BERTHOLF FIRE DETECTION SYSTEM INSPECT AND TEST SAP 1.docx
DOCX document 818 KB Posted
- Attached to
- Fire Detection System Inspect and Test
- Solicitation number
- 70Z08525Q203
About this file
This document is a Standard Specification for Fire Detection System Inspection and Testing for the USCGC BERTHOLF (WMSL 750), a United States Coast Guard vessel. The work involves a comprehensive inspection and testing of the Siemens MXL Fire Alarm System, including 100% testing of all field devices such as smoke detectors, heat detectors, control panels, horns, strobes, and bells. The period of performance is from 24 February 2025 to 09 April 2025, with the work to be performed alongside the pier at 1 Eagle Road, Alameda, California.
Key requirements include providing a Qualified Technical Representative from Siemens Building Technology Inc who will assist with manufacturer-specific procedures, conducting annual fire alarm testing per NFPA-72 standards, renewing sealed lead acid batteries, verifying signals to the Machinery Control and Monitoring System, and performing initial and post-repair operational tests. The contractor must submit various documentation including Contractor Inspection Reports (CIR) and Contractor Furnished Reports (CFR), and must adhere to specific Coast Guard standard specifications and technical publications throughout the inspection and testing process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW Fire Detection SAP 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Requirements
1. SCOPE
Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans Coast Guard Drawing 750-WMSL-436-011, Rev E, Fire Detection Sys Deck Plan (ASC436009) Coast Guard Drawing 750-WMSL-436-013, Rev C, Fire Detection Sys Cable Running Sheets (ASC436010) Coast Guard Drawing 750-WMSL-436-014, Rev -, Fire Detection and Control System Schematic (ASC436028)
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Coast Guard Technical Publication (TP) 7001, SWSB 436, May 2007, Fire Detection System
OTHER REFERENCES
National Fire Protection Association (NFPA) 72, 2022 Edition, National Fire Alarm and Signaling Code
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI apply to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Materials. The Contractor must obtain all of the materials required to complete this job with the exception of the Government-furnished Property shown in Paragraph 1.2 of Work Item.
3.3. Period of Performance. The period of performance window for this work starts on 24 FEB 2025 and ends on 09 APR 2025.
3.4. Location. The Contractor must perform the work while the USCGC BERTHOLF (WMSL 750) is alongside the pier on 1 Eagle Road, Alameda Ca 94501-5100
43600_SSMJ_0524_(NSC 1-through 5 ONLY)_750 43600_JSP_0721_(NSC 1-through 5 ONLY)_418
1. Fire Detection System, Inspect and Test
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspect and test Fire Detection System listed in Table 1.
TABLE 1 – FIRE ALARM SYSTEM
| MODEL NO./ MANUFACTURER |
| DESCRIPTION |
| COAST GUARD DRAWING / TECH PUB |
| MXL / Siemen Corp. |
| Fire Alarm System complete with MXL Control Panel, Repeater Panel, Fire Print Intelligent Detectors, Photoelectric Detectors, Ionization Detectors, Thermal Detectors, Pull Station, Bells, and Loop Isolation Modules. Profibus Module |
| *750-WMSL-436-011 / 7001 & 9770 |
*Applicable sheet are referenced as NSC 1-5 ONLY
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans Coast Guard Drawing 750-WMSL-436-011, Rev E, Fire Detection Sys Deck Plan (ASC436009) Coast Guard Drawing 750-WMSL-436-013, Rev C, Fire Detection Sys Cable Running Sheets (ASC436010) Coast Guard Drawing 750-WMSL-436-014, Rev -, Fire Detection and Control System Schematic (ASC436028) Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Coast Guard Technical Publication (TP) 7001, SWSB 436, May 2007, Fire Detection System Other References National Fire Protection Association (NFPA) 72, 2019 Edition, National Fire Alarm and Signaling Code
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
· 3.3 System inspect and test.
3.1.2 Tech Rep. The Contractor must provide the services of a Qualified Tech Rep, who is familiar with the Siemens MXL Marine Smoke Detection System to accomplish the following tasks – on site:
· Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.
· Assist with proper repair methods, and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, and reassembly of the equipment/system.
