This Statement of Work (SOW) details fire detection system inspection and testing for the USCGC BERTHOLF (WMSL 750), a United States Coast Guard vessel. The work will be performed at the pier on Spencer Road in Alameda, CA during a period of performance from 17 March 2025 to 13 May 2025. The contractor is required to conduct a comprehensive inspection and testing of the Siemens MXL Fire Alarm System, which includes control panels, repeater panels, intelligent detectors, photoelectric detectors, ionization detectors, thermal detectors, pull stations, bells, and loop isolation modules.
Key requirements include providing a Siemens-certified technical representative to assist with inspection, performing 100% testing of all field devices according to NFPA-72 standards, verifying signals to the Machinery Control and Monitoring System, renewing sealed lead acid batteries, and conducting pre- and post-repair operational tests. The solicitation (70Z08525Q203) is issued by the Department of Homeland Security US Coast Guard, with a local point of contact being LT Caleb Patton. The contractor must submit various compliance and inspection reports (CIR and CFR) throughout the process and ensure all work meets specified Coast Guard standard specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BERTHOLF FIRE DETECTION SYSTEM INSPECT AND TEST SAP 1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI apply to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Materials. The Contractor must obtain all of the materials required to complete this job with the exception of the Government-furnished Property shown in Paragraph 1.2 of Work Item.
3.3. Period of Performance. The period of performance window for this work starts on 17 March 2025 and ends on 13 May 2025.
3.4. Location. The Contractor must perform the work while the USCGC BERTHOLF (WMSL
750) is alongside the pier on Spencer Road, Alameda, CA 94501.
1. 43600_SSMJ_0524_(NSC 1-through 5 ONLY)_750
2. 43600_JSP_0721_(NSC 1-through 5 ONLY)_418
Fire Detection System, Inspect and Test
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect and test Fire Detection System listed in Table 1.
TABLE 1 – FIRE ALARM SYSTEM
MODEL NO./
MANUFACTURER
DESCRIPTION
COAST GUARD
DRAWING / TECH
PUB
MXL / Siemen Corp.
Fire Alarm System complete with MXL Control Panel, Repeater Panel, Fire Print Intelligent Detectors, Photoelectric Detectors, Ionization Detectors, Thermal Detectors, Pull Station, Bells, and Loop Isolation Modules. Profibus Module
*750-WMSL-436-011 /
7001 & 9770
*Applicable sheet are referenced as NSC 1-5 ONLY
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements
Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans
Coast Guard Drawing 750-WMSL-436-011, Rev E, Fire Detection Sys Deck Plan
(ASC436009)
Coast Guard Drawing 750-WMSL-436-013, Rev C, Fire Detection Sys Cable Running Sheets
(ASC436010)
Coast Guard Drawing 750-WMSL-436-014, Rev -, Fire Detection and Control System Schematic (ASC436028)
Coast Guard Publications
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Coast Guard Technical Publication (TP) 7001, SWSB 436, May 2007, Fire Detection System
Other References
National Fire Protection Association (NFPA) 72, 2019 Edition, National Fire Alarm and Signaling Code
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
• 3.3 System inspect and test.
3.1.2 Tech Rep. The Contractor must provide the services of a Qualified Tech Rep, who is familiar with the Siemens MXL Marine Smoke Detection System to accomplish the following tasks – on site:
• Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.
• Assist with proper repair methods, and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, and reassembly of the equipment/system.
3.1.2.1 Ensure that the Tech Rep is a Certified Representative of Siemens Building Technology Inc
3.1.2.2 Submit the Tech Rep’s name and résumé to the COR at the Arrival Conference.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
• Sheathing
• Bulkhead insulation
• Piping
• Electrical Cables
• Overhead Lights
3.1.5 Electrical work. The Contractor must accomplish all electrical work in accordance with SFLC Std Spec 3042, and test cables in accordance with SFLC Std Spec 3041.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.1.6 Operational test, initial. Prior to commencement of work, the Contractor, in the presence of a Coast Guard Inspector, must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR..
3.2 Fire detection system. The Fire Detection System components and zone loop wiring is shown on the Coast Drawing 750-WMSL-436-011. The Coast Drawings and Tech Pub referenced in the Para 2 provides information of the Fire Detection System on the Cutter.
3.2.1 Password protection. Fire alarm panel is password protected for software. Prior to start work on this item (i.e. Maximum 5 days prior to Tech Rep arrival) Tech Rep must request Password through Siemens HQ and Coast Guard Inspector.
3.3 Fire detection system inspect and test. The Contractor must perform inspection and test of the Fire Alarm System in accordance with NFPA-72 (i.e. National Fire Alarm and Signaling Code) and TP referenced in the Para 2. Annual Fire Alarm Testing requirement is listed in Table 1. The Contractor must perform 100 % test on all field devices (I.e., ALARM- INITIATING DEVICES AND CIRCUITS) listed in Table 1. Submit CIR.
TABLE 1 – NFPA-72 ANNUal fire alarm test
DESCRIPTION
Test and Visual Inspection of Panel Functionality
Test Panel Battery Charger
Battery Discharge Test
Test and Visual Inspection Horns, Strobes, Chimes and Bells
Test and Visual Inspection of Smoke Detectors
Test and Visual Inspection of Heat Detectors
Replace Sealed Lead Acid Battery every Five Years (Verify Expiration Date on the Battery and Submit a CFR)
Smoke and Heat Detectors : Replacement is recommended every 10 Years
3.3.1 The Contractor must renew seal lead acid battery mounted inside Fire Alarm Control Panel.
NOTE
The Contractor must perform only applicable test on the Fire Alarm System. Some of the test identified on the attached Data Sheet may not be required on installed Fire
Alarm System on the Cutter.
3.3.2 The Contractor must perform applicable test on Fire Alarm System with assistance from Tech Rep. Submit a CFR.
3.3.2.1 Perform applicable test as identified in Figure 1A-through Figure 1H (i.e. Annual Fire Alarm System Test and Inspection Records).
3.3.2.2 Verify signals from Fire Alarm Control Panel to Machinery Control and Monitoring System (i.e. MCMS) display console.
3.3.2.3 Certify that Fire Alarm System on the Cutter is operating properly (i.e. Figure 1H).
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.4 Operational test – post repairs. After completion of work, the Contractor must witness an operational test (by Coast Guard personnel) of all items or shipboard devices that have been disturbed, used, repaired, altered, or installed, to prove that they are in satisfactory operating condition. Submit a CFR.
3.5 Touch-up preservation. The Contractor must prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).
4. NOTES
USCG Local POC:
LT Caleb Patton 1 Eagle RD. BLDG 15
Alameda, CA 94501-5100
BERTHOLF Port Engineer
United States Coast Guard
C: 410-718-1196
W: 571-608-1102
File details come from the government source that posted it. Updated .