This Statement of Work (SOW) details inspection requirements for rudder bearings on a Coast Guard vessel. The work involves disassembling and inspecting the port rudder upper carrier bearing and taking feeler gauge readings of the port and starboard rudder lower bearings while the vessel is waterborne. Key tasks include:
Specific inspection requirements include measuring carrier ring thickness, checking bearing housing depths, assessing axial play between bearing races, and taking precise measurements of various rudder stock and bearing components. Divers will take feeler gauge readings at four locations on the lower bearings. The period of performance is 14-15 August, with the work to be conducted at 4000 Coast Guard Blvd in Portsmouth, VA. Reference documents include Coast Guard drawings 901 WMEC 562-005 and 905 WMEC 562-003, and Technical Publication 2835, which provide detailed specifications for the rudder and bearing assemblies.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Smart Matrix SAP CM FFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work: Rudder Bearings, Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Coast Guard Yard (referred to as “the Contractor” herein) to disassemble and inspect the port rudder upper carrier bearing and take feeler gauge readings of the port and stbd rudder lower bearings while the vessel is waterborne.
1.2 Government-furnished property.
None
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 562-005, Rev K, A & B Class Rudder Stock and Steering Gear A & D
Coast Guard Drawing 905 WMEC 562-003, Rev B, GA of 11.10” Type ES Rudderstock Seal for WMEC Coast Guard 270’ BEAR Class Cutters
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 2835, Oct 1992, Rudderstock Seal Assembly Type ES
US-72047
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
Rudder tiller
Steering gear ram and rudder angle indicators
Bearing retainer (lower bearing)
Bearing grease
Grease tubing
3.2 Port rudder upper carrier bearing measurements. The Contractor must disassemble and obtain measurements of the various carrier bearing components to determine source of excessive axial play in the port rudder using Coast Guard Drawing 901 WMEC 562-005 as guidance. Submit a CFR.
CAUTION
Ship’s Force is responsible for ensuring that the vessel is trimmed such that the rudder seal is above the waterline.
3.2.1 Ensure that the rudder assembly is secured from the overhead to prevent any movement when the upper carrier bearing assembly, especially the carrier ring is disassembled. A chainfall is recommended so that the carrier ring can be unloaded for disassembly, and thrust readings can be taken for the carrier bearing.
3.2.2 Loosen the drive clamp ring of the rudder seal to release the preload on the rudder seal.
3.2.3 Disassemble and remove the upper bearing upper packing gland. Reassemble and reinstall upon completion of inspections and any corrective actions authorized.
FIGURE 1 – RUDDER UPPER CARRIER BEARING COMPONENTS
3.2.4 Prior to disassembly, inspect and note if there is a gap between the bearing retainer flange and the bearing housing. Disassemble and remove the bearing retainer, pc 31 in Figure 1. Measure and report the depth of the bearing retainer spigot (.500” +/- .010” dimension in Figure 1) to the nearest .001”.
3.2.5 Ensure bearing is fully seated in the housing and measure and report the depth from the top edge of the housing down to the bearing outer race, to the nearest .001” (should be between .485” and .505”). Do not include the gasket in the measurement. Note in the CFR the difference between the spigot depth and the bearing housing depth (negative value if it is in compression and positive value if there is a gap), and the thickness of the installed gasket.
CAUTION
Ensure rudder assembly is secured from the overhead prior to removing the carrier ring.
3.2.6 Disassemble and remove the carrier ring, pc 24 in Figure 1. Measure and report the thickness (2.000” +.000” - .001”) of the carrier ring, to the nearest .001”.
3.2.7 Measure the width of the carrier ring groove in the rudder stock (2.000” +.002” -.000”) to the nearest .001”
3.2.8 Measure from the bottom of the carrier ring groove in the rudder stock to the top of the bearing inner race, to the nearest .001” (should be between .009” - .012”).
3.2.9 Reinstall carrier ring and install one half of the bearing retainer to secure the bearing from lifting.
Using chain fall to lift and lower the rudder assembly, measure the axial play between the inner bearing race and the outer bearing race (.027” - .042”).
3.2.10 Reassemble the upper carrier bearing assembly. Recompress the rudder seal body and tighten the drive clamp in accordance with TP 2835 and Coast Guard Drawing 905 WMEC 562-003.
FIGURE 2 – RUDDER LOWER BEARING
3.3 Port and stbd lower bearing feeler gauge readings. For both the port and stbd rudders, the Contractor must have divers take feeler gauge readings of the clearance between the rudder stock and the Thordon bearing, pc 21 in Figure 2, at the lower end of the bearing, in four locations (fwd, aft, port and stbd).
Ensure that the readings are between the rudder stock and the bearing pc 21, and not between the rudder stock and the retainer pc 97. Remove the retainer, pc 97, if required. Submit a CFR. Note in the CFR how deep the feeler gauges were inserted.
4. PERIOD OF PERFORMANCE
14-15 August