3.1.2.1 Ensure that the Tech Rep is a Certified Representative of Siemens Building Technology Inc
3.1.2.2 Submit the Tech Rep’s name and résumé to the COR at the Arrival Conference.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
· Sheathing
· Bulkhead insulation
· Piping
· Electrical Cables
· Overhead Lights
3.1.5 Electrical work. The Contractor must accomplish all electrical work in accordance with SFLC Std Spec 3042, and test cables in accordance with SFLC Std Spec 3041.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.1.6 Operational test, initial. Prior to commencement of work, the Contractor, in the presence of a Coast Guard Inspector, must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR..
3.2 Fire detection system. The Fire Detection System components and zone loop wiring is shown on the Coast Drawing 750-WMSL-436-011. The Coast Drawings and Tech Pub referenced in the Para 2 provides information of the Fire Detection System on the Cutter.
3.2.1 Password protection. Fire alarm panel is password protected for software. Prior to start work on this item (i.e. Maximum 5 days prior to Tech Rep arrival) Tech Rep must request Password through Siemens HQ and Coast Guard Inspector.
3.3 Fire detection system inspect and test. The Contractor must perform inspection and test of the Fire Alarm System in accordance with NFPA-72 (i.e. National Fire Alarm and Signaling Code) and TP referenced in the Para 2. Annual Fire Alarm Testing requirement is listed in Table 1. The Contractor must perform 100 % test on all field devices (I.e., ALARM-INITIATING DEVICES AND CIRCUITS) listed in Table 1. Submit CIR.
TABLE 1 – NFPA-72 ANNUAl fire alarm test
DESCRIPTION
Test and Visual Inspection of Panel Functionality
Test Panel Battery Charger
Battery Discharge Test
Test and Visual Inspection Horns, Strobes, Chimes and Bells
Test and Visual Inspection of Smoke Detectors
Test and Visual Inspection of Heat Detectors
Replace Sealed Lead Acid Battery every Five Years (Verify Expiration Date on the Battery and Submit a CFR)
Smoke and Heat Detectors : Replacement is recommended every 10 Years
3.3.1 The Contractor must renew seal lead acid battery mounted inside Fire Alarm Control Panel.
NOTE
The Contractor must perform only applicable test on the Fire Alarm System. Some of the test identified on the attached Data Sheet may not be required on installed Fire Alarm System on the Cutter.
3.3.2 The Contractor must perform applicable test on Fire Alarm System with assistance from Tech Rep. Submit a CFR.
3.3.2.1 Perform applicable test as identified in Figure 1A-through Figure 1H (i.e. Annual Fire Alarm System Test and Inspection Records).
3.3.2.2 Verify signals from Fire Alarm Control Panel to Machinery Control and Monitoring System (i.e. MCMS) display console.
3.3.2.3 Certify that Fire Alarm System on the Cutter is operating properly (i.e. Figure 1H).
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.4 Operational test – post repairs. After completion of work, the Contractor must witness an operational test (by Coast Guard personnel) of all items or shipboard devices that have been disturbed, used, repaired, altered, or installed, to prove that they are in satisfactory operating condition. Submit a CFR.
3.5 Touch-up preservation. The Contractor must prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).
4. NOTES
Figure 1A: ANNUAL FIRE ALARM SYSTEM TEST AND INSPECTION RECORDS
Figure 1B: ANNUAL FIRE ALARM SYSTEM TEST AND INSPECTION RECORDS
Figure 1C: ANNUAL FIRE ALARM SYSTEM TEST AND INSPECTION RECORDS
Figure 1d: ANNUAL FIRE ALARM SYSTEM TEST AND INSPECTION RECORDS
Figure 1E: ANNUAL FIRE ALARM SYSTEM TEST AND INSPECTION RECORDS
Figure 1F: ANNUAL FIRE ALARM SYSTEM TEST AND INSPECTION RECORDS
Figure 1G: ANNUAL FIRE ALARM SYSTEM TEST AND INSPECTION RECORDS
Figure 1H: ANNUAL FIRE ALARM SYSTEM TEST AND INSPECTION RECORDS image6.png image7.png image8.png image1.png image2.png image3.png image4.png image5.png
File details come from the government source that posted it. Updated .