qty 2, 10K capacity), bearings, mounting hardware, weather seals, locks, and operating components; verification of existing framing and mounting surfaces; proper alignment, leveling, balancing, and lubrication of all moving parts; testing through multiple open and close cycles; and demonstration of proper operation to the Government representative upon completion. All work must comply with manufacturer installation instructions, applicable building codes, and OSHA safety requirements.

The contractor must be licensed by the State of Connecticut and shall designate a primary point of contact. Work shall be performed Monday through Friday, 7:30 a.m. to 4:00 p.m. local time, excluding Federal Holidays, at the Coast Guard Academy, 15 Mohegan Dr, New London, CT 06320. The Government will provide electricity (120vac @ 20 amps) and water; all other utilities and temporary connections are the contractor's responsibility. The Technical Advisor is Jason Askew (Jason.M.Askew@uscg.mil), who will conduct inspections and acceptance of work. Site visits are encouraged prior to bidding. The contractor must coordinate all work scheduling with the TA, maintain the site in a clean condition, remove all debris and equipment daily, and dispose of all removed materials offsite in compliance with applicable federal, state, and local regulations. Overnight parking is not authorized, and all work must minimize interference with Coast Guard operations.

View the file

Other files

File Type Posted
UPDATED_Combined Synopsis Solicitation_garage doors.docx DOCX document
Q and As garage door.docx DOCX document
Combined Synopsis Solicitation_garage doors.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work United States Coast Guard Academy New London, Connecticut Replace garage Doors

Part 1 – GENERAL

1.1 Project Description:

The contractor shall furnish all labor, material, equipment, and transportation, to replace garage doors at the Grounds Storage building, Coast Guard Academy, New London, Connecticut.

1.2 Contractor Qualifications and Personnel Requirements:

The contractor and contractor personnel performing work under this contractor shall be licensed by the State of Connecticut. The contractor shall provide a primary point of contact to include a phone number and email address.

1.3 Technical Advisor:

All work performed by the contractor is subject to inspection and acceptance by the Contracting Officer or the Technical Advisor during and after the completion of each visit. Unsatisfactory work shall be corrected at no additional cost to the government. The Technical Advisor for site visits and technical support is Jason Askew who may be reached at Jason.M.Askew@uscg.mil. TA are not authorized to issue changes to the contractor or resolve contractual disputes.

1.4 Location of Work:

All work shall be performed at the Coast Guard Academy, 15 Mohegan Dr, New London, CT 06320.

1.5 Site Visit:

Bidders are encouraged to visit the site to become familiar with existing conditions. Failure to do so will not relieve the successful bidder from furnishing all labor, materials, and equipment to satisfactorily complete performance of all required work. Bidders shall contact the primary TA to schedule a site visit.

1.6 Hours of Work:

All work shall be performed between the hours of 7:30 a.m. and 4:00 p.m. local time, Monday through Friday excluding Federal Holidays. Should the contractor desire to work outside these hours, the contractor shall submit a request to the primary TA no less than 48 hours in advance.

1.7 Scheduling of Work:

The contractor shall schedule all work with the TA.

1.8 Contractor’s Use of Premises:

The contractor will be working within an operational Coast Guard military installation. The contractor shall perform and conduct all work to minimize interference with Coast Guard operations.

1.9 Parking:

The contractor is authorized parking during the performance of work. Overnight parking is not authorized. Parking arrangements shall be made through the TA.

1.10 Inspection and Acceptance of Work:

The contractor shall keep the TA fully informed of contract operations throughout the performance of work. The contractor shall notify the TA upon completion of work. The contractor and TA shall perform a joint final inspection and the contractor shall correct any noted deficiencies.

1.11 Government Furnished Utilities:

The government will furnish electricity (120vac @ 20 amps), and water from existing building services will be provided at no cost to the contractor. Additional hookups or temporary connections shall be the responsibility of the contractor and shall be removed by the contractor upon completion of work.

1.12 Storage Facilities:

The government will not provide storage facilities.

1.13 Site Clean Up:

Upon completion of daily work, the contractor shall remove and properly dispose of site debris and rubbish. Contractor equipment shall be removed from Coast Guard Academy premises unless otherwise authorized by the TA.

1.14 Disposal of Removed Materials:

All materials and equipment removed by the contractor shall become the property of the contractor and shall be disposed of offsite in accordance with all applicable federal, state and local laws and regulations. Under no circumstances shall materials be placed in government-owned or leased refuse containers.

1.15 Smoking:

The contractor shall strictly adhere to the Coast Guard Academy’s smoking policy which limits smoking to 4 designated locations. The TA will provide smoking area locations upon request.

Part 2 – SCOPE OF WORK

2.1 General:

The Contractor shall furnish all labor, materials, equipment, tools, supervision, and transportation necessary to remove and replace two existing garage doors, including all associated tracks, hardware, and operating components, to restore full functionality.

The Contractor shall:

•Remove and dispose of the two existing garage doors, tracks, hardware, fasteners, and associated components.
•Furnish and install two new garage doors of the same size, configuration, and performance characteristics as the existing doors unless otherwise specified by the Government.
•Furnish and install all new tracks, rollers, hinges, brackets, cables, springs, bearings, mounting hardware, weather seals, and other components necessary for a complete and fully functional installation.
•Verify that the existing framing and mounting surfaces are suitable for installation and notify the COR of any deficiencies prior to proceeding with work.
•Properly align, level, and adjust the doors to ensure smooth operation, proper sealing, and correct balance.
•Lubricate all moving components in accordance with the manufacturer’s recommendations.
•Test each garage door through multiple open and close cycles to verify proper operation, alignment, safety features, and reliable performance.
•Remove all debris, packaging, and replaced materials from the site and leave the work area clean and safe.
•Demonstrate proper operation of both garage doors to the Government representative upon completion.

All work shall be performed in accordance with the manufacturer’s installation instructions, applicable building codes, OSHA safety requirements, and industry standards. Upon completion, both garage doors shall be fully operational, securely mounted, weather-tight, and free of defects.

New door required specs:

Door, 596, 10' 0" x 8' 1", White, Flush Panel, Glazed, LHR, Torsion (2) DOOR: 596, 10' 0" x 8' 1", Flush Panel, White, 4 Sect, SES, Std Btm Seal LITES: Third Section Only, 44" x 15" DSB, 1/8", , Full Row STRUTS: Standard, S1: NONE, S2: NONE, S3: 2" STRUT x 1, S4: NONE

LOCK: ISL, 1

TRK/HDW: Metal Step Plate/Lift Handle, Gray, 2", LHR: 9, Angle Out, Wood, 0.055 V.Trk, 0.055 H.Trk, 96.995 FTSC SPRING: Torsion, Qty: 2, Rear, 10K, Tubular, 2" x 0.219 x 24.25, 8.07 Turns, D400-96, 1/8" x 214", Bal Wt: 239.65 OPERATION: Push Up image4.jpeg image1.jpeg image2.jpeg image3.jpeg